R.G. Pope Construction Co. v. Guard Rail of Roanoke, Inc.

244 S.E.2d 774, 219 Va. 111, 1978 Va. LEXIS 167
CourtSupreme Court of Virginia
DecidedJune 9, 1978
DocketRecord 761655
StatusPublished
Cited by11 cases

This text of 244 S.E.2d 774 (R.G. Pope Construction Co. v. Guard Rail of Roanoke, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.G. Pope Construction Co. v. Guard Rail of Roanoke, Inc., 244 S.E.2d 774, 219 Va. 111, 1978 Va. LEXIS 167 (Va. 1978).

Opinion

COMPTON, J.,

delivered the opinion of the Court.

In this construction contract case, the dispute is between the general contractor on a highway project and the guardrail subcontractor. The controversy stems from the refusal of the subcontractor to perform its. agreement.

In June of 1971, plaintiffs R. G. Pope Construction Company, Inc. and Pope Paving Corporation (hereinafter sometimes collectively referred to as Pope) executed a written contract with the Commonwealth of Virginia, Department of Highways (hereinafter, Highway Department) for the construction of a 6.5-mile section of U. S. Route 58 in Russell County between Dickensonville and Hansonville. During the following month, Pope and defendant Guard Rail of Roanoke, Inc. signed a written subcontract in the amount of $103,086.85 calling for the defendant to furnish and install steel guardrail in connection with the project. The prime contract expressly stated that all the work on the project was to be completed by October 1,1973. The site was not ready for erection of all of the guardrail pursuant to the subcontract until July of 1974. As the result of Guard Rail’s refusal to perform at that time, due to a shortage of steel and increases in steel prices, Pope engaged another subcontractor to do the work, which commenced in August of 1974 at a cost of $132,071.90 more than the original subcontract price.

Subsequently in February of 1975, Pope proceeded by motion for judgment against Guard Rail and its surety, Fidelity & Deposit Company of Maryland, seeking damages against Guard Rail in the foregoing amount, and against the surety in the amount of its bond, for Guard Rail’s alleged breach of contract. Guard Rail thereafter *113 filed a counterclaim for $13,183.01 alleging lost profits as the result of an alleged breach of the subcontract by Pope.

After a jury trial lasting five and one-half days, the panel hung. The court below then discharged the jury and declared a mistrial. The respective parties thereafter renewed separate motions, earlier made during the course of the trial, to strike their adversary’s evidence, Rule 1:11, and Pope also filed a motion for a new trial. The trial court, following consideration of additional memoranda of law and further argument of counsel, denied Pope’s requests and granted the defendants’ motions. Judgment was accordingly entered in favor of Guard Rail and the surety on Pope’s original claim and in favor of Guard Rail against Pope in the amount sued for in the counterclaim. We granted Pope a writ of error to the August 1976 judgment order.

The documents comprising the agreement between Pope and the Highway Department included a proposal submitted by Pope in May of 1971, plans, and the Road and Bridge Specifications of the Highway Department contained in a 583-page manual. In the writings, Pope agreed to start work on the date specified in a Notice to Proceed and to complete all work in accordance with the plans and specifications “within the time limit set forth in the contract which is: October 1, 1973.” The documents provided that “[tjime is an essential element of the contract and it is important that the work be completed within the time specified.” Under such a “fixed calendar date” contract, according to the agreement, the prime contractor must “take into consideration normal conditions considered unfavorable for the prosecution of the work and place sufficient men and equipment on the project to complete the work in accordance with the time limit.” The contract also provided that extensions of time may be granted by the Highway Department “when a delay occurs due to unforeseen causes beyond the control of and without the fault or negligence of the Contractor.” Under the agreement, if the work was not completed within the time limits, the Highway Department had the option of either permitting the prime contractor to continue with the work, assessing liquidated damages for each day of additional time consumed, or, take the prosecution of the work out of the contractor’s hands, declaring him in default, and calling upon his surety for the satisfactory and expeditious completion of all work under the prime contract.

*114 The subcontract was embodied in a printed form provided by Pope to Guard Rail. The subcontractor agreed “to furnish all labor, materials, equipment, and services as may be necessary to complete items of work on [the] project” relating to installation of the guardrail. In addition, Guard Rail acknowledged that it had “examined all the project plans, specifications, and other prime contract documents” and agreed to “assume and fulfill” all of Pope’s obligations included in the prime contract, insofar as they applied to erection of guardrail. The subcontract further provided that Guard Rail would “prosecute the various portions of [its] work as directed by [Pope’s] superintendent in order to assure orderly completion of the whole project within the contract time limit.” The subcontract also required Guard Rail to “protect and maintain” its work until final acceptance by the Highway Department “or longer if so required by job specifications.”

In a written “certification” executed on behalf of Guard Rail in September of 1971, the subcontractor acknowledged that “all stipulations of the ‘Required Contract Provisions’ of the Prime Contract” had been “physically incorporated” into the subcontract.

According to the evidence, one of the last items of work to be performed on a highway project is the installation of guardrail. This is because installation must occur in a continuous sequence, not piecemeal, after the highway shoulders and surface are completed. Unless such construction is at this final stage, serious problems of placement and alignment of the guardrail arise. The components of the device include a post, which is set in the ground; a block, attached to the post; and the rail, affixed to the block.

The record shows that the Highway Department notified Pope to proceed with construction on June 28, 1971. In the spring of 1973, Guard Rail entered into a contract with Syro Steel Company of Girard, Ohio, for Syro to furnish the guardrail components to enable defendant to perform the Pope subcontract. The testimony showed that Syro was not a steel manufacturer, but a fabricator and supplier which maintained an inventory of raw materials. The fabrication is accomplished about four weeks prior to the time the customer needs the product; the material is then placed on a truck when the customer calls for it and shipped directly to the job site to arrive at a time just before the rails are to be erected. In this *115 instance, Syro, which had examined the relevant prime contract documents, calculated that Guard Rail would need its product in August of 1973. According to the record, installation of guardrail in this quantity takes about four to six weeks.

Knowing that the prime contract called for completion of the project by the fixed calendar date of October 1, 1973, Syro’s quotation to Guard Rail was based on a “locked in” price, provided delivery took place anytime from August of 1973 to “early November” of that year. Syro’s representative testified that if Guard Rail did not call for the material within that time period, a new contract at different prices would have to be negotiated between the supplier and the defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rastek Constr. & Dev. Corp. v. Gen. Land Commercial Real Estate Co.
806 S.E.2d 740 (Supreme Court of Virginia, 2017)
Payman v. St. Mary's Hospital, Inc.
72 Va. Cir. 582 (Wise & Norton County Circuit Court, 2004)
Jack Quinn's Norfolk v. Commonwealth Enterprises
57 Va. Cir. 396 (Virginia Circuit Court, 2002)
US EX REL. VIRG. BEACH MECH. v. SAMCO Const. Co.
39 F. Supp. 2d 661 (E.D. Virginia, 1999)
Foster v. Gates
38 Va. Cir. 5 (Northumberland County Circuit Court, 1995)
Carley Capital Group v. City of Newport News
709 F. Supp. 1387 (E.D. Virginia, 1989)
Pennsylvania Life Insurance v. Bumbrey
665 F. Supp. 1190 (E.D. Virginia, 1987)
Talbott v. Miller
350 S.E.2d 596 (Supreme Court of Virginia, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
244 S.E.2d 774, 219 Va. 111, 1978 Va. LEXIS 167, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rg-pope-construction-co-v-guard-rail-of-roanoke-inc-va-1978.