Richard Tominsky v. Town of Ogunquit et al.

2024 ME 30
CourtSupreme Judicial Court of Maine
DecidedMay 23, 2023
DocketYor-22-206
StatusPublished
Cited by1 cases

This text of 2024 ME 30 (Richard Tominsky v. Town of Ogunquit et al.) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Richard Tominsky v. Town of Ogunquit et al., 2024 ME 30 (Me. 2023).

Opinion

MAINE SUPREME JUDICIAL COURT Reporter of Decisions Decision: 2023 ME 30 Docket: Yor-22-206 Argued: January 12, 2023 Decided: May 23, 2023

Panel: STANFILL, C.J., and MEAD, JABAR, HORTON, CONNORS, and LAWRENCE, JJ.

RICHARD TOMINSKY

v.

TOWN OF OGUNQUIT et al.

CONNORS, J.

[¶1] This is an appeal brought by Richard Tominsky pursuant to M.R.

Civ. P. 80B challenging the issuance of building permits by the Town of

Ogunquit’s code enforcement officer (CEO) to 477 Shore Road LLC. Because the

Town’s Board of Appeals erred in concluding that good cause existed for

Tominsky’s untimely appeal, its decision denying Tominsky’s administrative

appeal on the merits must be vacated and his appeal to the Superior Court must

be dismissed. In so ruling, we resolve thorny questions regarding the interface

among standing requirements, M.R. Civ. P. 80B, and M.R. App. P. 2C(a)(1).

I. BACKGROUND

[¶2] The LLC owns a parcel of property located at 477 Shore Road in

Ogunquit. Between December 2020 and January 2021, the CEO issued six 2

building permits to the LLC for construction relating to six single-family

dwelling units. The permits allowed for renovations and width and height

changes to four existing units and the demolition and rebuild of a “barn” into

two separate units.

[¶3] Tominsky owns property abutting the LLC’s parcel. When the

permits were issued, Tominsky was living in Florida; he only learned of the

project when he returned to Ogunquit in May 2021. Tominsky’s counsel

contacted the CEO on May 27, 2021, requesting information about the project

but did not receive a response.

[¶4] In June 2021, having not received a response from the CEO,

Tominsky filed a complaint in the Superior Court requesting an injunction, a

writ of mandamus, and a declaratory judgment against the Town, the CEO, and

the LLC. That matter was dismissed in early August 2021 because of

Tominsky’s failure to exhaust his administrative remedies. On

August 8, 2021—roughly seven months after the CEO’s issuance of the final

building permit and three months after Tominsky learned of the project—

Tominsky filed an administrative appeal with the Board requesting that it

overturn the CEO’s issuance of the permits. 3

[¶5] The Board held a hearing on Tominsky’s appeal on

September 9, 2021, and, as a threshold matter, debated whether it could hear

Tominsky’s appeal given its untimeliness. The Ordinance provides that once

the CEO has “render[ed] a written decision to a party, any aggrieved party may

file an administrative . . . appeal within 30 calendar days of the date of the

official, written decision.” Ogunquit, Me., Zoning Ordinance § 225-5.3.A

(Apr. 1, 2009). The Board may “grant exceptions to this 30-day rule” but “only

where, in its sole and exclusive judgment, extraordinary circumstances have

been shown which would result in a flagrant miscarriage of justice unless the

said 30-day time period is extended.” Id. The Board referred to this language

as a “good cause” exception.

[¶6] After debate, the Board unanimously agreed to apply the exception

to hear Tominsky’s appeal on the merits.1 Its decision “was based, in part, on

[Tominsky’s counsel’s] assertion that he received no response from the [CEO]

to his May 27, 2021 request for information; and by the delay caused by . . .

