Beals v. Centre County

14 Pa. D. & C. 62, 1930 Pa. Dist. & Cnty. Dec. LEXIS 481
CourtPennsylvania Court of Common Pleas, Centre County
DecidedJanuary 14, 1930
DocketNo. 71
StatusPublished

This text of 14 Pa. D. & C. 62 (Beals v. Centre County) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Centre County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beals v. Centre County, 14 Pa. D. & C. 62, 1930 Pa. Dist. & Cnty. Dec. LEXIS 481 (Pa. Super. Ct. 1930).

Opinion

Fleming, P. J.,

The jury has awarded the plaintiff the sum

of $500 as damages to her land, caused by the relocating and building of the State highway, running through Bald Eagle Valley, from Bellefonte to Tyrone. The jury also awarded the plaintiff the further sum of $161.10 as compensation for the detention of moneys found to be due her from April 1, 1925, to Sept. 19, 1929, the date of the verdict. The defendant seeks a new trial and has assigned as reasons therefor the following:

1. The verdict of the jury is excessive.

2. That the verdict of the jury was against the weight of the evidence.

3. That the item of interest in the sum of $161.10 should not have been awarded the plaintiff, for the reason that the delay in this case was caused by reason of plaintiff’s excessive demand for damages, which delay on the part of the defendant was fully justified by the award of the jury, in its award of the principal sum of the damages.

In approaching our consideration of this motion we begin with two conclusions in which we are certain all parties will agree, to wit: (1) That if the verdict of the jury was excessive, it was excessive only to the extent of the sum awarded as damages for delay in payment; and (2) that if the verdict of the jury was against the weight of the evidence, it was only against the weight of such evidence, in so far as the allowance of any compensation for delay is concerned. This brings us, therefore, to a consideration of the third reason assigned, and leaves for our discussion and determination the sole question, viz., Is the plaintiff entitled to the sum of $161.10 awarded her as compensation for delay in payment?

It appears to be a well settled rule that while interest, as such, is not allowed on damages in condemnation proceedings, it is, nevertheless, proper for the jury to consider the lapse of time between the taking of the land and the time of the trial, in making up the damages for which to render a verdict: Hewitt v. Railroad Co., 19 Pa. Superior Ct. 304; Klages v. Phila. & R. T. Co., 160 Pa. 386; Penna. S. V. R. R. Co. v. Ziemer, 124 Pa. 560. It [63]*63is, further, clearly the rule that when the plaintiff by grossly excessive and unreasonable demands makes the delay of payment imperative on the part of the defendant, and thereby causes such defendant to await a verdict before making such payment, no compensation for delay can be recovered by the plaintiff.

In Richards v. Citizens Natural Gas Co., 130 Pa. 37, Justice Mitchell says: “Interest is recoverable of right, but compensation for deferred payment in torts depends on the circumstances of each case. The plaintiff may have set his damages so inordinately high as to have justified the defendant in refusing to pay, or in other ways the delay may be plaintiff’s fault. ... In such cases the jury probably would not, and certainly ought not to make the allowance.”

We must, therefore, carefully scan the circumstances of the instant case in determining the question before us. As an aid or guide therein, let us first consider what has heretofore been said in cases of like nature.

In Stevenson v. Coal Co., 203 Pa. 316, 333, Justice Dean says: “Here, the plaintiff in his statement claimed specifically for the deposit of culm and the interruption of business at mill, $75,000; then, further, for the pollution of the stream and the destruction of about twenty acres of land for agricultural purposes, $25,000, making altogether $100,000. Perhaps the mere averments in the statement would not of themselves be sufficient to warrant the belief of an extortionate demand, for it is a common practice in pleading to fix the amount claimed at a higher sum than the plaintiff is willing to accept or expects to get, but here the unconscionable demand in the statement is followed by a like demand at the trial. The two sons of plaintiff, Charles and William Stevenson, were both called by plaintiff as witnesses and each computed the damages at $100,000. So incredible was their testimony and so exorbitant the demand that the court felt compelled to instruct the jury practically to disregard both. Beyond question, the plaintiff set his demand inordinately high; defendants must resist by litigation with its consequent delays. Therefore, they were excusable in not promptly paying, and should not be subject to a penalty for non-payment. The jury should have been peremptorily instructed that, under these circumstances, damages for detention, not to exceed legal interest, should not be allowed; that they had no discretion in the matter.” In this case the jury had returned a verdict for plaintiff in the sum of $21,000.

