Gjellefald v. Drainage District No. 42

212 N.W. 691, 203 Iowa 1144
CourtSupreme Court of Iowa
DecidedMarch 15, 1927
StatusPublished
Cited by4 cases

This text of 212 N.W. 691 (Gjellefald v. Drainage District No. 42) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gjellefald v. Drainage District No. 42, 212 N.W. 691, 203 Iowa 1144 (iowa 1927).

Opinion

*1145 Albert, J.

The Graettinger Tile Works is an intervener in this action on certain claims held by it against appellee, O. N. Gjellefald, but, as these matters were all determined in another case, and its only interest in this case is the application of the funds obtained by Gjellefald in this case against the drainage district, we will give this matter of the petition of intervention no further consideration.

In September, 1919, the board of supervisors of Osceola County, Iowa, duly established its codefendant herein, the Drainage District No. 42, under the drainage laws of the state of Iowa. It advertised for bids for labor and material to construct the improvement m said drainage district. In pursuance thereof, on the ¿ay 0£ September, 1919, the appellee, Gjellefald, filed his written bid for labor and material to construct said improvement. Ilis general bid was for the sum of $143,010. It also contained the following provisions:

“Intake material $1 per inch in size of -tile. * * * Over-depth 50% above attached schedule. Underdepth in proportion to bid.”

To this bid was attached a schedule, covering all tile from 5 inches to 48 inches in diameter, together with the charge for laying said tile at different depths. The bid thus made by Gjellefald -was accepted by the board. Later, the county auditor purported to draw a contract for labor and material, which was made in two contracts, one to cover labor and the other to cover the material. These were forwarded by mail to Gjellefald, who signed same and returned them to the county auditor. It appears that, in preparing these written contracts, the county auditor did not, in terms, follow the accepted bid. With reference to the inlets, the contract read as follows:

“It is further bargained and agreed that the inlet material for all direct inlets additional to those specified in Notice to Contractors, etc., will be furnished by second party [Gjellefald] upon the basis of one dollar per inch of diameter of inlet. ’ ’

At this point, it is argued that this paragraph of the eon-, tract should be reformed by striking out the words ‘ ‘ additional to those specified in the Notice to Contractors. ’ ’ As to- this matter, the contract written varied from the accepted bid in this: *1146 that in the bid it read, “Overdepth 50% above attached schedule. ’ ’ In the contract, as written, it reads:

“It is hereby stipulated and agreed that 50% of the prices specified in Exhibit A [the schedule attached to the bid] hereto attached shall be the schedule for ■ additional services, if any, performed by the second party in excavating for and installing tile at depths additional to those specified in the existing plans. ’ ’

It is argued that the contract should be reformed to correspond to the bid: in other words., that for overdepth work the pay should be 50- per cent above the schedule prices, instead of 50 per cent of the schedule price.

At the time in controversy herein, there was no. provision whatever in the drainage laws of Iowa specifying or providing for or authorizing the making of such contracts as were made in this case. It is a well settled principle of law that, in these public improvements, where there is no provision for the making of contracts, that the bid made, with its acceptance by the proper municipal body, constitutes the contract. City of Ft. Madison v. Moore, 109 Iowa 476; Hedge v. City of Des Moines, 141 Iowa 4; Capital City B. & P. Co. v. City of Des Moines, 152 Iowa 354; 13 Corpus Juris 289.

Under these mies, the real contract between these parties, therefore, was the bid made, and the acceptance by the board. It is also apparent from the record that, when the written contracts were attempted to be made, in the respects above pointed out they varied from the contract as actually made by the bid and acceptance. The testimony in the case overwhelmingly shows that, when 'these written contracts were made, it was the intention of all parties that they should correspond in all respects with the bid.

In Day v. Dyer, 171 Iowa 437, at 450, .this court said:

“We find this doctrine laid down in the books: that, whenever it clearly appears that the written instrument, drawn professedly to carry out the agreement -of the parties previously entered into, is executed under the misapprehension that it really embodies the agreement, whereas, by a mistake of the draughtsman, either as to fact or law, it fails to fulfill that purpose, equity will correct the mistake by reforming the instrument in accordSnce with the previous agreement.”

In Merriam v. Leeper, 192 Iowa 587, the court said:

*1147 “It is a general rule in equity that a party to a written contract may not escape the obligations thereof by merely showing that he failed to read the same, and therefore failed to discover some of its provisions. * * * Such is not the case before us. The minds of these parties had previously met, and their contract had been reduced to writing. Their mutual rights and liabilities were therefore defined by such written contract. There' is no claim of any mistake in such contract. There were no later negotiations looking to a new contract. * * * True, it was competent for the parties to the antecedent contract to modify the same by subsequent negotiations, and such modification could properly have been included in the notes and mortgages. But there were no negotiations between the parties looking to any modification of the original contract.”

So in this case, these parties had made a complete contract when the bid was accepted by the board, and if, in their attempt subsequently to make a written contract covering this contract, errors crept into it which were detrimental to the interests of the contractor, there is no reason why the same should not be corrected in equity. As tending to support this conclusion, see Stelpflug v. Wolfe, 127 Iowa 192; Fullerton v. City of Des Moines, 147 Iowa 254; Hyde Park Inv. Co. v. Glenwood Coal Co., 170 Iowa 593; Merriam v. Leeper, supra.

We are quite satisfied, under the evidence and record in this case, that the district court was warranted in reforming this contract to make it correspond to the bid. This being true, the district court rightfully determined the amounts due appellee for the intakes and also for the overdepths.

A dispute has also arisen as to charges for a certain bulkhead put in at the end of the tile drain where it empties into the open ditch. The engineer in charge admits that in his proposed settlement he omitted this, and the only dispute is as to the amount thereof. It was provided for in the original plans and specifications; and, of course, the contractor is entitled to pay therefor. The weight of the evidence in the case satisfies us that the action of the district court was right, in making the allowance he did therefor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCarter v. Uban
166 N.W.2d 910 (Supreme Court of Iowa, 1969)
Gordon Construction Co. v. Board of Supervisors
72 N.W.2d 551 (Supreme Court of Iowa, 1955)
Haugen v. Humboldt-Kossuth Joint Drainage District No. 2
1 N.W.2d 242 (Supreme Court of Iowa, 1941)
Pospishil v. Jensen
219 N.W. 507 (Supreme Court of Iowa, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
212 N.W. 691, 203 Iowa 1144, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gjellefald-v-drainage-district-no-42-iowa-1927.