Ralph P. Eagerton, Etc. v. Valuations, Inc., and United States Fidelity & Guaranty Company

698 F.2d 1115, 35 Fed. R. Serv. 2d 1546, 1983 U.S. App. LEXIS 30325
CourtCourt of Appeals for the Eleventh Circuit
DecidedFebruary 22, 1983
Docket80-7926
StatusPublished
Cited by46 cases

This text of 698 F.2d 1115 (Ralph P. Eagerton, Etc. v. Valuations, Inc., and United States Fidelity & Guaranty Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ralph P. Eagerton, Etc. v. Valuations, Inc., and United States Fidelity & Guaranty Company, 698 F.2d 1115, 35 Fed. R. Serv. 2d 1546, 1983 U.S. App. LEXIS 30325 (11th Cir. 1983).

Opinion

JAMES C. HILL, Circuit Judge:

This is a contract dispute between state and county agencies and a real estate appraisal firm and its surety. 1 The parties involved are non-diverse and no federal question is presented. Prior to trial, plaintiffs alleged that the case was properly in federal court as an “ancillary” action to Weissinger v. Boswell, 330 F.Supp. 615 (M.D.Ala.1971). The district court exercised jurisdiction and ^warded plaintiffs $296,488.10 in damages for the appraisal firm’s breach of contract. The deféndants did not question the court’s jurisdiction, nor did they raise the issue on appeal. A member of this panel raised the question of subject matter jurisdiction at oral argument, and the parties were requested to file supplemental briefs on the issue. Having considered the question thoroughly, we conclude that the district court did not have subject matter jurisdiction to hear this case under the doctrine of ancillary jurisdiction.

I.

In Weissinger, a three judge district court determined that Alabama’s ad valorem property tax was unconstitutional because corporate property was assessed at a substantially higher percentage of fair market value than other property in the state. The court therefore ordered that the property be reassessed to attain the proper equalization. 2 Pursuant to this order, the Alabama Legislature passed an act requiring the reappraisal of all property within the state for ad valorem tax purposes within two years of the Act’s effective date of *1117 January 9,1972. 3 To implement the legislature’s command, plaintiffs Hale and Greene Counties separately contracted with Valuations, Inc. to perform the necessary property reappraisal. These contracts were uniform documents approved by the state. In accordance with the terms of the contracts, United States Fidelity & Guaranty Company (“U.S.F. & G.”) executed separate performance and payment bonds to guarantee completion of Valuations’ undertaking in each of the counties. Valuations, in turn, subcontracted all of the mapping and appraisal duties to Allied Appraisal Company and subcontracted all necessary aerial photography work to Tobin Research, Inc.

The contract originally called for Valuations to submit invoices on a monthly basis to the Commissioner of Revenue who would then approve or disapprove the charges. Upon this approval, the county then would disburse the payments quarterly, but would withhold a ten percent retainage to be paid upon satisfactory completion of the project. At Valuations’ request, county payments became a monthly practice so that subcontractors could be paid promptly for their services.

The Hale County contract was scheduled to be completed on June 1, 1975. On or about May 1,1975, however, work reached a standstill because of payment disputes among the subcontractors. On May 11, 1975, the Commissioner of Revenue approved an invoice for the period of September 30, 1974, through May 1, 1975, and sent the approval to the county for payment June 9, 1975. The invoice was received by the chairman of the Hale County Commission who decided on his own not to make payment because of the standstill. Upon this refusal, the state sent Valuations a default notice on June 17,1975, and allowed Valuations ten days to provide a firm schedule for completion. By then, however, Valuations had closed its offices in the area. The contract was between 50 and 80 percent completed when the work stopped.

