Reed v. Buckeye Fire Equipment

241 F. App'x 917
CourtCourt of Appeals for the Fourth Circuit
DecidedJuly 30, 2007
Docket06-1481
StatusUnpublished
Cited by24 cases

This text of 241 F. App'x 917 (Reed v. Buckeye Fire Equipment) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reed v. Buckeye Fire Equipment, 241 F. App'x 917 (4th Cir. 2007).

Opinion

*919 PER CURIAM:

Ramsey Reed (“Appellant”) appeals the district court’s grant of summary judgment in favor of Buckeye Fire Equipment Company (“Buckeye”) and Bryan Bower (collectively, “Appellees”) on various claims related to the termination of his employment on April 30, 2001. He alleges that, in firing him while he was on medical leave, Buckeye violated the Family and Medical Leave Act (the “FMLA”), 29 U.S.C. § 2601, et seq. and North Carolina’s prohibition against age discrimination in employment, N.C. Gen.Stat. § 143-422.2. He also alleges that Bryan Bower obstructed justice and engaged in a civil conspiracy by attempting to blackmail him into not filing this lawsuit.

The district court discerned no material issue of fact in any of Appellant’s claims and granted summary judgment in favor of Appellees on both the FMLA and state-law claims. Our review of the record reveals, however, that Appellant has presented triable issues in the claims against Buckeye and the obstruction of justice claim against Bryan Bower. Accordingly, we reverse the district court’s order on the FMLA, age discrimination and obstruction of justice claims, and affirm on the civil-conspiracy claim. We set forth the pertinent facts below, reciting them in the light most favorable to Appellant. See Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 255, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986).

I.

Buckeye is a family-owned business headquartered in Kings Mountain, North Carolina that manufactures and sells firefighting equipment. Tom Bower and his two sons, Kevin and Bryan, own and operate the company.

On January 25, 2001, Appellant was involved in a serious car accident that necessitated medical leave. He suffered a severe compound fracture to his leg that punctured his skin in several places and required immediate surgery. Appellant was hospitalized for several days following the surgery and underwent rehabilitative therapy thereafter.

On the day of the accident, Appellant’s wife called Kevin Bower, Buckeye’s Vice President of Operations, to inform him of her husband’s accident and injury. Once Appellant was discharged from the hospital, he also spoke with Kevin Bower and informed him that he would require at least two months’ leave from work to recover. 1 Appellant updated Kevin Bower from time to time regarding his medical progress, which was steady until late-February.

On February 15, 2001, Buckeye’s maintenance manager, Howard Corbin (“Cor-bin”), called Appellant to seek his help *920 with several equipment problems that had arisen during his absence. Appellant’s doctor cleared him to return to work on a limited basis in a wheelchair, and Appellant returned to Buckeye on February 23. He fixed a problem with an automated label machine and taught the maintenance crew how to resolve it in his absence. For a variety of reasons, however, Appellant had to delay fixing a separate problem with a gauge assembly machine until the following week.

Over the intervening weekend, Appellant was hospitalized for treatment of a serious blood clot in his leg. He remained in the hospital for two days and was placed on blood-thinning medication before being discharged with an order to remain home-bound for six weeks. Appellant spoke with Buckeye’s comptroller about this setback, but was unsuccessful in several attempts to reach Kevin Bower about the same.

Following treatment for the blood clot, Appellant’s recovery continued at a steady pace. By the end of March 2001, he was using a walker, was cleared by his doctors to leave his house, and was receiving outpatient physical therapy. By mid-April, he was walking with a cane and had purchased a new truck in preparation for his return to work. On April 17,. Appellant told Corbin that he would return to Buckeye full-time on May 7. However, Tom Bower called Appellant on April 30 to tell him that Buckeye was terminating his employment for performance-related reasons. By that time, Appellant had been on medical leave for nearly thirteen-and-a-half weeks.

