Robertson County: Our Land, Our Lives (RCOLOL) And Roy Henrichson v. Texas Commission on Environmental Quality and Oak Grove Management Company, LLC

Court of Appeals of Texas·Decided July 17, 2014·No. 03-12-00801-CV·Published

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN

ON MOTION FOR REHEARING

NO. 03-12-00801-CV

Robertson County: Our Land, Our Lives (RCOLOL); and Roy Henrichson, Appellants

v.

Texas Commission on Environmental Quality and Oak Grove Management Company, LLC, Appellees

FROM THE DISTRICT COURT OF TRAVIS COUNTY, 261ST JUDICIAL DISTRICT NO. D-1-GN-10-003925, HONORABLE TIM SULAK, JUDGE PRESIDING

MEMORANDUM OPINION

We withdraw our opinion and judgment dated June 6, 2014, and substitute the

following in their place. We deny the motion for rehearing filed by appellant, Robertson County:

Our Land, Our Lives.

This is an administrative appeal challenging a Texas Commission on Environmental

Quality (TCEQ) final order granting a permit amendment to appellee Oak Grove Management

Company, LLC. For reasons we explain below, we will affirm the district court’s judgment and

TCEQ’s decision.

BACKGROUND

Oak Grove Management Company operates the Oak Grove Steam Electric Station

in Robertson County, Texas. As its name suggests, Oak Grove Steam Electric Station (OGSES) is a facility that generates electricity by producing steam to drive a turbine, which in turn powers

an electric generator. The steam is generated from water heated by the combustion of lignite.

Oak Grove operates OGSES under various environmental permits, including a permit from TCEQ

to dispose of wastewater created as a byproduct of the electricity-generation process. In 2007,

Oak Grove submitted an application to TCEQ to renew and amend OGSES’s wastewater discharge

permit to allow it to change the outfall1 location and volume of its wastewater discharge.2 This

permit application and the resulting administrative process gave rise to this appeal. Two specific

categories of OGSES’s wastewater are relevant to our disposition of appellants’ issues and, thus,

merit further explanation.

OGSES wastewater

The first category of wastewater is a byproduct of OGSES’s steam-generating

process. After the steam produced by the boiler has passed through the turbines, it is condensed

into water and recycled to the boilers to make more steam. That cooling is accomplished using a

condenser and large quantities of cool water drawn from the adjacent Twin Oak Reservoir, which

is a privately owned “industrial cooling impoundment” specifically constructed to provide cooling

1 An “outfall” is the “point or location where waterborne waste is discharged” into or near water. See 30 Tex. Admin. Code § 305.2(25) (TCEQ, Definitions) (defining “outfall” in context of consolidated permits). 2 OGSES has been permitted to discharge wastewater since 1976. Its first wastewater- discharge permit was issued by the State of Texas. Then, following the enactment of the National Pollutant Discharge Elimination System program (NPDES) in the Clean Water Act, OGSES obtained a federal wastewater permit from the EPA in 1983. See 33 U.S.C. §§ 1251 et seq. (CWA); id. at § 1342 (NPDES). After 1998, when the EPA transferred NPDES permitting authority to the state, OGSES’s permit was issued by TCEQ. For convenience, we will refer to this permit as OGSES’s “original” permit.

2 water to OGSES.3 Billions of gallons of cool water are continuously pulled from the reservoir,

treated with small amounts of chlorine and dispersant/scale inhibitor, and then pumped into a

network of tubes running through the condenser where the “used” steam is collected. The cooling

water, which does not come into direct contact with the steam, absorbs the steam’s heat through the

pipes, condensing the steam into water to be reused in the boilers. The then-warmer reservoir water,

called “once-through cooling water,”4 is discharged first into the “Primary Discharge Canal” and

then ultimately into the reservoir through “external Outfall 001.”

