Rea v. Pittsburg & Connellsville Railroad

78 A. 73, 229 Pa. 106, 1910 Pa. LEXIS 558
CourtSupreme Court of Pennsylvania
DecidedJuly 1, 1910
DocketAppeal, No. 10
StatusPublished
Cited by35 cases

This text of 78 A. 73 (Rea v. Pittsburg & Connellsville Railroad) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rea v. Pittsburg & Connellsville Railroad, 78 A. 73, 229 Pa. 106, 1910 Pa. LEXIS 558 (Pa. 1910).

Opinion

Opinion by

Mr. Justice Moschzisker,

The plaintiffs claimed compensation for 88,000 square feet of land lying between Greenough street and the yard tracks of the defendant railroad in the city of Pittsburg appropriated by the defendant company in March, 1903. Viewers were appointed April 13, 1903, and awarded $416,000, from which award both sides appealed. The appeals were tried May 4, 1908, and resulted in a verdict for $775,133.33, which the parties agree was composed of $616,000 principal and $159,133.33, compensation for de[112]*112lay in payment. On motion of the defendant the court below granted a new trial, without indicating its reason for so doing. At the retrial on April 5, 1909, a verdict was rendered for $765,893.33, which the parties agree was made up, $616,000 principal and $149,893.33, compensation for delay. Defendant’s motion for a new trial was refused, and it has appealed.

The first question we have to consider is whether the defendant was properly chargeable with compensation for delay. The defendant claims that this case is governed by the rule in Phila. Ball Club v. Phila., 192 Pa. 632, and Stevenson v. Coal Co., 203 Pa. 316, to the effect that where the delay is due to the unconscionably high demands of the claimant no such compensation should be allowed. The facts at bar are quite different from those in the cases relied upon by the defendant. There was no actual taking of property in either of those cases. The ball club case was an instance of a change of grade. A claim for $85,000 was “sought to be supported by theories and testimony of an illegitimate character,” and a verdict obtained for $29,000 was reversed. On a new trial “other theories and testimony were set up in support of a demand for $62,000, quite as indefensible and unreasonable as the demand in the first trial,” and a verdict for $39,000 was cut by the court below to $30,000. But the trial judge had instructed the jury, “You must add to the damages which the plaintiff has suffered reasonable compensation for the detention of those damages.” We said it was manifest that “the oppressive and unreasonable demands of the plaintiff” caused the delay, and reversed, holding that the plaintiff was not entitled to any damages on that score. The Stevenson case was an action of trespass to recover damages for the pollution of a stream with coal dirt, and this court characterized the plaintiff’s claim as “extortionate, unconscionable and incredible.”

In the present case the defendant company took actual possession of the plaintiff’s property in 1903, and has ever since enjoyed whatever revenues there were to be [113]*113derived, therefrom'. At the trial the highest value claimed by the plaintiff was $12.00 a square foot, and the court below states in its opinion refusing a new trial that the jury were not asked for a verdict of more thaii $9.00 a square foot. The defendant in its plea declared the land only to be of a value of $1.00 per square foot, and gave testimony of a value of less than $3.00 a square foot. The jury rendered a verdict of $7.00 a square foot. Both parties appealed from the award of the viewers and all of the seven years’ delay, excepting two months, occurred subsequent to these appeals. In his instructions to the jury the trial judge said: “It is for you to say in the exercise of your sound discretion whether the parties are entitled to compensation for delay in receiving their money. That amount you may give or you may not, just as you conclude .... remembering that as a general principle where there has been delay which is not the fault of the plaintiff, and he has been kept out of his money, for the time lost the jury could give compensation by way of damages. But on the other hand, if it is the plaintiff’s fault and the plaintiff’s own conduct caused the delay, there can be no compensation by way of damages. . . . When you have fixed the market value at so much a foot, compare that with Mr. Rea’s price, and if you are fairly of the opinion and come to a fair and honest conclusion that the difference between the price you fix and the valuation placed by Mr. Rea was so great that you would say that it was an extortionate demand, that it was an inordinate demand, so that the officers of the railroad company were justified in contesting .... then it would be your duty, and I so instruct you, to refuse to give any damages for delay in payment. . . .” And after referring to the testimony, the charge continued: “But if ... . this was merely an honest difference of opinion .... you could give compensation for delay.” These instructions are practically in accord with those approved by us in the case of James v. West Chester Boro., 220 Pa. 490, and with the rule laid [114]*114down in the cases relied upon by the defendants. It could not be said by the trial judge that the delay was due entirely to the size of the demands made by the claimants. The record shows no offer of settlement at any figure, nor do we find any indication therein that reasonably lower demands would have met with payment. The court left the question squarely and fairly to the jury, and we cannot say that there was any error in so doing. In addition to this, the court could not have affirmed the request covered by the first assignment of error, for it states that Henry B. Rea testified before the viewers that the market value of'the property was $15.00 a square foot. As pointed out by the trial judge in his charge, Mr. Rea denied this fact, claiming that he had merely said, “it was worth that to us.” The assignment is overruled.

