Reed v. Pittman

242 So. 2d 554, 257 La. 389, 1970 La. LEXIS 3492
Supreme Court of Louisiana·Decided December 14, 1970·No. 50389·Published·Cited by 15 cases

Opinions

TATE, Justice.

Both the trial court and the court of appeal 1 dismissed this suit as abandoned by the plaintiff because of his failure to take any step in its prosecution during a period of five years. La. CCP Art. 561. The case is before us on certiorari. 255 La. 553, 232 So.2d 76 (1970).

The sole issue is whether the five-year period was interrupted by steps taken during this interval by the plaintiff in another action, with which the present suit was consolidated.

The present suit arises out of a large construction contract entered into between the defendant Pittman, a general contractor, and the Housing Authority of New Orleans (HANO). The plaintiff Reed entered into a subcontract with Pittman to furnish glass and glazing and all painting on the low-rent housing project to be constructed.

. Reed filed the present suit to recover $30,005.01 for monies allegedly due him by Pittman on the subcontract.

This suit was filed on December 23, 1954. In 1956, it was consolidated with a related suit. After proceedings in the related suit, to be described below, the plaintiff moved to set the present case for trial on April 16, 1962. After several continuances, in 1968 the defendant Pittman filed a rule to show cause why this proceeding should .not be dismissed as abandoned because no action had been taken in it from 1956 to 1962, a period exceeding five years.

Both the trial court and the court of appeal sustained this position of the defendants and dismissed the suit. They rejected the contention of the plaintiff that his numerous appearances and pleadings during the years 1956 through 1962 in the consolidated suit relating to this claim should be held to have interrupted the five-year period.

At this time it is appropriate to describe the relationship of the present suit to the related suit.

On October 23, 1956, by ex parte motion the Pittman defendants secured an order to consolidate the present suit (Suit One) with the related case (Suit Two).2 (This 1956 motion and order is the last pleading in the present suit until the motion for [393] trial of 1962.) The present (Suit One) was filed in Division “E” of the trial court, while the other (Suit Two) was filed in Division “F” thereof.

In its motion to consolidate, the defendant Pittman made certain pertinent allegations in this pleading in this suit. Pittman alleged that Suit Two involved issues of law and fact which embraced and were related to the issues of the present proceeding (Suit One). The motion further alleged that it was necessary to make Reed a third-party defendant in Suit Two, so that the ends of justice would be served by the consolidation of the present suit with Suit Two.

The trial judge of Division “E” thereupon ordered the present suit transferred to Division “F”, “there to be consolidated and tried with” Suit Two.

Suit Two had been filed by Pittman against the Housing Authority (HANO) to recover for all materials furnished and all work performed by Pittman and its subcontractors (including Reed) on the housing construction project.3 (Eventually, as the court of appeal opinion in Suit Two shows, Pittman recovered in excess of six hundred thousand dollars in this action, including for substantially all of the work performed on the Reed subcontract. 169 So.2d 122 at 148, see also p. 144.)

Soon after the consolidation, Pittman instituted a third-party demand against Reed in Suit Two for the amount of the alleged defects in the painting contract.4 On October 10, 1958, in Suit Two Reed filed a reconventional demand to this third-party demand by Pittman against him. A copy of this pleading was introduced to form part of the record of the present suit, per order [395] of the court of appeal below. See 224 So.2d 100.

By this pleading in Suit Two, Reed asserted the identical claim of $30,005.01 sought by the demand in the present Suit One. The demand was asserted, in the event the court (Division “F”) maintained the order consolidating Suit One with Suit Two. The plaintiff again reiterated his right to have the claim decided in the present Suit One, instead of with Suit Two.

So far as the record shows,5 this reconventional demand was not disposed of, nor was any order ever issued rescinding the consolidation of Suit One (involving the identical issue) with Suit Two. (To repeat, the various principal and incidental demands in Suit Two all arise out of the prime contract between Pittman and HANO and of several of the subcontracts involved, including the one between Reed and Pittman which is the subject matter of the present Suit One.)