The Greene County contract was to be completed by July 31, 1976. On July 30, 1975, the state sent Valuations notice that there was substantial evidence that progress was insufficient to complete the required work by the date of completion. 4 Again Valuations was given ten days to provide a firm completion schedule. Instead, Valuations responded by shutting down its operations in Greene County on or about September 1, 1975. A formal declaration of default was conveyed to Valuations on September 17, 1975. On September 8, 1975, however, the Commissioner of Revenue received an invoice from Valuations covering the period December 1, 1974 through July 31, 1975. The invoice was approved and forwarded to the county on September 15, 1975. The then Acting County Attorney individually refused to make payment. The Greene County contract was between 20 and 40 percent completed upon its termination by the state.

In 1977, both projects were relet to another appraisal company at a higher price than the original contract with Valuations. Plaintiffs then initiated this action against Valuations and U.S.F. & G. for the full penal sums on each of the bonds on January 14,1977. The district court found that Valuations breached both contracts by failing to respond to the notices of default with a firm schedule for completion. The court also found, however, that the individual county officials, who withheld payment from Valuations on state approved invoices, acted without proper authority. Nevertheless, neither improper withholding constituted a breach of the contract by the counties because Valuations, by an established course of dealings, indicated its assent to accept payments one to three months after *1118 submission of the invoice. The counties, therefore, were not in arrears when the contracts were formally revoked, and Valuations thus was unjustified in failing to perform the remaining work. The total cost of completion, which was the amount paid to Valuations and to the replacement appraisal company less the original contract price, was awarded to plaintiffs. Upon motion of U.S.F. & G., this amount was reduced to the amount of the surety’s bonds.

II.

Neither party nor the district court explored the question of subject matter jurisdiction. Indeed, the issue was mentioned only once. In a pre-trial conference, the parties reached a consensus that the present dispute simply was “another Weissinger case,” involving the supervision of the Weissinger order. 5 Nevertheless, it is well established that subject matter jurisdiction cannot be waived or conferred on a court by consent of the parties. E.g., American Fire & Casualty Co. v. Finn, 341 U.S. 6, 17-18, 71 S.Ct. 534, 541-542, 95 L.Ed. 702 (1951); People’s Bank v. Calhoun, 102 U.S. 256, 260-61, 26 L.Ed. 101 (1880); Lowry v. International Brotherhood, 259 F.2d 568, 575 (5th Cir.1958). Subject matter jurisdiction is an issue which can and must be raised by the court at any level of the proceeding. Fed.R.Civ.P. 12(h)(3); e.g., City of Indianapolis v. Chase National Bank, 314 U.S. 63, 69, 62 S.Ct. 15, 16, 86 L.Ed. 47 (1941); Texas v. Florida,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Curtis Solomon
136 F.4th 1310 (Eleventh Circuit, 2025)
United States v. Ismael Camacho
Eleventh Circuit, 2023
VVIG, Inc. v. Alvarez
S.D. Florida, 2019
Forster v. Nations Funding Source, Inc.
648 F. App'x 850 (Eleventh Circuit, 2016)
Anago Franchising, Inc. v. SHAZ, LLC
677 F.3d 1272 (Eleventh Circuit, 2012)
Richard S. Gallaher v. United States
271 F. App'x 946 (Eleventh Circuit, 2008)
United States v. Straub
508 F.3d 1003 (Eleventh Circuit, 2007)
Rosemary C. Riley v. Fairbanks Capital Corporation
222 F. App'x 897 (Eleventh Circuit, 2007)
Nichols v. CITIGROUP GLOBAL MARKETS, INC.
364 F. Supp. 2d 1330 (N.D. Alabama, 2004)
Harris v. United States
149 F.3d 1304 (Eleventh Circuit, 1998)
Hawthorne v. Mac Adjustment, Inc.
140 F.3d 1367 (Eleventh Circuit, 1998)
North Central F.S., Inc. v. Brown
951 F. Supp. 1383 (N.D. Iowa, 1996)
Sandlin v. Corporate Interiors Inc.
972 F.2d 1212 (Tenth Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
698 F.2d 1115, 35 Fed. R. Serv. 2d 1546, 1983 U.S. App. LEXIS 30325, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ralph-p-eagerton-etc-v-valuations-inc-and-united-states-fidelity-ca11-1983.