Red Maple Properties v. Zoning Commission

610 A.2d 1238, 222 Conn. 730, 1992 Conn. LEXIS 218
CourtSupreme Court of Connecticut
DecidedJune 18, 1992
Docket14341
StatusPublished
Cited by46 cases

This text of 610 A.2d 1238 (Red Maple Properties v. Zoning Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Red Maple Properties v. Zoning Commission, 610 A.2d 1238, 222 Conn. 730, 1992 Conn. LEXIS 218 (Colo. 1992).

Opinion

Berdon, J.

The principal issue in this appeal is whether a real estate developer, who sought a permit from a local zoning commission, had a property interest protected by the substantive component of the due process clause of the federal constitution. The plaintiff, Red Maple Properties, brought suit against the defendants, the zoning commission of the town of Brookfield (commission) and its members,1 pursuant to 42 U.S.C. § 19832 claiming that its civil rights had been violated by the actions of the defendants in preventing the use of its property as a multi-unit condominium project after the plaintiff had received approval for two units. After the close of the plaintiffs case-in-chief, the trial court granted the defendants’ motion for a directed verdict and this appeal followed from the judgment rendered thereon.3 We now affirm the judgment of the trial court.

The relevant facts are as follows. The plaintiff is a limited partnership formed for the purpose of developing a parcel of land consisting of approximately 133 [733]*733acres, along Route 133 in Brookfield. The plaintiff, through its agent and general partner, Gull Development Corporation, entered into option agreements to purchase two pieces of land, which together comprised the 133 acre parcel.

The plaintiff sought to develop the parcel in phases for an expandable condominium project totalling 208 units. On January 13,1983, the plaintiff filed a formal application with the defendants for approval of two units, known as “phase I,” which was submitted as an application for design review approval. In February, 1983, the plaintiff, through its engineer, Paul Carroccio, and its representatives, Joseph and Susan Fritz, met informally with the then commission chairman, Alan Sniffin, and a commission member, William Schappert, to discuss the application. The plaintiff claimed at trial that at this meeting Sniffin and Schappert had given it “conceptual approval” for the entire 206 unit project, provided it complied with the zoning regulations in effect at that time.

A public hearing on the plaintiffs application for phase I was conducted on April 14,1983. At the hearing, Sniffin stated that the commission was reviewing the development potential of 206 units on the plaintiff’s land. On April 20,1983, Sniffin sent the plaintiff’s engineers a letter seeking additional information about the project, including data regarding wetlands protection and water supplies and the designation of local access drives. On June 23,1983, the defendants approved the application for design review with respect to the two units.

On July 12,1983, a lawsuit, which was subsequently withdrawn in 1985, was filed by some Brookfield residents appealing the decision of the defendants granting approval for phase I. In late 1984, the conservation commission proposed an amendment to § 242-404D of [734]*734the Brookfield zoning regulations, which provides for multifamily dwellings, including condominiums. The proposal sought, in effect, to place a “cap” on the number of multifamily dwellings allowed in the town. The defendants held public hearings, at which the plaintiff appeared and testified against the proposed amendment. On May 23, 1985, the defendants approved a modification of the regulation limiting multifamily dwelling projects to 150 units.4 Prior to the change in the regulations, the plaintiff had not sought approval of any additional phases of its planned project. On October 24, 1985, the plaintiff sent the commission a letter inquiring whether its project would be “grandfathered,” or exempted, under the new regulation. Schappert responded that under any new application submitted by the plaintiff, the commission would exempt only the two units, which had previously been approved.

The plaintiff brought the present § 1983 action in Superior Court claiming that its civil rights were violated by the defendants because the amendment to the regulation was arbitrary and capricious and was intended to thwart the plaintiffs entire project, which the plaintiff claimed had been given “conceptual approval.” The plaintiff claimed at trial that it was entitled to approval of the entire project, and that its entitlement was a protected property interest sufficient to trigger federal substantive due process rights. In its amended complaint, the plaintiff also claimed it was [735]*735deprived of its procedural due process rights. The plaintiff also pleaded but subsequently withdrew a claim of equitable estoppel.

The trial court granted the defendants’ motion for a directed verdict upon concluding that the defendants were vested with broad discretion as to whether to approve an application for design review, and that this broad discretion manifestly overcame and defeated any claim that the plaintiff had established an entitlement allowing it to invoke the constitutional protections of the fourteenth amendment. The trial court summarily dismissed the plaintiffs claim of “conceptual approval.”

