Concrete Construction Supply, Inc. v. M. F. C., Inc.

636 S.W.2d 475, 1982 Tex. App. LEXIS 4844
CourtCourt of Appeals of Texas
DecidedMay 21, 1982
Docket20958
StatusPublished
Cited by17 cases

This text of 636 S.W.2d 475 (Concrete Construction Supply, Inc. v. M. F. C., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Concrete Construction Supply, Inc. v. M. F. C., Inc., 636 S.W.2d 475, 1982 Tex. App. LEXIS 4844 (Tex. Ct. App. 1982).

Opinion

FISH, Justice.

In this usury case, suit was brought by Concrete Construction Supply, Inc., a supplier, to recover for materials sold on open account to M.F.C., Inc., a contractor. A short time later, M.F.C. instituted suit against Concrete to obtain usury penalties for interest charges on the same account. The two suits were consolidated for a non-jury trial. Judgment was rendered in favor of M.F.C. for $4,533.96 (three times the amount of usurious interest charged), plus attorney’s fees of $4000 for services in the trial court and additional amounts in the event of an appeal. The judgment also forfeited all principal, interest and other charges on Concrete’s open account in the amount of $10,593.60. We agree with the court’s assessment of penalties, but modify the judgment by limiting the recovery to the amount prayed for by M.F.C.

In considering the seven points of error advanced by Concrete, we must decide (1) whether, under the facts of this case, M.F.C. was an obligor; (2) whether federal law has pre-empted the Texas law of usury that would otherwise control this case; (3) what difference there is, if any, between the amount of interest Concrete charged and the amount of interest allowed by law; and (4) whether M.F.C.⅛ recovery is limited to the amount prayed for in its pleadings. After determination of these issues, all of Concrete’s other contentions are resolved by formulas set out in the applicable usury laws.

I. WAS M.F.C. AN OBLIGOR?

In its first point of error Concrete contends that M.F.C. could not have been an obligor entitled to recover usury penalties because M.F.C. denied owing any debt to *477 Concrete on the open account. Article 5069-1.06(1) of the Texas Revised Civil Statutes provides that:

“[A]ny person who contracts for, charges or receives interest which is greater than the amount authorized by this Subtitle, shall forfeit to the obligor three times the amount of usurious interest contracted for, charged or received. . .. ” (Vernon Supp. 1982) [emphasis added].

To recover under this statute, M.F.C. had to show that it was an obligor of Concrete. Patterson v. Neel, 610 S.W.2d 154,156 (Tex.Civ.App.—Houston [1st Dist.] 1980, no writ).

So long as one is an immediate party to the transaction, see Childs v. Taylor Cotton Oil Co., 612 S.W.2d 245, 251 (Tex.Civ.App.—Tyler 1981, writ ref’d n.r.e.), and there is a binding obligation existing between those immediate parties, an obligor is a person who pays, is charged, or has contracted to pay interest at a rate in excess of that allowed by law. Patterson v. Neel, supra, at 156. There is no doubt that M.F.C. was an immediate party to the transaction or that M.F.C. was “charged” interest. 1 Our question, then, is whether there was a binding obligation between the parties. Concrete contends that the following testimony by one of M.F.C.’s corporate officers conclusively established that there was no binding obligation:

ANSWER: Well, on two particular jobs when I was purchasing from Concrete Construction Supply at the time we had an agreement with the sales manager then that we would not have to pay them until we had received our money from the owners of the jobs at that time and the two particular jobs stick out in my mind.
* * * * * *
ANSWER: We had a financial arrangement and all of the jobs that we didn’t pay until we had received our money, but he expected me to pay the day that I received my funds, and that practice was basically followed throughout our business relationship.
QUESTION: Has that been true on every job that Concrete Construction supplied materials?
ANSWER: As far as I know, it has.
* * * * * *
QUESTION: So you did not consider MFC even indebted to Concrete Construction Supply until you received your money on a job, is that right?
ANSWER: I am not obligated to pay them until I receive my money on a job.
QUESTION: And when did this arrangement begin? When was the first time this happened?
ANSWER: Probably when we started doing business.
***** *
QUESTION: So, as far as you were concerned, if you did not collect any money from them, you would not have to pay Concrete Construction Supply, is that correct?
ANSWER: That is correct.

Notwithstanding this testimony, it was stipulated in open court, and thereby judicially admitted, that

“the Plaintiff, MFC, Inc. purchased goods from Concrete Construction Supply on an open account ... [and] that the net amount due under Concrete Constructions Supply’s statement of account to MFC, Inc. of September 24, 1980, in the principal amount owing for the cumulative invoices on that statement was $8,684.98.”

A fact judicially admitted does not require evidence; rather, it is established conclusively as a matter of law and precludes the *478 trial court from finding any facts to the contrary. See Gevinson v. Manhattan Construction Co. of Okl., 449 S.W.2d 458, 466 (Tex.1969); Hagar v. Williams, 593 S.W.2d 783, 787 (Tex.Civ.App.— Amarillo 1979, no writ); 1A Ray, Texas Practice, Law of Evidence § 1127 (3rd ed. 1980). Consequently, the stipulation that a sum was due and owing constituted M.F.C. an obligor as a matter of law.

II. IS M.F.C.’S USURY CLAIM PREEMPTED BY FEDERAL LAW?

In its sixth point of error, Concrete maintains that article 5069-1.03 of the Texas Revised Civil Statutes has been preempted in this case by Title 12, United States Code § 86(a). 2 Concrete reasons that because M.F.C.’s open account had not been paid in full, all transactions in the account, dating back to its inception on July 31, 1978 and continuing to the last transaction on July 26,1979, have been pre-empted by this federal statute. We do not agree. Without deciding what effect this statute might have had on those transactions if they had occurred after April 1, 1980 (the effective date of the statute), we hold that, because each item on the open account was a separate transaction between the parties,

*479 Watson v. Cargill, Inc., Nutrena Division, 573 S.W.2d 35, 39 (Tex.Civ.App.—Waco 1978, writ ref’d n.r.e.), and because all of M.F.C.’s obligations on the open account were incurred before April 1, 1980, the transactions in this case are governed by article 5069-1.03.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
636 S.W.2d 475, 1982 Tex. App. LEXIS 4844, Counsel Stack Legal Research, https://law.counselstack.com/opinion/concrete-construction-supply-inc-v-m-f-c-inc-texapp-1982.