Redbud Cooperative Corp. v. Clayton

700 S.W.2d 551, 1985 Tenn. App. LEXIS 3060
CourtCourt of Appeals of Tennessee
DecidedAugust 1, 1985
StatusPublished
Cited by62 cases

This text of 700 S.W.2d 551 (Redbud Cooperative Corp. v. Clayton) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Redbud Cooperative Corp. v. Clayton, 700 S.W.2d 551, 1985 Tenn. App. LEXIS 3060 (Tenn. Ct. App. 1985).

Opinion

OPINION

KOCH, Judge.

This appeal arises from a dispute between the developer of a planned unit development located in an affluent section of Nashville and the development’s homeowners. In 1979, the non-profit corporation consisting of the development’s homeowners together with several individual owners brought an action in the Chancery Court for Davidson County against the developer and the Metropolitan Government of Nashville and Davidson County claiming that the development was being damaged by an inadequate surface water drainage system. The trial court heard this case without a jury and on May 18, 1984, entered a judgment against the developers in the amount of $157,389.85. 1 The developers have duly perfected this appeal. For the reasons stated herein, we affirm the judgment of the trial court.

I.

The Facts

Creason Clayton, his wife, and their construction company are the developers and builders of Redbud, a planned residential development located in the Green Hills Section of West Nashville. This development, consisting of twenty-one separate parcels and adjoining common areas, was built on a sloping 5.27 acre tract bordered by Hobbs Road on the north and by other residential property on the other sides. Because of the terrain in this area, the surface water from approximately ten acres of neighboring residential property flows in a northwesterly direction onto the property where Redbud is located.

The Claytons began to develop this property in early 1974. They retained a landscape architecture and engineering firm to *553 prepare a master development plan for the site and to obtain the required approvals from the local governmental agencies. The developers’ engineers prepared a preliminary master development plan for Redbud which included the proposed preliminary grading plan that was required by the local zoning ordinance. 2 The Metropolitan Planning Commission approved these plans on February 20, 1974. This preliminary plan was ultimately approved on June 4, 1974, when an ordinance amending the local zoning regulations was passed by the Metropolitan Council and approved by the Mayor.

In order to obtain building permits for the construction of the homes to be built in Redbud, the developers were required to submit a final master development plan to the Metropolitan Planning Commission for review and approval. In addition to the information provided in the proposed master development plan, the local zoning ordinance required that this plan also contain “the location and size of water, sewerage, and drainage structures” and “detail grading plans showing existing and proposed topography.” Thus, in accordance with the local ordinance, the developers’ landscape architect filed a detailed “grading plan” dated July 3, 1974, with the Metropolitan Planning Commission and with the Division of Public Works.

The developers’ grading plan showed Redbud’s existing topography as-well as its proposed topography. It revealed that the developers intended to make provisions for the drainage of the surface water by constructing sodded swales 3 on portions of Redbud’s eastern boundary, on its southwestern boundary, and along its entire western boundary. As originally designed, these swales would run through the middle of the residents’ relatively small backyards. The grading plan also called for the construction of an underground drainage system in the form of a conduit and three thirty-inch catch basins running in a generally northerly direction through the middle of Redbud. The purpose of this underground conduit was to carry off to Hobbs Road the surface water collected by the swale that was to be constructed on the southeastern portion of the development as well as other surface water that would be expected to accumulate on the upper portions of the development and then flow downhill in a northwesterly direction across other portions of the development.

The grading plan, as submitted, did not envision the construction of a perimeter wall around the entire development. 4 Nor did it envision the construction of protective or privacy walls between the backyard of each parcel. Nor did it envision the construction of patios in the homeowner’s backyards. The grading plan, as filed, was ultimately approved by the Metropolitan Planning Commission, and the developers were issued building permits in accordance therewith.

The developers began to grade and to prepare the site for the construction of the homes. However, as they proceeded to construct Redbud, the developers decided to depart from the approved grading and drainage plan on file with the Planning Commission in a number of significant respects.

The first departure relates to the underground drainage conduit that was originally planned to run in a northerly direction through the middle of the development. *554 The Nashville Electric Service installed its primary and secondary underground cables for the development before this conduit was constructed. Once these cables were in place, the developers discovered that they could not construct their underground drainage conduit as originally planned because it would interfere with the underground electric cables. Rather than constructing an alternate underground drainage system that would carry off the surface water to Hobbs Road, the developers decided to abandon constructing two of the three catch basins and the portions of the conduit that would have caught and carried off the surface water collecting upon the upper most portions of the development. 5 The developers did, however, construct one catch basin in front of their own home which was connected to the portion of conduit that was originally intended to carry off the water to Hobbs Road.

The second departure from the grading and drainage plan was the construction of a masonry wall around the entire perimeter of Redbud. The developers did not intend originally to construct this wall. However, during the early phases of construction, and in response to individual requests by persons who had purchased homes in Red-bud, the developer decided to build this wall primarily to provide the property owners with additional privacy. 6 The developers began to build this wall in late 1974. It was built in increments as the home on each parcel was constructed and it was completed in late 1976. The wall was constructed of concrete blocks and was not reinforced. The developers included weep holes at the base of this wall for the purpose of permitting water to flow through freely at these points.

The third departure from the grading and drainage plan was the construction of similar sideline privacy walls between the backyards of each parcel. These walls were not originally planned but were erected by the developer as the construction progressed in response to the requests of individual purchasers.

The fourth departure related to the construction of the swales which, as originally planned, would run through the backyards of a majority of the homes in Redbud.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Orson E. Steward v. Regent Homes, LLC
Court of Appeals of Tennessee, 2024
Annaliese Potter v. Paul Israel
Court of Appeals of Tennessee, 2023
Clayton Pickens v. John R. Underwood
Court of Appeals of Tennessee, 2018
Sandra Prewitt v. Kamal Brown
525 S.W.3d 616 (Court of Appeals of Tennessee, 2017)
Synovus Bank v. David A. Paczko
Court of Appeals of Tennessee, 2015
James M. Bowley v. Richard Lane
Court of Appeals of Tennessee, 2013
Sisco and Close Properties v. C & E Partnership
Court of Appeals of Tennessee, 2012
Brooke Buttrey v. Holloway's, Inc.
Court of Appeals of Tennessee, 2012
Phillip A. Corbitt v. Rolanda Amos
Court of Appeals of Tennessee, 2012
Wilson Reynolds v. Lee Roy Roberson
Court of Appeals of Tennessee, 2012
Discover Bank v. Morgan
363 S.W.3d 479 (Tennessee Supreme Court, 2012)
John Gallon v. Harry Elberson
Court of Appeals of Tennessee, 2010
GARY R. PRINCE REVOCABLE TRUST v. Blackwell
735 F. Supp. 2d 804 (M.D. Tennessee, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
700 S.W.2d 551, 1985 Tenn. App. LEXIS 3060, Counsel Stack Legal Research, https://law.counselstack.com/opinion/redbud-cooperative-corp-v-clayton-tennctapp-1985.