Pyle v. Kernan

36 P.2d 580, 148 Or. 666, 1934 Ore. LEXIS 195
CourtOregon Supreme Court
DecidedSeptember 14, 1934
StatusPublished
Cited by16 cases

This text of 36 P.2d 580 (Pyle v. Kernan) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pyle v. Kernan, 36 P.2d 580, 148 Or. 666, 1934 Ore. LEXIS 195 (Or. 1934).

Opinion

BELT, J.

In July, 1929, the state highway commission called for bids on a contract to resurface 12 miles *668 of the Roosevelt coast highway between Riverton and Bandon, in Coos county, and to furnish 15,400 yards of broken stone for highway construction purposes. The specifications called for Tupper rock, that is, rock to be obtained from a certain quarry located near Ban-don. The commission considered the bids excessive and therefore rejected them. The following month a second call for bids was made. Pursuant to this call the following bids were submitted: Guy Pyle and the Newport Construction Co., $144,802; the defendant, P. J. Kernan, $153,400; and Joplin & Elden, $155,220. Plaintiffs being the lowest bidder, the contract was awarded to them. In accordance with the rules and regulations of the commission, the plaintiffs accompanied their bid with a bond in amount equal to 5 per cent of the total amount of the bid. Within three or four days after the award was made on the 29th day of August, the plaintiffs began preliminary work and, much to their surprise and dismay, found that Tupper rock is extremely hard and that it was not practicable to crush it for highway construction purposes. Three different compressors were used to determine whether this rock could be satisfactorily crushed but none of them could do the work. A ton and a half of the rock was shipped to Portland for experimental purposes and the tests made proved that the rock could not be crushed without excessive cost. Engineers of the highway commission also made a thorough test of the rock and found that the complaint of the contractors was well founded. In this preliminary work the plaintiffs expended approximately $3,000.

Continued negotiations relative to a change of the plans and specifications — in which the plaintiffs, the defendant and the highway commission engineers participated — finally culminated in a meeting at a hotel *669 in Coquille, on December 6,1929, where it was verbally agreed between the plaintiffs and the defendant that the latter would take over the contract if Umpqua river gravel were substituted for Tupper rock and that Kernan would pay $3,000 to the plaintiffs for the assignment of the award to him. Engineers of the commission who were in attendance at this meeting testified in support of the plaintiffs as to the understanding and agreement of the parties. Kernan had a dredge and other machinery at Reedsport near the mouth of the Umpqua river and was well equipped to carry out the contract if the substitution were made. Under this proposed change, the gravel would be taken from the river and shipped by train to Coquille where it would be placed on barges and carried down the Coos river to various landings and then hauled by trucks where needed. The matter was formally considered by the commission on December 12, 1929, as thus evidenced by its minutes:

“Ross Newport and Guy Pyle, the successful bidder on the Riverton-Bandon-South resurfacing projection which bids were received on August 29, 1929, stated that they had attempted by various methods to work the rok in the government quarry at Bandon but were unable to drill it on account of its hardness. Mr. Newport stated that they had made a thorough search for other quarries in the vicinity but had found no prospect of sufficient quantity complying with the specifications except the Norway quarry south of Coquille. The Engineer stated that he confirmed the opinion of Mr. Newport that it was imprctical to drill the rock in the Bandon quarry after checking the methods and equipment used by the contractors. Also the department’s engineers had made an exhaustive search for suitable rock to substitute but had found no deposits in the vicinity of the project. As to the Norway quarry satisfactory rock could be secured there if the soft strata were screened out, but because of its location, a long truck haul over an improved highway would be neees *670 sary which would he objectionable, particularly in the winter months. Mr. Newport stated that if gravel from the Umpqua river was accepted in lieu of rock, that he could make arrangements to assign his contract to F. J. Kernan who would do the work under the same specifications and at the same price, Kernan’s plan being to dredge the gravel from the Umpqua river, load into cars at Eeedsport, ship by rail to Coquille, there unload into barges, which would be towed down the river to various landings below Eiverton, and there hauled out on the road in trucks. The Engineer recommended that the substitution of gravel be permitted and an assignment of the contract to Kernan be accepted. Matter taken under consideration. ’ ’

On the following day the commission approved the proposed alteration and the assignment of the award.

Plaintiffs insisted upon reducing their verbal agreement with defendant to writing before making assignment of the award. Hence the following letter of defendant to them under date of January .17,1930:

“In confirmation of our agreement relative to the assignment by you of your right and interest in and to the award of the contract covering the re-surfacing of 12 miles of the Eoosevelt Coast Highway between Eiverton and Bandon in Coos county, and the furnishing of 15,400 cubic yards of broken stone for highway construction purposes, and in consideration of said assignment I hereby agree to pay you the sum of $3,000, which said sum is to be paid out of the fourth estimate of funds earned by me under said contract, provided that in the event there are not sufficient funds in the fourth estimate to permit the payment of the full amount of the said $3,000 the balance shall be paid out of the immediately succeeding estimate or estimates of money earned for work accomplished under said contract; provided further that in the event there are not four estimates then said sum shall be paid out of the final estimate.”

*671 After receipt of the above letter, the plaintiffs made an assignment of the award and a contract for performance of the work was thereupon executed. Thereafter, in accordance with the revised plans and specifications, the construction work was completed and Kernan was paid in full for the same. The latter, however, failed and refused to pay plaintiffs for the assignment of the award. Hence this action.

The cause was submitted to the court without a jury and a judgment was rendered in favor of the plaintiffs for $3,000, together with interest thereon at 6 per cent per annum from June 30, 1930. From this judgment defendant appeals.

Defendant’s motion for directed verdict is based upon three propositions which will be considered in the order stated: (1) That the agreement for assignment of the award is without consideration in that, at the time it was executed, plaintiffs had no vested rights in the contract as no bond for performance had been filed within ten days after the contract was prepared by the commission and submitted to the plaintiffs for execution; (2) That the agreement to pay the plaintiffs $3,000 is contrary to public policy in that its effect is to prevent free bidding and tends towards the stifling of competition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lowes v. Thompson
374 Or. 23 (Oregon Supreme Court, 2025)
Bagley v. Mt. Bachelor, Inc.
340 P.3d 27 (Oregon Supreme Court, 2014)
Compton v. Compton
66 P.3d 572 (Court of Appeals of Oregon, 2003)
A-1 Sandblasting & Steamcleaning Co. v. Baiden
643 P.2d 1260 (Oregon Supreme Court, 1982)
Harrell v. Travelers Indemnity Co.
567 P.2d 1013 (Oregon Supreme Court, 1977)
W. J. Seufert Land Co. v. Greenfield
496 P.2d 197 (Oregon Supreme Court, 1972)
Home Owners Construction Co. v. Borough of Glen Rock
169 A.2d 129 (Supreme Court of New Jersey, 1961)
Ohio Casualty Insurance v. Mallison
354 P.2d 800 (Oregon Supreme Court, 1960)
Evans v. Ideal Brick & Brikcrete Manufacturing Co.
1955 OK 205 (Supreme Court of Oklahoma, 1955)
Worlton v. Davis
249 P.2d 810 (Idaho Supreme Court, 1952)
Hanna v. Bd. of Ed. of Wicomico Co.
87 A.2d 846 (Court of Appeals of Maryland, 1952)
Chesnutt v. Schwartz
12 N.E.2d 912 (Appellate Court of Illinois, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
36 P.2d 580, 148 Or. 666, 1934 Ore. LEXIS 195, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pyle-v-kernan-or-1934.