Rheiner v. Varner

627 S.W.2d 459, 1981 Tex. App. LEXIS 4415
CourtCourt of Appeals of Texas
DecidedNovember 30, 1981
Docket1403
StatusPublished
Cited by11 cases

This text of 627 S.W.2d 459 (Rheiner v. Varner) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rheiner v. Varner, 627 S.W.2d 459, 1981 Tex. App. LEXIS 4415 (Tex. Ct. App. 1981).

Opinion

SUMMERS, Chief Justice.

The genesis of this lawsuit was the construction of a shopping center in Hays County, Texas. The owners of the center, W. C. Carson, Ronald 0. Wilson, Frank Corte, and their corporation, San Marcos North Diversified, Inc., entered into a construction contract with Dan J. Rheiner, d/b/a D. J. Rheiner Construction Co. (general contractor). The general contractor entered into subcontracts with Hugh Var-ner (Varner) for the underground utility work and with Marshall Construction Co. (Marshall) for site work and asphalt paving.

After completion of that phase of the project involving those subcontractors named above, Varner instituted suit against the general contractor for $12,300, reprer senting the balance due under his contradi and for $14,100 as payment for “extras” to the contract. The general contractor im-pleaded the owners claiming that Varner’s extra work was authorized and directed by the owners, and, if Varner recovered from the general contractor for such extras, then the owners were liable to the general contractor for that amount. The owners subsequently counterclaimed against the general contractor and its bonding company, American States Insurance Co., alleging that the work done by subcontractors Var-ner and Marshall was defective; that the owners were damaged by such defective work in the amount of $71,475; and that the general contractor was liable for such damage. The general contractor then brought a third party action against subcontractor Marshall for an offset in the event the asphalt and site work was found to be defective. The general contractor also counterclaimed against Varner for an offset should Varner’s work be found to be defective. Marshall responded to the general contractor’s third party action against him with his own claim for extras. Since the owners had heretofore denied that they authorized the two subcontractors to perform any extra work, alleging that the authorization, if any, came from the architect Joseph Hans and was his responsibility, the general contractor brought a third party action against the architect for indemnity. A claim of usury was also asserted against Varner by both the general contractor and the owners. Finally, Varner brought an action against the owners to recover the money owed him in the event the general contractor was found not to be liable.

Against this background, trial was had to the court below without the aid .of a jury. The trial court held that subcontractor Var-ner was entitled to recover $23,105.79, together with attorney’s fees and interest from the general contractor and $5,225 plus *462 interest from the owners. Judgment was entered for subcontractor Marshall that he recover $22,045.53, together with attorney’s fees and interest from the general contractor. The owners were given judgment against the general contractor and its bonding company 1 for $42,180 as damages for defective work, together with attorney’s fees and interest. The owners were also allowed to collect the $5,225 they owed Var-ner from the general contractor and its bonding company. A take-nothing judgment was rendered as to all claims asserted against the architect, and all costs were assessed against the general contractor. From this judgment only the general contractor and its bonding company appeal.

We reverse and render in part, modify and, as modified, affirm.

Appellants (hereafter referred to as the general contractor) predicate their appeal on six points of error. The first point attacks the trial court’s mathematical computation of the award granted Varner. Specifically, the general contractor claims that the $23,105.79 awarded Varner included $7,000 in attorney’s fees, yet the trial court in its judgment awarded Varner another $7,000 for attorney’s fees. Varner agrees with the general contractor on this point, and our review of the record convinces us that such an error was made. We sustain point of error one. Accordingly, we order that the judgment against the general contractor as it relates to Varner’s claims be reduced to $16,105.79, together with attorney’s fees in the amount of $7,000.

In points 2, 3, 5 and 6 the general contractor does not attack the awards made by the trial court, but does attack the trial court’s judgment pertaining to who should pay the awards. It is significant to point out here that the general contractor admitted in its brief that no attack was being made on the trial court’s findings; that there was evidence to support such findings. Apparently, then, the general contractor is claiming on appeal that the findings made by the court below do not support the judgment. The rule is that where the trial court’s findings of fact are supported by the evidence, it is the duty of the appellate court to uphold the judgment on any theory of law applicable to the case, regardless of whether the trial court gives the correct legal reason for the judgment. Gulf Land Co. v. Atlantic Refining Co., 134 Tex. 59, 131 S.W.2d 73, 84 (1939); Wirth Ltd. v. Panhandle Pipe and Steel, 580 S.W.2d 58, 62 (Tex.Civ.App.—Tyler 1979, no writ).

The question for us on appeal is whether the findings of the trial court support the judgment. If they do, then we must affirm; if they do not, we are obligated to reverse the trial court’s judgment.

Turning now to the second assignment, the general contractor claims it was error for the trial court to allow the owners to recover, by way of indemnification, from the general contractor for the extras performed by Varner. In other words, Varner was found to have performed services that were not contemplated under the original contract. These extras consisted of (1) boring under a state highway, instead of performing an open cut as the original plans specified, at a cost of $6,000; (2) installing five extra water service lines at a cost of $2,225; and (3) obtaining a permit to bore under a railroad track at a cost of $775, making the total amount of extras $9,000. Of this total amount, the court found that the general contractor was to pay Varner for the railroad permit and one half the cost of boring under the highway. The owners were to pay for the extra water lines and one half of the boring costs. The judgment of the trial court further provided that the owners would be indemnified by the general contractor and its bonding company for the $5,225 paid to Varner. As the general contractor points out, the net result of the trial court’s judgment is that the general contractor is liable for all the extras performed by Varner.

*463 Since there was no privity of contract between the owners and the subcontractor Varner, Varner’s award against the owners must have been based on quantum meruit. Black Lake Pipe Line Co. v. Union Const Co., 538 S.W.2d 80, 91 (Tex.1976).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seth v. Seth
694 S.W.2d 459 (Court of Appeals of Texas, 1985)
Foreman v. Graham
693 S.W.2d 774 (Court of Appeals of Texas, 1985)
Muhlbauer v. Muhlbauer
686 S.W.2d 366 (Court of Appeals of Texas, 1985)
J.M.R. v. A.M.
683 S.W.2d 552 (Court of Appeals of Texas, 1985)
B.A.L. v. Edna Gladney Home
677 S.W.2d 826 (Court of Appeals of Texas, 1984)
Austin Elcon Corp. v. Avco Corp.
590 F. Supp. 507 (W.D. Texas, 1984)
Ellis Oil Co. v. Union Oil Co. of California
661 S.W.2d 342 (Court of Appeals of Texas, 1983)
Concrete Construction Supply, Inc. v. M. F. C., Inc.
636 S.W.2d 475 (Court of Appeals of Texas, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
627 S.W.2d 459, 1981 Tex. App. LEXIS 4415, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rheiner-v-varner-texapp-1981.