A. Contested Workplace Issues

The parties dispute virtually every material fact underlying Appellant’s termination. To substantiate its claim of inadequate job performance, Buckeye points to a number of equipment problems arising both during and after Appellant’s tenure, a change in Appellant’s job title in 1996, and a series of personal conduct issues. Appellant disputes the significance of the equipment problems, contests Buckeye’s characterization of the change in job title, and challenges the claims of unprofessional conduct. We now briefly summarize each episode in contention and the nature of the dispute.

1. The Weld Line

In 1997, Buckeye contracted with a local manufacturer, Sotec, to develop a weld line to automate the production of its fire extinguisher cylinders. Tom Bower wanted the automated line to produce two hundred forty welded cylinders per hour and pay for itself within three years. Sotec agreed to Buckeye’s design specifications and promised to deliver the weld line within twenty to twenty-two weeks.

Appellant, as Buckeye’s head engineer, spent significant time at Sotec’s plant working closely with its personnel during the production and testing phase of the line. The project experienced technical problems and the line remained nonfunctional after eighteen months, far beyond the contractual time frame. Buckeye contends that Appellant failed to keep it fully informed of these problems. Kevin Bower eventually grew so frustrated with Sotec that he ordered the line moved to Buckeye’s facilities for completion. It became apparent that even then the weld line could not meet the expectations of Buckeye’s management.

Buckeye contends that Appellant was principally responsible for this project and that its problematic history, along with his lack of communication regarding the problems during the line’s construction, is evidence of his poor job performance. Appellant argues that the problems with the weld line lay in its construction, which was *921 Sotec’s responsibility, and not in the design that he developed. He additionally contends that he kept Buckeye folly apprised of the project’s status and that he was not principally responsible for the weld line.

2. Gauge Assembly Machine

Sometime in either 1996 or 1999 (Appellant claims the former and Buckeye the latter), Buckeye purchased a machine to automate the gauge assembly for its fire extinguishers. The machine never functioned properly because of design flaws attributable to the original manufacturer. As a result, Buckeye required the manufacturer to redesign and rebuild parts of the machine. The machine’s laser sensors proved particularly troublesome, requiring constant manual adjustment. When Appellant was on medical leave, the gauge assembly machine began malfunctioning, with expensive consequences.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

WALL v. GULLEDGE
M.D. North Carolina, 2024
Fairmont Tool, Inc. v. Norvel Louis Opyoke
West Virginia Supreme Court, 2022
Hannah P. v. Daniel Coats
916 F.3d 327 (Fourth Circuit, 2019)
Lovely-Coley v. District of Columbia
191 F. Supp. 3d 20 (District of Columbia, 2016)
Hodges v. District of Columbia
172 F. Supp. 3d 271 (District of Columbia, 2016)
Alexander v. Carolina Fire Control Inc.
112 F. Supp. 3d 340 (M.D. North Carolina, 2015)
Downs v. Winchester Medical Center
21 F. Supp. 3d 615 (W.D. Virginia, 2014)
Ramos v. Molina Healthcare, Inc.
963 F. Supp. 2d 511 (E.D. Virginia, 2013)
Harris v. Powhatan County School Board
885 F. Supp. 2d 804 (E.D. Virginia, 2012)
Mike Duffy v. Belk, Inc.
477 F. App'x 91 (Fourth Circuit, 2012)
McFadyen v. Duke University
786 F. Supp. 2d 887 (M.D. North Carolina, 2011)
Feldman v. Law Enforcement Associates Corp.
779 F. Supp. 2d 472 (E.D. North Carolina, 2011)
Bosse v. Baltimore County
692 F. Supp. 2d 574 (D. Maryland, 2010)
Breeden v. NOVARTIS PHARMACEUTICALS CORP.
684 F. Supp. 2d 58 (District of Columbia, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
241 F. App'x 917, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reed-v-buckeye-fire-equipment-ca4-2007.