However, in affirming Pittman’s recovery of some six hundred thousand dollars ’ for contract work performed (including that covered by the Reed subcontract), the .court of appeal dismissed all claims between Pittman, Reed, and HANO relating to the painting subcontract. The dismissal was without prejudice to the parties to assert them in this suit “relating to the same subject matter now pending in the Civil Court for the Parish of Orleans”. 169 So.2d 122 at 148. See also 169 So.2d 144.

Nevertheless, when Reed sought once again to assert its claim in this Suit One to recover for money due on the painting subcontract, Pittman successfully claimed that the present Suit One was abandoned. The reason contended is that because between 1956 and 1962 no steps had been taken in the prosecution or defense of the present suit on the docket of Division “E” —even though numerous steps had been taken in the consolidated proceedings of Division “F” to which this Division “E” suit had been transferred.

In our view, this contention overlooks that the plaintiff Reed in the present Suit One could not practicably secure any action in it in Division “E” while it was consolidated with Suit Two in another division and before another judge of the trial court. It further overlooks the several actions taken by Reed and Pittman in this other suit, including the reconventional demand in 1958 by Reed asserting in Suit Two the same claim as that now urged in the present suit.

[397] We should further note that the defendant Pittman secured the consolidation of Suit One with Suit Two and its transfer to another division, upon specific allegations that Suit Two’s issues embraced Suit One’s and that the interests of justice should best be served by adjudicating all issues of both suits in consolidated proceedings. Pittman itself thus secured this consolidation and transfer which had the effect of staying all proceedings in the present suit.

We reject the contention of Pittman that, because of the delay directly resulting solely from this maneuver by it, the present suit should be considered abandoned.

La. CCP Art. 561 provides that an action is abandoned when the parties fail to take any step in its prosecution or defense during five years and that this provision is self-operative.

Free access — add to your briefcase to read the full text and ask questions with AI

Reed v. Pittman, 242 So. 2d 554, 257 La. 389, 1970 La. LEXIS 3492 (La. 1970).

242 So. 2d 554 (Reed v. Pittman) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Solomans Real Estate, LLC v. Evan Edmondson
Louisiana Court of Appeal, 2026
Harmonia LLC v. Felicity Properties Co, LLC
Louisiana Court of Appeal, 2023
Cynthia Duplechain v. Town of Church Point
Louisiana Court of Appeal, 2012
Occidental Properties, Ltd. v. Reed
79 So. 3d 1135 (Louisiana Court of Appeal, 2011)
Wooley v. Lucksinger
14 So. 3d 311 (Louisiana Court of Appeal, 2009)
Dendy v. City Nat. Bank
977 So. 2d 8 (Louisiana Court of Appeal, 2007)
Pichon v. Reynolds
841 So. 2d 756 (Supreme Court of Louisiana, 2003)
Sassau v. Louisiana Workover Service, Inc.
607 So. 2d 809 (Louisiana Court of Appeal, 1992)
O'ROURKE v. Cormier
459 So. 2d 200 (Louisiana Court of Appeal, 1984)
Pan American Import Co., Inc. v. Buck
440 So. 2d 182 (Louisiana Court of Appeal, 1983)
US Fire Ins. Co. v. Swann
424 So. 2d 240 (Supreme Court of Louisiana, 1982)
Howard v. Hercules-Gallion Co.
417 So. 2d 508 (Louisiana Court of Appeal, 1982)
U. S. Fire Insurance v. Swann
411 So. 2d 1173 (Louisiana Court of Appeal, 1982)
Home Indem. Co. v. Central La. Elec. Co.
384 So. 2d 455 (Louisiana Court of Appeal, 1980)
Reed v. Pittman
242 So. 2d 554 (Supreme Court of Louisiana, 1970)