The second type of wastewater, also a byproduct of the steam-generation process,

is created in connection with the lignite fuel, used to run the two steam boilers, that is stored on

OGSES’s grounds. Storm water that comes into contact with the stored lignite is collected in a lined

storage pond—the “Lignite Retention Pond”—designed to hold the amount of storm water that

would run off from approximately 87 acres following a 10-year, 24-hour storm event. Ultimately,

some of the wastewater stored in the lignite retention pond is, like the cooling water described above,

discharged into the adjacent Twin Oak Reservoir. Under OGSES’s original permit, however, the

discharge from the lignite retention pond flowed into a drainage ditch and then into the reservoir

through “external Outfall 002.”

3 See 30 Tex. Admin. Code § 307.3(31) (TCEQ, Texas Surface Water Quality Standards) (defining “industrial cooling impoundment”). As will be discussed in more detail below, the Twin Oak Reservoir is periodically refilled with water drawn from the nearby Lake Limestone. This “make-up” water is pumped from Lake Limestone and transported to Twin Oak Reservoir through an eleven-mile pipeline. 4 See id. § 210.52(15) (TCEQ, Definitions) (in context of industrial reclaimed water, defining “once-through cooling water” as “water passed through main cooling condensers in one or two passes for the purpose of removing waste heat”).

3 2007 permit application

In its 2007 permit application to TCEQ, Oak Grove sought one administrative and

one technical change to OGSES’s original permit. Administratively, Oak Grove sought to renumber

OGSES’s permitted outfalls and reroute certain already-permitted wastewater streams without

changing the overall quality or quantity of the discharge. Under the original permit, each wastewater

stream from the facility had its own designated outfall, but all streams ultimately discharged into

the Twin Oak Reservoir. Under the requested modifications, most of OGSES’s wastewater streams,

including the once-through cooling water and, intermittently, some of the coal-pile runoff,5 would

discharge into the Primary Discharge Canal and then into the Twin Oak Reservoir at Outfall 001.

The coal-pile runoff that did not discharge at external Outfall 001, would continue to discharge into

the reservoir at Outfall 002, as it did under OGSES’s original permit.6

Technically, Oak Grove sought to increase the allowable maximum daily volume of

effluent discharged at Outfall 001 from 1.47 billion to 1.61 billion gallons per day. According to

Oak Grove, this volume change was necessary to correct for the fact that the prior discharge limit

5 According to TCEQ’s order, the new permit authorized an additional internal outfall to discharge coal-pile runoff from the lignite storage area to the discharge canal and then, ultimately, to the reservoir through Outfall 001: “Pursuant to the amendment application, Oak Grove seeks a new outfall, Outfall 201, discharging in the Primary Discharge Canal from the Lignite Retention Pond in lieu of or in addition to using Outfall 002.” 6 Under the original permit, Oak Grove was authorized to discharge “coal pile runoff and storm water from the lignite/limestone storage area.” (Footnotes omitted.) The new permit authorizes discharge of “coal pile runoff, low volume waste, and storm water from the lignite/limestone storage area.” (Footnotes omitted.) RCOLOL argues in its motion for rehearing that the addition of low-volume waste to the permit is a significant change in the permitted discharge. We disagree.

Free access — add to your briefcase to read the full text and ask questions with AI

Robertson County: Our Land, Our Lives (RCOLOL) And Roy Henrichson v. Texas Commission on Environmental Quality and Oak Grove Management Company, LLC, (Tex. Ct. App. 2014).

Robertson County: Our Land, Our Lives (RCOLOL) And Roy Henrichson v. Texas Commission on Environmental Quality and Oak Grove Management Company, LLC (Robertson County: Our Land, Our Lives (RCOLOL) And Roy Henrichson v. Texas Commission on Environmental Quality and Oak Grove Management Company, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Pierce v. Underwood
487 U.S. 552 (Supreme Court, 1988)
City of El Paso v. Public Utility Commission
883 S.W.2d 179 (Texas Supreme Court, 1994)
Lauderdale v. Texas Department of Agriculture
923 S.W.2d 834 (Court of Appeals of Texas, 1996)
Southwestern Public Service Co. v. Public Utility Commission of Texas
962 S.W.2d 207 (Court of Appeals of Texas, 1998)
RAILROAD COM'N v. Pend Oreille Oil & Gas Co., Inc.
817 S.W.2d 36 (Texas Supreme Court, 1991)