In Pierce v. Lehigh Valley Coal Co. (No. 2), 232 Pa. 170, Justice Mestrezat says: “The facts fully warranted the court in disallowing the damages awarded for the detention of the payment of the plaintiff’s claim. As appears by the evidence and as stated by the court, the claim was for $50,000, and it was strongly insisted upon in its entirety at the trial. At no time did the plaintiff offer to reduce the claim or to accept any smaller sum than his original demand. The fact that the verdict in his favor was for only $6200 shows that the demand was excessive, extortionate and unreasonable and one which the defendant was fully warranted in contesting. The officers of the defendant company would manifestly not have been justified in paying the claim. Had they done so, they would have failed to perform their duty and would have been responsible to the company.”

In Trustees of Kingston v. Lehigh Valley Coal Co., 241 Pa. 481, Justice Elkin says: “Appellant also contends that interest should have been allowed by way of compensation for detention. The learned trial judge decided this question against the plaintiff, and very properly so. The demand was grossly [64]*64excessive and unreasonable, as is shown by the verdict returned. The demand was for more than $2,000,000, while the verdict was for a little over $100,000.”

In Rea v. Pittsburg, etc., R. R. Co., 229 Pa. 106, cited by the plaintiff in support of her contention that, inasmuch as defendant failed to show an offer of settlement at any figure or any indication that reasonably lower demands would have met with payment, we find the court quoting with approval the charge of the trial judge as follows: “It is for you to say in the exercise of your sound discretion whether the parties are entitled to compensation for delay in receiving their money. That amount you may give or you may not, just as you conclude, . . . remembering that as a general principle, where there has been delay which is not the fault of the plaintiff, and he has been kept out of his money, for the time lost the jury could give compensation by way of damages. . . . When you have fixed the market value at so much a foot, compare that with Mr. Rea’s price, and if you are fairly of the opinion and come to a fair and honest conclusion that the difference between the price you fix and the valuation placed by Mr. Rea was so great that you would say that it was an extortionate demand, that it was an inordinate demand, so that the officers of the railroad company were justified in contesting, . . . then it would be your duty, and I so instruct you, to refuse to give any damages for delay in payment. . . . But if . . . this was merely an honest difference of opinion, . . . you could give compensation for delay.” In this ease plaintiff’s claim was $1,056,000. At the first trial the verdict was for $616,000 principal and $159,133.33 compensation for detention.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Penn. Schuyl. V. R. v. Ziemer
17 A. 187 (Supreme Court of Pennsylvania, 1889)
Richards v. Citizens Natural Gas Co.
18 A. 600 (Supreme Court of Pennsylvania, 1889)
Klages v. Phila. & Reading Terminal Co.
28 A. 862 (Supreme Court of Pennsylvania, 1894)
Stevenson v. Ebervale Coal Co.
52 A. 201 (Supreme Court of Pennsylvania, 1902)
Rea v. Pittsburg & Connellsville Railroad
78 A. 73 (Supreme Court of Pennsylvania, 1910)
Pierce v. Lehigh Valley Coal Co.
81 A. 142 (Supreme Court of Pennsylvania, 1911)
Trustees of the Proprietors v. Lehigh Valley Coal Co.
88 A. 768 (Supreme Court of Pennsylvania, 1913)
Hewitt v. Pittsburg, Shawmut & Northern Railroad
19 Pa. Super. 304 (Superior Court of Pennsylvania, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
14 Pa. D. & C. 62, 1930 Pa. Dist. & Cnty. Dec. LEXIS 481, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beals-v-centre-county-pactcomplcentre-1930.