The gravamen of the plaintiff’s appeal is that it has a property interest in the zoning approval for its entire project, and that the defendants’ actions arbitrarily and capriciously deprived it of its property interest in the approval, which violated its federal substantive due process rights. The plaintiff also claims on appeal that the trial court improperly: (1) found that the plaintiff had not advanced a procedural due process claim; and (2) excluded as irrelevant certain testimony of the plaintiff’s project engineer, Paul Carroccio. We agree with the trial court that the plaintiff did not have a property interest protected by the substantive component of the due process clause of the federal constitution, and, therefore, we affirm the judgment of the trial court. We also reject the other claims of the plaintiff.

I

At the outset, we note that although we do not generally favor directed verdicts; John T. Brady & Co. v. Stamford, 220 Conn. 432, 440, 599 A.2d 370 (1991); “[a] verdict may properly be directed where the decisive question is one of law. Rich v. Dixon, 153 Conn. 52, 61-62, 212 A.2d 417 (1965); Sedita v. Steinberg, 105 Conn. 1, 5, 134 A. 243 (1926).” Gottesman v. Aetna Ins. Co., 177 Conn. 631, 634, 418 A.2d 944 (1979). There[736]*736fore, if the trial court properly determined that, as a matter of law, the actions of the defendants had not violated the plaintiff’s substantive due process rights, then the trial court was correct in directing the verdict because “ ‘[i]t is merely reaching more speedily and directly a result which would inevitably be reached in the end.’ People’s Savings Bank v. Borough of Norwalk, 56 Conn. 547, 556, 16 A. 257 (1888); Simmons v. Southern Connecticut Gas Co., 7 Conn. App. 245, 250, 508 A.2d 785 (1986).” Petriello v. Kalman, 215 Conn. 377, 383, 576 A.2d 474 (1990).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dufresne v. Camden-Wyoming Fire Company Inc.
Superior Court of Delaware, 2020
Farrell v. Johnson & Johnson
335 Conn. 398 (Supreme Court of Connecticut, 2020)
State v. Bermudez
195 Conn. App. 780 (Connecticut Appellate Court, 2020)
Martinez v. Empire Fire & Marine Ins. Co.
139 A.3d 611 (Supreme Court of Connecticut, 2016)
Honulik v. Town of Greenwich
963 A.2d 979 (Supreme Court of Connecticut, 2009)
Szewczyk v. Department of Social Services
881 A.2d 259 (Supreme Court of Connecticut, 2005)
Hall v. Pennsylvania Board of Probation & Parole
851 A.2d 859 (Supreme Court of Pennsylvania, 2004)
Dillman v. Allen-Warren, No. X02-Cv-00-0167578s (Jul. 22, 2002)
2002 Conn. Super. Ct. 9426 (Connecticut Superior Court, 2002)
City Recycling, Inc. v. State
778 A.2d 77 (Supreme Court of Connecticut, 2001)
State v. Rigual
771 A.2d 939 (Supreme Court of Connecticut, 2001)
Tooley v. Metro-North Commuter Railroad
755 A.2d 270 (Connecticut Appellate Court, 2000)
Turner v. Frowein
752 A.2d 955 (Supreme Court of Connecticut, 2000)
Shareamerica Inc. v. Ernst Young, No. Cv 93-0150132 S (Jul. 2, 1999)
1999 Conn. Super. Ct. 9951 (Connecticut Superior Court, 1999)
Thomas v. City of West Haven
734 A.2d 535 (Supreme Court of Connecticut, 1999)
Northeast Parking v. Plumridge, No. Cv95-0466606s (Jun. 14, 1999)
1999 Conn. Super. Ct. 7131 (Connecticut Superior Court, 1999)
Nelson v. Suraci, No. 403034 (May 28, 1999)
1999 Conn. Super. Ct. 5928 (Connecticut Superior Court, 1999)
Grimes v. Conservation Commission
703 A.2d 101 (Supreme Court of Connecticut, 1997)
State v. Sebastian
701 A.2d 13 (Supreme Court of Connecticut, 1997)
Thomas v. City of West Haven, No. Cv89 0284555s (Jul. 30, 1997)
1997 Conn. Super. Ct. 7471 (Connecticut Superior Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
610 A.2d 1238, 222 Conn. 730, 1992 Conn. LEXIS 218, Counsel Stack Legal Research, https://law.counselstack.com/opinion/red-maple-properties-v-zoning-commission-conn-1992.