Tyger Construction Company Incorporated Fidelity and Deposit Company of Maryland v. Beer Precast Concrete Limited v. Skyline Crane Service, Inc., Third Party Tyger Construction Company Incorporated, and Fidelity and Deposit Company of Maryland v. Beer Precast Concrete Limited v. Skyline Crane Service, Inc., Third Party Fidelity and Deposit Company of Maryland, and Tyger Construction Company Incorporated v. Beer Precast Concrete Limited v. Skyline Crane Service, Inc., Third Party

896 F.2d 1367, 1990 U.S. App. LEXIS 2114
CourtCourt of Appeals for the Third Circuit
DecidedFebruary 13, 1990
Docket89-2934
StatusUnpublished

This text of 896 F.2d 1367 (Tyger Construction Company Incorporated Fidelity and Deposit Company of Maryland v. Beer Precast Concrete Limited v. Skyline Crane Service, Inc., Third Party Tyger Construction Company Incorporated, and Fidelity and Deposit Company of Maryland v. Beer Precast Concrete Limited v. Skyline Crane Service, Inc., Third Party Fidelity and Deposit Company of Maryland, and Tyger Construction Company Incorporated v. Beer Precast Concrete Limited v. Skyline Crane Service, Inc., Third Party) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tyger Construction Company Incorporated Fidelity and Deposit Company of Maryland v. Beer Precast Concrete Limited v. Skyline Crane Service, Inc., Third Party Tyger Construction Company Incorporated, and Fidelity and Deposit Company of Maryland v. Beer Precast Concrete Limited v. Skyline Crane Service, Inc., Third Party Fidelity and Deposit Company of Maryland, and Tyger Construction Company Incorporated v. Beer Precast Concrete Limited v. Skyline Crane Service, Inc., Third Party, 896 F.2d 1367, 1990 U.S. App. LEXIS 2114 (3d Cir. 1990).

Opinion

896 F.2d 1367
Unpublished Disposition

NOTICE: Fourth Circuit I.O.P. 36.6 states that citation of unpublished dispositions is disfavored except for establishing res judicata, estoppel, or the law of the case and requires service of copies of cited unpublished dispositions of the Fourth Circuit.
TYGER CONSTRUCTION COMPANY INCORPORATED; Fidelity and
Deposit Company of Maryland, Plaintiffs-Appellees,
v.
BEER PRECAST CONCRETE LIMITED, Defendant-Appellant,
v.
SKYLINE CRANE SERVICE, INC., Third Party Defendant.
TYGER CONSTRUCTION COMPANY INCORPORATED, Plaintiff-Appellant,
and
Fidelity and Deposit Company of Maryland, Plaintiff,
v.
BEER PRECAST CONCRETE LIMITED, Defendant-Appellee,
v.
SKYLINE CRANE SERVICE, INC., Third Party Defendant.
FIDELITY AND DEPOSIT COMPANY OF MARYLAND, Plaintiff-Appellant,
and
Tyger Construction Company Incorporated, Plaintiff,
v.
BEER PRECAST CONCRETE LIMITED, Defendant-Appellee,
v.
SKYLINE CRANE SERVICE, INC., Third Party Defendant.

Nos. 89-2934, 89-2935 and 89-2937.

United States Court of Appeals, Fourth Circuit.

Argued: Dec. 5, 1989.
Decided: Feb. 13, 1990.

John S. Morris, III (Thomas F. Farrell, II, McGuire, Woods, Battle & Boothe, on brief), for appellant.

Arthur Isaac Leaderman (Randall C. Allen, Smith, Pachter, McWhorter & D'Ambrosio, on brief), for appellees.

Before DONALD RUSSELL and CHAPMAN, Circuit Judges, and JAMES H. MICHAEL, Jr., United States District Judge for the Western District of Virginia, sitting by designation.

CHAPMAN, Circuit Judge:

These appeals raise several issues regarding the construction and performance of a contract between Tyger Construction Company, Inc. ("Tyger") and Beer Precast Concrete Ltd. ("Beer"). In Beer's claim against Tyger (C.A. No. 88-175), the district court held that Tyger wrongfully terminated the contract and awarded Beer damages. In Tyger's claim against Beer (C.A. No. 88-48), the district court held that Beer was responsible for damages resulting from its delays in performing under the contract. However, the court found that the modification of the contract agreed to by both parties was not the result of economic duress. After oral argument and a careful review of the briefs and record, we find no error in the district court's rulings and affirm.

