Opinion

*351 VAN HOOMISSEN, J.

Real Estate Loan Fund (RELF), a limited partnership, filed a complaint for strict foreclosure of a land sale contract against defendants Fast and Hevner, 1 owners of a condominium unit. RELF joined as a defendant the Association of Unit Owners of Bayshore Inn (the Association), which claimed a lien on the unit. The Association cross-claimed for foreclosure of its assessment lien on the unit, claiming a priority. See ORS 94.195. In reply, RELF claimed that it had priority over the Association’s lien. RELF alleged that the Association had entered into a contract with RELF to release its liens, so as to permit RELF to foreclose or to accept deeds in lieu of foreclosure where contracts for condominium units were in default, and that the Association was estopped to deny that contract. The trial court found that there was no contract between RELF and the Association, that the Association was not estopped to assert its priority and that the Association’s lien had priority. On de novo review, we reverse.

In 1977, Brenneman, then the owner of a motel known as the Bayshore Inn, converted it to condominiums. An association of unit owners was formed. RELF was involved in the formation of the Association and approved its by-laws. See ORS 94.004 et seq. Brenneman sold some of the condominium units on land sale contracts. He later sold sixty of those contracts to RELF. By 1981, RELF was having trouble collecting on some of the contracts. RELF was aware that the Association had filed liens for nonpayment of assessments against some of the units in which RELF had an interest. The Association’s aggregate assessments against the units on which RELF had contracts totaled more than $90,000.

In order to avoid a judicial foreclosure of each unit and the necessity of litigating priority between itself and the Association, RELF and MBC, RELF’s general partner, wanted the Association to release its priority lien claims against the units on which RELF held a contract. That would *352 allow RELF to accept deeds in lieu of judicial foreclosure. RELF asked Holmes, an attorney who had represented both parties in the past and who was then the Association’s registered agent, to convey RELF’s offer to the Association. On February 17,1982, he wrote to the Association:

“S. E. Brenneman, Manager
Association of Unit Owners
The Bayshore Inn
500 Bayshore Drive
Waldport, Oregon 97394
“Re: Bayshore Inn Assessments/ Mortgage Bancorporation Lien Priorities
“Dear Ed:
“I would appreciate your presenting this letter to the Board. Mortgage Bancorporation has a number of contracts to foreclose upon. They claim a priority of their lien as being ahead of the assessments made by the Association. As you know, the Court has agreed with that and have (sic) given then (sic) a prior lien in the only case brought to issue. [2] In many instances they can obtain a deed in lieu of foreclosure and could avoid the time, expense and delay of foreclosing if the Board would release the unit they intend to foreclose from the assessment. In order to eliminate the joining of the association in each lawsuit, Mortgage Bancorporation [RELF’s general partner] would offer to do the following:
“(1) Pay the Association $100 for a release of the lien as to the property being foreclosed or deed taken in lieu with the understanding that that assessment can still be collected by the association from the individual against whom the foreclosure action is brought or whoever may own it; and
“(2) During the foreclosure proceedings and until the unit is sold to a third party, who would become a member of the association, the association would be free to rent the unit and retain all the proceeds so long as no continuing assessments or costs were charged Mortgage Bancorporation.
“I would appreciate your response to this at your earliest convenience. Thank you kindly.
“Very truly yours,
“/s/ Kenneth A. Holmes”

*353 Holmes’ letter was received by Brenneman, who at that time was the Association’s manager.

A special meeting of the Association was held on February 27, 1982, at which all members of the Association’s Board of Directors were present. The minutes of that meeting show that Holmes’ letter was read and discussed. The letter, which is included verbatim in the minutes of the meeting, is followed by a notation, “Decision made to comply with request.” Immediately following the special meeting, the Association’s Board of Directors met. The minutes of the Board of Directors’ meeting do not mention Holmes’ letter or RELF’s proposal.

On March 2, 1982, Holmes received a letter from Brenneman on the Association’s stationery. It stated, in relevant part:

“The members of the Board of the Association of Unit Owners unanimously agreed to the proposal of February 17 to accept the terms for the release of liens on properties to be foreclosed or deed taken in lieu of foreclosure in favor of Mortgage Bancorporation.
“I will send you a copy of the minutes as soon as possible.” 3

At the Board of Directors’ meeting on March 13, 1982, the minutes of the February 27 Association meeting were “read and approved.” After receiving Brenneman’s March 2 letter, RELF suspended foreclosure and collection activity on the delinquent units. RELF sent release documents to the Association, but they were not returned. After subsequent negotiations failed to resolve the dispute between the parties, this foreclosure action resulted.

The trial court stated:

“After reviewing the facts in this case and the exhibits, the Court is of the opinion and will hold that the plaintiff has failed in [its] burden to establish that the defendant Association entered into an agreement whereby they would subordinate their assessments to the plaintiffs interest. The plaintiff was aware that the Association acted through its board of directors both because it originally examined the prospectives [sic] for the condominiums and because it held one or more of the condominium units and it received the information from *354 the Association concerning the assessments and the meeting of the Unit Holders as well as the Board of Directors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bridge City Family Medical Clinic v. Kent & Johnson, LLP
346 P.3d 658 (Court of Appeals of Oregon, 2015)
Apeldyn Corp. v. Eidos, LLC
943 F. Supp. 2d 1145 (D. Oregon, 2013)
Estate of Pruyn v. Axmen
2009 MT 448 (Montana Supreme Court, 2009)
Ken Hood Construction Co. v. Pacific Coast Construction, Inc.
120 P.3d 6 (Court of Appeals of Oregon, 2005)
Newton/Boldt v. Newton
86 P.3d 49 (Court of Appeals of Oregon, 2004)
Novak v. Seiko Corp.
37 F. App'x 239 (Ninth Circuit, 2002)
Hildebrandt v. Anderson
42 P.3d 355 (Court of Appeals of Oregon, 2002)
Holdner v. Holdner
29 P.3d 1199 (Court of Appeals of Oregon, 2001)
Kaiser Foundation Health Plan of the Northwest v. Doe
903 P.2d 375 (Court of Appeals of Oregon, 1995)
City of Canby v. Rinkes
902 P.2d 605 (Court of Appeals of Oregon, 1995)
Wooton v. Viking Distributing Co., Inc.
899 P.2d 1219 (Court of Appeals of Oregon, 1995)
J.J. & L. Properties, Inc. v. Henry
858 P.2d 161 (Court of Appeals of Oregon, 1993)
Calbag Metals Co. v. Guy F. Atkinson Co.
770 P.2d 600 (Court of Appeals of Oregon, 1989)
Lindgren v. Berg
749 P.2d 1212 (Court of Appeals of Oregon, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
709 P.2d 727, 76 Or. App. 349, Counsel Stack Legal Research, https://law.counselstack.com/opinion/real-estate-loan-fund-oreg-ltd-v-hevner-orctapp-1985.