Monaghan v. Vanatta

122 N.W. 610, 144 Iowa 119
CourtSupreme Court of Iowa
DecidedOctober 2, 1909
StatusPublished
Cited by8 cases

This text of 122 N.W. 610 (Monaghan v. Vanatta) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Monaghan v. Vanatta, 122 N.W. 610, 144 Iowa 119 (iowa 1909).

Opinion

Ladd, J.

A bayou three and eight-tenths miles long curved to the southeast, and then back to the southwest, flowing through a narrow channel into the Missouri River. This channel was crossed by a wagon bridge six hundred feet from the river and the hayou by the railroad bridge about a mile further north. Into the north end of the bayou emptied an old county ditch, which extended to the north seven thousand four hundred feet, and beyond it was “Mule” slough. By appropriate proceedings the board of supervisors of Fremont County established a drainage district and ordered the construction of a bulkhead across the channel, with flood gates, to prevent the water backing from the river into the bayou, the widening of the channel to the width of eighteen feet for a distance of about one thousand feet from the river, the excavation of a ditch six feet wide and two and one-half feet deep for a distance of about one thousand three hundred feet long, through a bench of land north of the railroad bridge and across an arm of the hayou, extending east and north, and which held the water back when medium or low. It also directed that the county ditch be widened to twenty feet and deepened from one to three feet, and that a ditch he excavated through Mule slough varying in width from twenty to four feet. This order was in pursuance of a report of the engineer, appointed by the board of supervisors, filed with the county auditor and accompanied with plat and profile of the proposed improvements, together with estimates of their probable cost. There were several laterals concerning which there is no controversy. The work was completed in 1907, and the disparity between the preliminary estimates of the engineer and his final report of the actual cost was such as to lead to the investigation involved in this 'action. On the part of plaintiff it is contended that the main ditch [122]*122extending from the north end of the bayou was exc'avated deeper and wider than the specifications called for, and that no charge should be made for the excess, and that much of the work in the bayou was not included in the contract, and that, if directed or approved by the engineer, this was the result of collusion and fraud between him and the contractors. In response to these charges the contractors assert that, even though the main ditch may have been excavated wider and deeper than indicated in the specifications, the engineer- rejected any excess over that called for in making the measurements, so that the main 'ditch cost no more according to the final report than it would have had it been no wider and the bottom no lower than .the line estimated in their preliminary survey. They further assert that the® preliminary report was uncertain and indefinite as to the amount of excavation in the bayou, and that they performed the work under the direction of the engineer, and should be compensated therefor.

1. Drainage: liability for work of construction. I. The dispute as to the main ditch first may be disposed of. In the final report the engineer certified that about one-third more earth was removed than had been estimated in the preliminary report on which the hoard of supervisors acted in ordering ^ improvement. This is a large discrepancy, and indicates either that the work of the preliminary survey was not performed as carefully as it should have been, or that the final report is incorrect. It appears that the elevations were taken at points one thousand feet apart in making the preliminary survey, and, of course, those of the ground intervening were merely inferred. The preliminary report was but of estimates, while that finally made was, if properly prepared, a statement of accurate measurements of what had been done. Some differences between the two- were to be anticipated, and that these are large will not alone justify the inference that there was fraudulent collusion between the engineer and contractors. [123]*123If tbe number of cubic yards reported as excavated in tbe engineer’s final report was actually removed, and in measuring the same be included therein nothing below tbe grade line established in tbe preliminary report as the bottom of tbe ditch nor any of tbe excess in width, then tbe plaintiffs are not entitled to relief. In tbe practical work of excavating ditches tbe depth and width often vary, and all that is required is that tbe ditch be constructed in substantial conformity with the specifications. Tbe complaint here is not that the work was improperly done, but that tbe contractors have'been allowed by the engineer for ■ excavating deeper or wider than was contemplated by tbe original report and profile. Tbe engineer testified that in tbe final report nothing of the excavation below the grade line established by the preliminary survey nor of any excess in width was included. The evidence was undisputed, ' and therefore we necessarily reach tbe conclusion that tbe plaintiffs are not entitled to relief with respect to any work done on the main ditch.

II. Tbe following extract from tbe report of the engineer clearly indicates tbe work which was to be done in the bayou:

The outlet from the bayou is a small channel under the above-mentioned highway bridge. During the time of high water in tbe river the water is held back in the bayou; in fact, tbe bayou fills up with backwater from tbe river. Tbe water level in tbe bayou will vary several feet according to tbe stage of the river. Tbe backwater from tbe river can be kept out of tbe bayou by a bulkhead across tbe channel fitted with gates, which, when closed, will close tbe channel and when open will allow the water to drain from tbe bayou, tbe bottom of tbe gates to be set so as to lower tbe water in tbe bayou from elevation of one hundred and one and thirty-five-one-hundredths, its present stage, at elevation ninety-nine. A design for a bulkhead with an estimate of cost accompanies this report. To put in tbe bulkhead will necessitate tbe removal of tbe highway bridge and replace that with an embankment, and [124]*124build a twenty-foot bridge across the channel leading to the bulkhead. This channel should be eighteen feet wide and about one thousand feet long. It is nineteen thousand and eighty-three feet or three and eight-tenths miles from the mouth of the bayou to its northern end, where the county ditch empties into it. It has a fall of four and six-tenths feet in the distance. From the river to the crossing under the C. B. & Q. bridge No. 5, a distance of one mile, the channel is several hundred feet wide. From the railroad bridge an arm of the bayou bears east and north close to the highway. There is a bench of land across this arm extending from the railroad bridge north about one thousand three hundred feet, which bench holds water above it, during medium and low stages of water in bayou below. A channel six feet wide and two and one-half feet deep should be cut through this bar. The building of the bulkhead and the cutting through the bar will, in my opinion, preclude the possibility of flooding any of the land to the west of the bayou during flood periods and will afford good drainage to the land at all times.

In the same report are the estimates of cost: “Excavating outlet channel (3000 cu. yd. at 30c.) $900. . . . Excavating channel in bayou above railroad bridge (725 cu. yds. at 40c.) $290.” And summarizing, under the heading “Bayou and Outlet”: “Length of outlet channel, one thousand feet. Length of channel above railroad, one thousand three hundred feet. . . . Excavation above bridge seven hundred and twenty-five cu. yds.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rodman v. Ladwig
274 N.W. 1 (Supreme Court of Iowa, 1937)
Dashner v. Woods Bros. Construction
217 N.W. 464 (Supreme Court of Iowa, 1928)
Gjellefald v. Drainage District No. 42
212 N.W. 691 (Supreme Court of Iowa, 1927)
Miller v. City of Glenwood
188 Iowa 514 (Supreme Court of Iowa, 1920)
Humboldt County v. Ward Bros.
145 N.W. 49 (Supreme Court of Iowa, 1914)
Barz v. Sawyer
141 N.W. 319 (Supreme Court of Iowa, 1913)
Littell v. Webster County
152 Iowa 206 (Supreme Court of Iowa, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
122 N.W. 610, 144 Iowa 119, Counsel Stack Legal Research, https://law.counselstack.com/opinion/monaghan-v-vanatta-iowa-1909.