Racer v. Wingate

36 N.E. 538, 138 Ind. 114, 1894 Ind. LEXIS 13
CourtIndiana Supreme Court
DecidedFebruary 13, 1894
DocketNo. 16,545
StatusPublished
Cited by11 cases

This text of 36 N.E. 538 (Racer v. Wingate) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Racer v. Wingate, 36 N.E. 538, 138 Ind. 114, 1894 Ind. LEXIS 13 (Ind. 1894).

Opinions

Coffey, J.

On the 4th day of June, 1891, Charles A. Rhine, as drainage commissioner, charged with the construction of a public ditch described in the record in this case, filed a report in the Blackford Circuit Court. So much of the report as is necessary to the controversy here, is as follows: “Comes now Charles A. Rhine, drainage commissioner, charged with the construction of said drain, and shows and reports to the court that Henry C. Paul, to. whom the contract for the construction of said ditch was awarded, has fully and completely constructed said ditch according to the contract for the construction thereof heretofore entered into between said Paul and a former drainage commissioner charged with the construction of said ditch, and according to the plans and specifications heretofore adopted and approved by this court.”

To this report the appellants, who are assessed to pay for the construction of the ditch, filed exceptions upon which issues were formed. The cause was tried by the court, resulting in a special finding of the facts upon which the court stated conclusions of law, and rendered judgment for the appellees, approving and confirming the report above set forth.

The assignment of error calls in question the correctness of the conclusions stated by the trial court upon the facts found. The sole question involved in the case is the question as to whether there should be an adjudication on the facts found by the trial court to the effect that the ditch described in the finding has been completed according to the plans and specifications. The question of the sum to be paid to the contractor is not [116]*116involved except incidentally. He is not a party to this suit. He receives his pay from the commissioner of drainage. As the report of the commissioner in this case contains the statement that the ditch has been completed according to the plans and specifications, it is not doubted that its approval by the court would constitute such an adjudication of that fact as would preclude every one from disputing it, so that the contractor would become entitled to receive the full contract price for the work whether he has, in fact, complied with his contract, or has violated it. <. In this incidental way, and in no other, is the amount to be paid to the contractor involved.

It is not claimed by either party to this suit, that the ditch in controversy has been completed according to the plans and specifications adopted by the court for its construction. It has been solemnly declared by this court time and again that those who pay the assessments have the right to insist upon the construction of the work as it has been established by' the report of the commissioners, and by the judgment of the court. It has, furthermore, been held that it is not to be presumed that the court would approve the final report of the commissioner and strike the cause from the docket until satisfied that the work had been completed according to its order. Indianapolis, etc., Gravel Road Co. v. State, ex rel., 105 Ind. 37; Fries v. Brier, 111 Ind. 65; Smith v. State, ex rel., 117 Ind. 167.

The finding of the court “that such open ditch, as constructed, has been completed by the contractor,” does not show that the work has been done according to the plans and specifications, or according to the order of the court, and is not, therefore, sufficient to authorize a conclusion of law that the commissioner is entitled' to a judgment approving his report.

[117]*117The court carefully omits to find that the work has been done according to its judgment or order, or according to the plans and specifications. Indeed it could not make such a finding in view of the preceding facts found. The facts found make it plain that there was almost a total disregard of the order directing the work. The plans and specifications, as well as the order of the court, required the ditch to be constructed with banks sloping one foot to each foot in depth. They also required that the dirt removed from the ditch should be placed at least two feet from each bank, and given a slope of one foot to each foot in depth. The finding shows that neither of these requirements has been complied with by the contractor. The banks were cut perpendicular, and while the dirt removed from the ditch was placed the required distance from the banks it was not given the required slope. The purpose of these requirements is easily and well understood, and involves matters of which we take judicial notice. It is well settled that the courts take notice of matters of common notoriety, as well as of the ordinary laws of nature. Am. and Eng. Ency. of Law, vol. 12, p. 195.

It is a well known fact that a current of water striking a perpendicular bank will ordinarily create a concave, thus causing the bank to fall. In the case of a ditch, we must take notice, we think, that the falling in of the banks would tend to fill it and obstruct the flow of the water, and thus lessen its usefulness. The purpose, therefore, of requiring the banks of this ditch to be given a slope of one foot to each foot in depth was to prevent the cutting and falling in of the banks, which would otherwise occur.

The purpose of requiring the dirt removed to be placed at least two feet from the banks of the ditch, and given the slope named in the plans and specifications, was to [118]*118prevent it from falling back into the ditch from which it was removed. With the perpendicular banks constantly-cutting and falling, by the action of the water, we have no assurance that the dirt deposited on the banks will not soon be reached, and that it will not fall into and obstruct the ditch. The plans and specifications were designed to prevent these results, and the order of the court required that they should be observed. There is no pretense that they have been complied with, and yet we are asked to solemnly adjudge that the work has been performed according to the plans and specifications. If we adjudge that the commissioner of drainage is, under these facts, entitled to have his report approved, which sets forth that the work has been completed according to the plans and specifications adopted by the court, we adjudge that a thing is true which appears upon the face of our judgment to be untrue. We cán not consistently say by our judgment that this ditch has been completed according to the plans and specifications when the contrary appears on the face-of our record.

'We do not think the appellants can complain simply because the ditch may be constructed with greater capacity than that contemplated by the plans and specifications, but they have just cause to complain, we think, if the banks of the ditch and the dirt excavated are not given the required slope, if thereby the value of the ditch to those who are required to pay for it is lessened.

It is said, however, that it appears from the special finding of facts that the ditch constructed by the contractor is larger than the ditch called for by the plans and specifications, and as beneficial to those who are to be assessed to pay for it, as it would have been had the order of the court been followed, and therefore they can not be heard to complain.

In answer to this position we would say (1) that there [119]*119is no finding of the court that the ditch, as constructed, is as beneficial to those assessed for its payment as it would have been had it conformed to the plans and specifications. Such a conclusion is a mere inference from the fact that it is wider than the one called for.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Board of Commissioners v. Summy
140 N.E. 913 (Indiana Supreme Court, 1923)
People v. Campisi
26 N.Y. Crim. 219 (Appellate Division of the Supreme Court of New York, 1911)
Monaghan v. Vanatta
122 N.W. 610 (Supreme Court of Iowa, 1909)
Karr v. Board of Commissioners
85 N.E. 1 (Indiana Supreme Court, 1908)
Mak-Saw-Ba Club v. Coffin
82 N.E. 461 (Indiana Supreme Court, 1907)
Boswell v. City of Marion
79 N.E. 1056 (Indiana Court of Appeals, 1907)
Ralya v. E. C. Atkins & Co.
61 N.E. 726 (Indiana Supreme Court, 1901)
Borders v. Williams
57 N.E. 527 (Indiana Supreme Court, 1900)
Shrack v. Covault
43 N.E. 229 (Indiana Supreme Court, 1896)
Stafford v. State ex rel. Rhine
40 N.E. 701 (Indiana Court of Appeals, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
36 N.E. 538, 138 Ind. 114, 1894 Ind. LEXIS 13, Counsel Stack Legal Research, https://law.counselstack.com/opinion/racer-v-wingate-ind-1894.