Remes v. Holland

382 N.W.2d 819, 147 Mich. App. 550
CourtMichigan Court of Appeals
DecidedDecember 16, 1985
DocketDocket 76728
StatusPublished
Cited by5 cases

This text of 382 N.W.2d 819 (Remes v. Holland) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Remes v. Holland, 382 N.W.2d 819, 147 Mich. App. 550 (Mich. Ct. App. 1985).

Opinion

V. J. Brennan, J.

Plaintiff, the trustee in bankruptcy for St. Clair Excavating Company (St. Clair), brought this action to recover monies which he alleged were owed to St. Clair pursuant to a contract entered into on June 15, 1981, by St. Clair and defendant, the City of Holland, a municipal corporation. On September 20, 1983, defendant filed a motion for accelerated judgment pursuant to GCR 1963, 116.1(5), asserting that plaintiffs claim was barred because of previous payment of the sum sought by plaintiff. Plaintiff responded by filing a motion for summary judgment pursuant to GCR 1963, 117.2(3), claiming that there was no genuine issue as to any material fact and that plaintiff was entitled to two specific sums of money. After a hearing held on the motions on December 5, 1983, the trial court took the matter under advisement. On January 25, 1984, the trial court granted defendant’s motion for accelerated judgment and denied plaintiffs motion for summary judgment. Plaintiff files this appeal as of right.

On June 15, 1981, St. Clair entered into a contract with the City of Holland under which it was to perform excavating work on Project S-264, a sanitary sewer project in the City of Holland. As required by statute, St. Clair and defendant executed a lien bond with the National Bonding and *553 Accident Insurance Company to guarantee payment of the subcontractors and materialmen on this public project. Work on the project commenced soon after the execution of the contract. We note that most of the facts set forth here are taken from the statements of fact contained in the parties’ briefs, as little relevant information can be gleaned from the record itself. We point out that St. Clair went into bankruptcy after the completion of the Holland project and that this action is being prosecuted by the trustee in bankruptcy.

Pursuant to the contract between St. Clair and the City of Holland, St. Clair could request partial payment as work on the project progressed. Under the payment agreement, defendant could pay St. Clair 90% of the value of the work performed and retain 10% of the amount earned until after completion of the entire project and its final acceptance. On July 13, 1981, the project engineers, Moore and Bruggink, recommended that St. Clair be paid $24,299. Thereafter, St. Clair was paid 90% of this sum, or $21,869.28, with $2,429.92 being retained by defendant. A second recommendation for payment was made on August 17, 1981. Pursuant to this recommendation, defendant paid St. Clair $26,234.06 and retained $2,914.90, or 10% of the amount earned by St. Clair.

On September 1, 1981, defendant received notice from several entities which had supplied materials to St. Clair that they had not received payment from St. Clair for the materials supplied. The total amount which St. Clair owed its material suppliers was $40,870.21. St. Clair’s nonpayment was reported to the surety, National Bonding and Accident Insurance Company. On September 24, 1981, the project engineers made the third and final recommendation for payment to St. Clair in the amount of $12,964.17. This payment was based *554 upon the value of the work which St. Clair performed from August 6, 1981, to September 21, 1981 ($7,619.35), and the total amount which defendant had retained pursuant to the contract ($5,344.82).

On October 8, 1981, defendant received a request from the bonding company to hold the money owed to St. Clair until the materialmen’s claims had been satisfied. On November 10, 1981, defendant was notified that a total of $40,870.21 had not been paid to various subcontractors and suppliers. Shortly thereafter, two of St. Clair’s creditors, Brewer’s City Dock and Nagel Construction Company, filed suit against St. Clair and the bonding company. Defendant then received a request from the bonding company to disburse the final payment which it owed to St. Clair to Brewer’s City Dock and to the bonding company so that it could pay Nagel Construction Company. Pursuant to this request, defendant paid Brewer’s City Dock $10,-000 and Nagel Construction Company received $2,770.89 from the bonding company. Pursuant to this payment, both creditors dismissed their suits against St. Clair and the bonding company.

St. Clair filed its petition in bankruptcy on July 19, 1982. The trustee in bankruptcy brought this claim alleging that St. Clair performed all the work it was required to do pursuant to its contract with defendant and, therefore, defendant still owed St. Clair its final payment of $7,619.35 despite the fact that defendant had already disbursed this money to satisfy St. Clair’s debts.

Pursuant to both parties’ stipulation filed in this Court on November 9, 1984, plaintiff’s claim for $5,344.82 accumulated retainage was abandoned. We hereby formally dismiss that claim. On appeal, plaintiff argues that it was improper for defendant to disburse to St. Clair’s creditors the funds *555 ($7,619.35) it owed to St. Clair. Thus, plaintiff claims that the grant of accelerated judgment in defendant’s favor was improper.

A motion for accelerated judgment provides a method by which certain disputed issues can be adjudicated at an early stage with the possibility of ending the cause and avoiding an expensive trial. Robinson v Emmet County Road Comm, 72 Mich App 623, 638; 251 NW2d 90 (1976). In reviewing motions for accelerated judgment, courts must accept all well pled allegations as true. Kircos v Goodyear Tire & Rubber Co, 108 Mich App 781; 311 NW2d 139 (1981). It is improper to grant a motion for accelerated judgment where factual issues exist.

In the instant case, this Court is called upon to review the trial court’s interpretation of a provision of the project contract executed by defendant and St. Clair. As a general rule, where a contract is open to construction, it is the duty of the court to determine, if possible, the true intent of the parties. In determining true intent, the court should consider the language employed in the contract, its subject matter and the circumstances surrounding the making of the agreement. It should attempt to effectuate the intent of the parties when the agreement was consummated. Stroud v Glover, 120 Mich App 258, 262; 327 NW2d 462 (1982). The contractual provision under review in the instant case is section 1.09.06 of the project specifications which were incorporated by reference into the contract between the parties. That section of the contract states:

"Acceptance and Final Payment — When the work has been completed and the Engineer has ascertained that each and every part of the work has been performed in accordance with the Plans and Specifications or such *556 modifications thereof as have been approved, the same will be accepted and the Engineer will make a final estimate, as soon as practicable, but not more than one month after acceptance, for the completed work, and the total amount due the Contractor less the total amount of all previous payment will be paid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Regional Federal Savings Bank v. Margolis
835 F. Supp. 356 (E.D. Michigan, 1993)
United States v. Palmer-Smith Co.
679 F. Supp. 641 (E.D. Michigan, 1987)
DMI Design & Manufacturing, Inc. v. Adac Plastics, Inc.
418 N.W.2d 386 (Michigan Court of Appeals, 1987)
Damerau v. C. L. Rieckhoff Co.
399 N.W.2d 502 (Michigan Court of Appeals, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
382 N.W.2d 819, 147 Mich. App. 550, Counsel Stack Legal Research, https://law.counselstack.com/opinion/remes-v-holland-michctapp-1985.