1 The LLC filed an appeal pursuant to M.R. Civ. P. 80B challenging the Board’s granting of the good

cause exception. The Superior Court (York County, Mulhern, J.) denied the appeal, and the LLC then appealed to us. Simultaneously with this decision, we are vacating the Superior Court’s judgment with instructions to dismiss the appeal, 477 Shore Road LLC v. Town of Ogunquit, Mem-23-61 (May 23, 2023), because, as discussed below, see infra ¶¶ 16-20, the LLC lacks standing to challenge the Town’s decision in a separate appeal. 4

Tominsky’s case in [the] Superior Court which he asserted he was forced to do

because of the Town’s lack of response.”

[¶7] In the same hearing, the Board addressed the merits of Tominsky’s

appeal. Tominsky raised multiple arguments, focusing primarily on the manner

in which the permits were issued and whether the sections in the Ordinance

concerning nonconformities were applicable. The CEO responded to each of

Tominsky’s arguments. The LLC was also permitted to address the Board and

asserted, inter alia, that the Board could still decline to grant the good cause

exception. Ultimately, the Board voted 4-1 to deny Tominsky’s appeal on the

merits and issued its written decision shortly thereafter.

[¶8] Tominsky timely appealed to the Superior Court (Tominsky I).

See Ogunquit, Me., Zoning Ordinance § 225-5.3.K (Apr. 1, 2009); 30-A M.R.S.

§ 2691(3)(G) (2023). His complaint contained multiple counts and named the

Town, the Board, the CEO, and the LLC as defendants. On a motion to dismiss

filed by all named defendants, the court (York County, Mulhern, J.) dismissed all

but one count and treated the remaining count as an appeal pursuant to

Rule 80B. It also dismissed Tominsky’s claims against the Board and the CEO

and ordered that the LLC remain as a party in interest. 5

[¶9] While Tominsky I was pending, the CEO issued a certificate of

occupancy for one of the dwelling units. Tominsky appealed the issuance of the

certificate to the Board. At a hearing held in December 2021, the Board had a

“lengthy discussion regarding whether it had jurisdiction to hear the appeal, in

light of the fact that it recently heard an appeal by the same appellant of the

same building permit.” Citing Salisbury v. Town of Bar Harbor, 2002 ME 13,

¶ 14, 788 A.2d 598, the Board unanimously voted not to hear the appeal.

[¶10] Tominsky then filed a second complaint containing multiple

counts against the Town and the LLC (Tominsky II). The Town moved to dismiss

the complaint pursuant to M.R. Civ. P. 12(b)(6), arguing that the action was an

attempt to litigate the underlying building permits in violation of Salisbury. The

LLC joined the Town’s motion.

[¶11] In June 2022, the court denied Tominsky’s appeal in Tominsky I

and dismissed his appeal in Tominsky II. Tominsky timely appealed both

decisions, and we consolidated the two appeals for our review.

II. DISCUSSION

A. Although the complaints in Tominsky I and Tominsky II contain multiple counts, they each assert only an appeal pursuant to Rule 80B.

[¶12] The complaints in both actions originally contained multiple 6

counts.2 As noted above, the Superior Court granted a motion to dismiss

various counts in Tominsky I and treated the remaining count as an appeal

pursuant to Rule 80B. In Tominsky II, the Superior Court disposed of all four

counts in one order.

[¶13] It is unclear whether in the appeals to us Tominsky seeks to

challenge the rejection of his complaints as containing anything but Rule 80B

appeals. In any event, the exclusive avenue to challenge a municipality’s

adjudicative decision is a Rule 80B appeal unless that avenue is somehow

inadequate or a statute provides otherwise. See Cayer v. Town of Madawaska,

2016 ME 143, ¶ 24, 148 A.3d 707; Fisher v. Dame, 433 A.2d 366, 372 (Me. 1981).

Here, the only relief Tominsky seeks is that obtainable under Rule 80B. In

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chris Calnan v. Sam Hurley
2024 ME 30 (Supreme Judicial Court of Maine, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
2024 ME 30, Counsel Stack Legal Research, https://law.counselstack.com/opinion/richard-tominsky-v-town-of-ogunquit-et-al-me-2023.