Capital City Brick & Pipe Co. v. City of Des Moines

152 Iowa 354
CourtSupreme Court of Iowa
DecidedJuly 11, 1911
StatusPublished
Cited by1 cases

This text of 152 Iowa 354 (Capital City Brick & Pipe Co. v. City of Des Moines) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Capital City Brick & Pipe Co. v. City of Des Moines, 152 Iowa 354 (iowa 1911).

Opinion

Per Curiam.

The case was before us on a former appeal, the opinion being found in 136 Iowa, 243. Prom the opinion in' that case, in which a judgment in favor of the plaintiff was reversed, it appears that the reversal was based on the ground that the trial court failed to submit to the jury the question whether plaintiff’s claim was presented to the board of public works in accordance with the provisions of the contract before the allowance and payment by the city of the final estimate under the contract; it being provided in the contract as follows: “All claims against the city of Des Moines for damages growing out of the performance of this contract, or for any tort, or alleged wrongful act of the city, shall be presented to the board of public works of the city of Des Moines by the party of the first part, and such claims must be adjusted and settled and a release in full for all damages against the city must be signed by the party of the first part, before the estimates above specified will be allowed, or other payments made under this contract, and any claim not so presented shall be deemed waived and action thereon barred.” There was in the contract a provision quoted in [357]*357full in the former opinion to the effect that the specified contract price should be in full compensation for the cost of the entire work, and the city should not be liable to the party of the first part for extras of any kind, nor for any damage which it might sustain by coming in contact with rock, etc., or any other unforeseen material or obstruction; it being strictly understood that the contract price specified should be in full for all work and material furnished under the contract. But, as pointed out in the former opinion, there was an addendum to the contract in which it was agreed that in case the surface of the rock was found to be otherwise than as shown by the plans and borings represented in the proposal for bids, and the first party was put to extra expense in order to make a suitable foundation, then said first party should be compensated for such extra work as provided in the specifications for the compensation of extra work upon the order of the city engineer. In the former opinion it was held that the compensation for which plaintiff sued on account of extra work rendered necessary by the fact that there was rock to be' removed before reaching bed rock for the purpose of laying the foundations of the abutments and piers not shown by the borings was recoverable under this addendum.

The contentions for the city now are that, first, this addendum was added to the contract without authority of law; and, second, that, even if this addendum was valid, the claim for compensation thereunder was not presented to the board of public works as required by the portion of the contract above set out.

The argument that the addendum was invalid is predicated upon the thought that the rights and liabilities of the plaintiff must be determined by the plans and specifications under which its bid was made, and that it was not' competent afterwards to add to or vary such rights or liabilities by mutual contract between the parties. It may be conceded that under statutes requiring contracts [358]*358to be let to the lowest bidder -the city council can not substantially vary the terms and conditions of a contract entered into under competitive bids, for to do so would be to destroy the advantage intended to be secured by such method of entering into the contract. Hedge v. Des Moines, 141 Iowa, 4. The legal notice for proposals for bids for the work in question given by the board of public works under authority of the city council advised prospective bidders that sealed proposals would be received by the board at its office in the city hall until 10 o’clock a. m. on the 14th day of December, 1901, for the described improvement, “according to plans and specifications to be found on file in the offices of the city4 engineer and the board of public works after December 1,- 1901.” The only reference in this notice to any contract was in a provision that payment for the work was to be made in warrants drawn on the bridge fund “in such amounts and at such times as are specified by the terms of the contract therefor, a 'draft of which may be found on file in the office of said board of public works on or before the 14th day of December, 1901.” It is evident that the sealed proposals were to have reference to the plans and specifications, and not to the contract, save as to amounts and times of payment, and the obligations of the plaintiff under its bid must be determined by the bid itself and the plans and specifications. In the plans and specifications it was provided that the site of the structure would be carefully surveyed and marked on the ground for examination by borings made on the center line of the structure as shown on the plans, and that the foundations for the abutments and piers should be carried to solid rock. The plans showed five borings, and indicated the different kinds of soil which had been encountered in excavating for the piers and abutments as shown by these borings.

[359]*359 x. Municipal corporations: public improvement: contracts: extra compensation

[358]*358When, therefore, the plaintiff on the acceptance of [359]*359its bid proceeded with the work, and in excavating for the piers and abutments encountered rock which it was necessary to remove which had not been indi- - , 1 _ .. í»it» catea in the description oi the borings, it 1 , was entitled to compensation for the extra - exPense involved, unless the right to. such-compensation was in some way cut off or forfeited under the terms of some valid contract entered into between the parties after the bids were made.

tract- when concluded. The acceptance of the plaintiff’s hid by defendant city, which constituted the conclusion of a contract between the parties (for the city had reserved the right under the notice for. proposals to reject any and all bids), consisted of the action of the . . council m approving the contract and 'bond of the plaintiff, which contract contained the addendum already referred to, added to it after the plaintiff’s sealed proposals had been signed. Now, it is - clear that until the contract was approved plaintiff’s bid had not been accepted, and that the contract, as approved, constituted the only contract under which the plaintiff could proceed with the work, or the defendant could insist on the work being done; and the only question involved in the modification of the form of the contract was as to whether in its terms it so far departed from the plans and specifications that it was more favorable to the plaintiff than the contract which would have arisen by the simple acceptance of the plaintiff’s proposal, without reference to the terms of the contract.

As has already been indicated, while the plans and specifications were to be on file on and after December 1, the contract was not to be on file until December 14, on which day, at 10 o’clock a. m., the sealed proposals must be on file, and it is not to be assumed that the sealed proposals were to be made with reference to the terms of the contract except as to amounts and times of payment. [360]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gjellefald v. Drainage District No. 42
212 N.W. 691 (Supreme Court of Iowa, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
152 Iowa 354, Counsel Stack Legal Research, https://law.counselstack.com/opinion/capital-city-brick-pipe-co-v-city-of-des-moines-iowa-1911.