United States v. Palmer-Smith Co.

679 F. Supp. 641, 61 A.F.T.R.2d (RIA) 906, 1987 U.S. Dist. LEXIS 12725, 1987 WL 35069
CourtDistrict Court, E.D. Michigan
DecidedMay 29, 1987
Docket2:84-cv-73718
StatusPublished

This text of 679 F. Supp. 641 (United States v. Palmer-Smith Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Palmer-Smith Co., 679 F. Supp. 641, 61 A.F.T.R.2d (RIA) 906, 1987 U.S. Dist. LEXIS 12725, 1987 WL 35069 (E.D. Mich. 1987).

Opinion

MEMORANDUM OPINION AND ORDER

JULIAN ABELE COOK, Jr., District Judge.

On August 9, 1984, the United States brought suit against the Defendant, Palmer-Smith Company, for its failure to honor an Internal Revenue Service levy. In August of 1986, the Court allowed the Government to amend its Complaint and add a second cause of action (to wit, foreclosure of federal tax liens).

The issues were joined on September 23, 1986 when Palmer-Smith filed its answer. Shortly thereafter, both parties filed motions for summary judgment. Oral arguments were conducted on April 3, 1987. The motion was taken under advisement because of the need for additional briefing. The matter is now before this Court for resolution.

I

Palmer-Smith is a Melvindale, Michigan general contract company which works within the commercial, industrial, and institutional construction industry. Kropf Mechanical Contractors, Inc. was utilized by Palmer-Smith as a subcontractor to perform mechanical work at the Epcot Center in Lake Buena Vista, Florida.

Palmer-Smith and Kropf entered into two subcontracts 1 for mechanical work. During the existence of the two subcontracts, the Secretary of the Treasury made assessments against Kropf for unpaid withheld income and Federal Insurance Contributions Act (FICA) taxes which totalled $2,379,787.58. 2 From 1982 to 1983, the *643 Government filed a series of notices of federal tax lien regarding these liabilities.

Subsequent to the completion of the work on subcontract 8105-13, Palmer-Smith terminated the mechanical work on subcontract 8107-18 on March 9, 1983. Palmer-Smith did so because it concluded that Kropf could not, and did not, fully perform its contractual obligation under this second subcontract. Palmer-Smith justified its decision on the basis of a provision within the second subcontract which allowed for the termination of the agreement at any time when Palmer-Smith believed that Kropf could not complete its obligations under Article 6 of the General Terms and Conditions of Subcontract 8107-18. 3

In defense against the claims of the Government, Palmer-Smith asserts that Kropf s failure caused it to hire other subcontractors to do the same work which resulted in an economic loss of $624,085. In an effort to recover a portion of its loss on the second subcontract, Palmer-Smith set off the sum of $95,850 against the balance due Kropf under the first subcontract 8105-13 on March 12, 1983. This *644 setoff was explicitly executed pursuant to Article 3, Paragraph E of the General Terms and Conditions of Subcontract 8105-13.

On March 16, 1983, the Internal Revenue Service (IRS) served a notice of levy on Palmer-Smith with respect to the federal tax liabilities of Kropf. Approximately two weeks later (March 30, 1983), the IRS served a final demand on Palmer-Smith regarding the notice of levy.

II

The principal statutory provisions in this cause are 26 U.S.C. §§ 6321 and 6322. 26 U.S.C. § 6321 essentially provides that if a taxpayer neglects or refuses to pay a tax after a demand has been made upon him, the amount “shall be a lien in favor of the United States upon all property and rights to property, whether real or personal, belonging to such person.” 4 26 U.S.C. § 6322 simply determines that a lien, which was imposed under 26 U.S.C. § 6321, arises at the time when the assessment is made.

The central question in this case is whether Palmer-Smith possessed any property in which Kropf had a right. According to the Sixth Circuit Court of Appeals, in United States v. Bank of Celina, 721 F.2d 163, 169 (6th Cir.1983), “state law controls the issue of whether property exists to which a tax lien may attach in the first instance.” Kropf’s right to payment (if any) is based upon its contractual relationship with Palmer-Smith. Thus, state contract law principles are determinative of any of Kropf’s possible property rights that it may have possessed in the contested funds. The Government bears the burden of showing that Palmer-Smith had possession of the property of Kropf. Hall v. United States, 258 F.Supp. 173, 174 (D.Miss.1966).

Two provisions of the first subcontract (8105-13) are particularly important to the parties. Article 3(c) of the Subcontract General Terms and Conditions specifies:

(c) The final balance due the Subcontractor shall be payable thirty days, or such other period specified in the [contract documents,] after completion and acceptance of all the work required by the [contract documents] and of approval of the final estimate and receipt of final payment from the Owner; provided, however, that such final balance shall not be paid in any event until the Subcontractor has proved to the satisfaction of the Company that all labor, materials, equipment and services or any other obligation for which he is responsible, used in performance of or connected with this Subcontract, have been paid for in full, that there are no liens or claims, present or contingent, against the work, the Company or the Owner; and that the work has received the approval of the Architect Engineer and the Owner; provided, further that the final balance due shall be reduced by the amount of any backcharges or other amounts withheld under any provision of this Subcontract; provided, further, that in the event the Subcontractor shall engage in any bankruptcy, insolvency, or arrangement proceeding, voluntary or involuntary, the Company may withhold the final balance, or any other payments, until expiration of the period of any guarantees required of the Subcontractor and Company may use and apply out of such final balance the amount necessary to satisfy any claims or costs arising out of such guarantees. The Subcontractor shall have no property interest in, or right to, such payment, nor any other payment hereunder until received by him.

(Emphasis added). On its face, this last sentence, which has been underlined, appears to indicate that Kropf had no claim to the monies that are held by Palmer-Smith.

*645 Article 3(e) of Subcontract 8105-13 reads:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Bess
357 U.S. 51 (Supreme Court, 1958)
Pittsburgh National Bank v. United States
657 F.2d 36 (Third Circuit, 1981)
United States v. Bank of Celina
721 F.2d 163 (Sixth Circuit, 1983)
Remes v. Holland
382 N.W.2d 819 (Michigan Court of Appeals, 1985)
Superior Ambulance Service v. City of Lincoln Park
173 N.W.2d 236 (Michigan Court of Appeals, 1969)
Geerdes v. St. Paul Fire & Marine Ins. Co.
341 N.W.2d 195 (Michigan Court of Appeals, 1983)
Amoco Oil Co. v. Kraft
280 N.W.2d 505 (Michigan Court of Appeals, 1979)
Atlantic Refining Co. v. Continental Casualty Co.
183 F. Supp. 478 (W.D. Pennsylvania, 1960)
Deboer v. Geib
238 N.W. 226 (Michigan Supreme Court, 1931)
Boughton v. Boughton's Estate
69 N.W. 94 (Michigan Supreme Court, 1896)
Hall v. United States
258 F. Supp. 173 (S.D. Mississippi, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
679 F. Supp. 641, 61 A.F.T.R.2d (RIA) 906, 1987 U.S. Dist. LEXIS 12725, 1987 WL 35069, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-palmer-smith-co-mied-1987.