* In furtherance of its contract with the County of Fairfax, Virginia ("County") for the construction of the Fairfax Adult Detention Center ("Project"), Tyger entered into a subcontract with Beer on February 1, 1984, whereby Beer agreed to fabricate, deliver and erect precast concrete panels and interior cell furniture for the fixed amount of $788,400, which was to be paid in installments before delivery. The contract required work to commence within three weeks of notice given by Tyger. On July 23, 1985, Beer and Skyline Crane Service ("Skyline") negotiated a contract under which Skyline agreed to perform Beer's contractual obligations to erect the precast panels and cell furniture for Tyger.

Because of a series of delays and postponements in the precast concrete commencement, Beer sent a letter to Tyger on February 1, 1985, demanding $159,159 in addition to the contract price before it would ship or erect the precast panels. Tyger disputes that these delays produced additional costs, asserts that it already had paid for and thus had title in the goods held by Beer, and argues that Beer threatened this postponement solely to obtain the additional money. In a letter dated June 28, 1985, Tyger told Beer that these actions constituted economic duress, but Tyger did not try to find another precast fabricator or pick up the precast itself. Consequently, Tyger and Beer agreed to Change Order 3, which was dated July 12, 1985, and which granted Beer the full $159,159 it had demanded.

The parties stipulated that, on March 21, 1985, Tyger instructed Beer to begin work on June 3, 1985. Also in March 1985, Beer informed Tyger that the building was inadequately prepared for panel installation because the dimensions of the concrete were incorrect and there was reinforcing steel ("rebar") in the pockets of the shearwall where the panels were to be connected. Although Tyger acknowledged its responsibility for these problems and promised to rectify them, the building was still not available for Beer's work as of July 1985.

Nevertheless, Tyger ordered Beer to proceed with its work by August 8, 1985. Notwithstanding the problems with the site, Beer began erection of the panels on August 8, 1985. The concrete and rebar problems led Beer to bear demurrage costs and caused Beer's subcontractor, Skyline, to incur idle time and resulted in Skyline walking off the job on three occasions in August, September, and November of 1985.

Beer substantially completed its work under the contract on January 10, 1986. However, Tyger contends that the project was greatly delayed by Beer's stoppages, that several of the panels furnished and installed by Beer were cracked, chipped and misaligned, and that it wrote Beer on January 10, 1986, to finish the remaining work. On February 24, 1986, Beer notified the County, but not Tyger, that it was suspending its contract guaranty, meaning that it had repudiated its obligation to repair or replace defective or damaged panels. On March 17, 1986, Tyger again wrote Beer outlining certain work to be corrected and completed and demanding that Beer respond within ten days showing its commitment to complete the subcontract work; otherwise, Tyger would consider Beer in default. When Beer failed to respond, Tyger terminated the contract on March 31, 1986, and completed the work.

This litigation began on January 21, 1987, when Beer filed a motion for judgment in the Circuit Court of Fairfax County, Virginia, against Tyger and Tyger's surety, Fidelity & Deposit Company of Maryland ("F & D"), seeking $345,766.27 in an unpaid contract balance and other damages resulting from Tyger's termination of the contract. Subsequently, Tyger removed the action to the United States District Court for the Eastern District of Virginia. Beer later joined Skyline as third-party defendant; Skyline, however, is not a party to this appeal.

Tyger filed a complaint against Beer seeking damages of $1,259,398 for delays caused by Beer, recovery of the $159,159 paid under economic duress, and damages for conversion of the withheld goods. The district court consolidated the two cases on June 9, 1988. After dismissing Tyger's conversion claim on summary judgment, the district court made findings of fact and conclusions of law.

In Case No. 88-175, the court awarded judgment to Beer in the amount of $108,445.76 against Tyger and F & D, finding that Tyger wrongfully terminated Beer by unilaterally imposing a condition in its letter of March 17, 1986.

In Case No. 88-48, the court initially awarded Tyger damages totaling $244,949.46, later increased to $250,607.46 because of a computation error. The court found that Beer was obligated to commence performance on June 3, 1985, and was responsible for damages resulting from the 66-day delay between June 3 and August 8, 1985, when Beer actually started work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jose R. Navato, M.D. v. Ivan W. Sletten, M.D.
560 F.2d 340 (Eighth Circuit, 1977)
Gloth v. Gloth
153 S.E. 879 (Supreme Court of Virginia, 1930)
R.G. Pope Construction Co. v. Guard Rail of Roanoke, Inc.
244 S.E.2d 774 (Supreme Court of Virginia, 1978)
Whitt v. Godwin
139 S.E.2d 841 (Supreme Court of Virginia, 1965)
Freedlander, Inc. v. NCNB National Bank of North Carolina
706 F. Supp. 1211 (E.D. Virginia, 1988)
Cities Service Helex, Inc. v. United States
543 F.2d 1306 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
896 F.2d 1367, 1990 U.S. App. LEXIS 2114, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tyger-construction-company-incorporated-fidelity-and-deposit-company-of-ca3-1990.