Although it well may be contended that the verdict approaches the verge of excessiveness, this is not a case which moves us to interfere under the Act of May 20, 1891, P. L. 101. The power conferred upon this court by that act has never been exercised on the plea of the ex-cessiveness of the verdict, except in a most extreme case: Stevenson v. Coal Co., 203 Pa. 316. The question of the amount of the verdict is ordinarily for the court below, and where a grossly excessive amount is returned the trial court should never allow it to stand, no matter how many new trials it may be obliged to grant. The third assignment of error is overruled.

The plaintiffs offered in evidence for the purpose of proving title the deed of the Consolidated Gas Company to Henry Rea, Jr., dated June 21, 1900, showing a consideration of $140,000 paid by the grantee. When Henry B. Rea, one of the claimants, was upon the stand he testified that the value of the property was $12.00 a square foot, which would give a total of $1,056,000, and under cross-examination he was asked, “In June, 1900, what did you or your father pay for this property?” This was objected to, and the objection was sustained. [115]*115The record then discloses that “Counsel for defendant offer on cross-examination to show by the witness for the purpose of testing the credibility of his testimony and the competency of his knowledge as to the value of this property in March, 1903, the fact that his father purchased the property appropriated by the railroad company in question in this case in the month of June, 1900, from the Consolidated Gas Company; that the said company had it upon the market for a number of years for sale, and was able to hold the property until it realized the fair market value of the same, and the price at the date of such purchase for which the said Consolidated Gas Company sold the property to the witness’s father.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. Redevelopment Authority
386 A.2d 1052 (Commonwealth Court of Pennsylvania, 1978)
Klick v. Commonwealth
342 A.2d 794 (Commonwealth Court of Pennsylvania, 1975)
Carlisle Borough Incinerator
71 Pa. D. & C.2d 559 (Cumberland County Court of Common Pleas, 1973)
Atlantic Refining Co. v. Director of Public Works
233 A.2d 423 (Supreme Court of Rhode Island, 1967)
McCue v. Commonwealth, Department of Highways
41 Pa. D. & C.2d 415 (Chester County Court of Common Pleas, 1966)
Rossi v. Commonwealth
39 Pa. D. & C.2d 308 (Luzerne County Court of Common Pleas, 1966)
Kelly v. Redevelopment Authority
26 Pa. D. & C.2d 662 (Alleghany County Court of Common Pleas, 1961)
Dempsey v. Stauffer
197 F. Supp. 260 (E.D. Pennsylvania, 1961)
B. & K., INC. v. Commonwealth
159 A.2d 206 (Supreme Court of Pennsylvania, 1960)
J. C. Grille, Inc. Liquor License Case
124 A.2d 659 (Superior Court of Pennsylvania, 1956)
Epstein v. City and County of Denver
293 P.2d 308 (Supreme Court of Colorado, 1956)
Berger v. Public Parking Authority of Pittsburgh
109 A.2d 709 (Supreme Court of Pennsylvania, 1954)
Berkley v. Jeannette
96 A.2d 118 (Supreme Court of Pennsylvania, 1953)
Lambert v. Durallium Products Corp.
72 A.2d 66 (Supreme Court of Pennsylvania, 1950)
McLendon v. Floyd
1 S.E.2d 466 (Court of Appeals of Georgia, 1939)
Hart's Appeal
199 A. 225 (Superior Court of Pennsylvania, 1938)
Brewer v. Blue Mountain Consolidated Water Co.
191 A. 408 (Superior Court of Pennsylvania, 1937)
Westinghouse Air Brake Co. v. Pittsburgh
176 A. 13 (Supreme Court of Pennsylvania, 1934)
Knickerbocker Lime Co. v. Philadelphia
14 Pa. D. & C. 477 (Philadelphia County Court of Common Pleas, 1930)
Beals v. Centre County
14 Pa. D. & C. 62 (Centre County Court of Common Pleas, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
78 A. 73, 229 Pa. 106, 1910 Pa. LEXIS 558, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rea-v-pittsburg-connellsville-railroad-pa-1910.