Public Service Company of New Mexico v. New Mexico Public Regulation Commission

444 P.3d 460
CourtNew Mexico Supreme Court
DecidedMay 16, 2019
DocketNO. S-1-SC-36115
StatusPublished
Cited by26 cases

This text of 444 P.3d 460 (Public Service Company of New Mexico v. New Mexico Public Regulation Commission) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Public Service Company of New Mexico v. New Mexico Public Regulation Commission, 444 P.3d 460 (N.M. 2019).

Opinion

VIGIL, Justice.

*466{1} This appeal arises from the final order of the New Mexico Public Regulation Commission (Commission) granting part, but not all, of the increase in retail electric rates sought by the Public Service Company of New Mexico (PNM) in Case No. 15-00261-UT. The Commission's final order is appealed by PNM and cross-appealed by the Albuquerque Bernalillo County Water Utility Authority (ABCWUA), New Energy Economy (NEE), and the New Mexico Industrial Energy Consumers (NMIEC). On appeal, PNM, NEE, ABCWUA, and NMIEC all raise numerous issues with the Commission's final order. In this opinion we address challenges made to the Commission's decisions regarding Palo Verde Nuclear Generating Station, the installation of balanced draft technology at San Juan Generating Station, the new coal supply agreement at Four Corners Power Plant, the inclusion of Rate 11B in rate banding, PNM's prepaid pension asset, and the adoption of Method A.

{2} With respect to Palo Verde, PNM appeals the Commission's denial of recovery in its rate base for (1) the repurchase of 64.1 MW of Palo Verde Unit 2 capacity at a valuation of $2,550/kW; (2) $49 million in improvements made to Palo Verde Unit 2; and (3) future recovery for nuclear decommissioning costs. In separate cross-appeals, NEE and ABCWUA each challenge the Commission's decision to allow PNM to recover for the repurchased 64.1 MW at a net book value of $1,306/kW and for the cost of renewing five leases at Palo Verde. We additionally address ABCWUA's argument that the Commission violated its right to due process by refusing to reopen the proceedings to allow replies to PNM's response to a bench request regarding Palo Verde.

{3} We also answer the remaining challenges to the Commission's final order: PNM's appeal to the Commission's decision to deny recovery of $52.3 million for the installation of balanced draft technology at San Juan Generating Station; NEE's claim that the Commission acted unreasonably and unlawfully by allowing recovery of $19.5 million for the new coal supply agreement at Four Corners Power Plant; ABCWUA's challenge to the Commission's decision to reject PNM's proposal to exclude Rate 11B from rate banding; and NMIEC's arguments that the Commission acted unreasonably or unlawfully by allowing recovery of $137.8 million for PNM's prepaid pension asset and by adopting the Method A rate adjustment.

{4} We reject each of the arguments on appeal except one: we conclude that, by denying PNM any future recovery for its nuclear decommissioning costs related to the Palo Verde capacity at issue in this case, the Commission denied PNM due process of law. Therefore, we declare all other aspects of the Commission's final order to be lawful and reasonable, yet must annul and vacate the final order in its entirety pursuant to NMSA 1978, Section 62-11-5 (1982). See Hobbs Gas Co. v. N.M. Pub. Serv. Comm'n , 1993-NMSC-032, ¶ 6, 115 N.M. 678, 858 P.2d 54 (concluding that the Court may declare parts of an order to be reasonable and lawful while vacating an order in its entirety pursuant to Section 62-11-5 ). We remand the case to the Commission for further proceedings as required and the entry of an order consistent with this opinion. See Hobbs , 1993-NMSC-032, ¶ 6, 115 N.M. 678, 858 P.2d 54 (recognizing that on remand "the Commission may properly enter an order embodying those provisions in the earlier, vacated order that have been declared reasonable and lawful"); Pub. Serv. Co. v. N.M. Pub. Serv. Comm'n , 1979-NMSC-042, ¶¶ 13, 24, 92 N.M. 721, 594 P.2d 1177 (remanding to the Commission for the entry of an order based on substantial evidence and acknowledging that the Commission may conduct additional hearings as necessary).

I. BACKGROUND

{5} The complexity of this case compels us to begin our opinion by setting forth a brief overview of the procedural history as well as the relevant legal background. See New Energy Economy v. Pub. Regulation Comm'n , 2018-NMSC-024, ¶ 2, 416 P.3d 277. Additional background is provided as necessary in our discussion.

*467A. Procedural Background

{6} On August 27, 2015, PNM filed an application with the Commission claiming a revenue requirement of approximately $123 million. In accordance with its procedural rules, the Commission appointed a hearing examiner to preside over the ratemaking proceedings and submit a recommended decision to the Commission. See 1.2.2.29(B), (D)(4) NMAC. Nearly twenty parties filed motions to intervene in the proceedings and, in a public hearing lasting three weeks and a two day supplemental hearing, over forty witnesses presented testimony on PNM's proposed rate increase.

{7} After the hearing examiner issued her corrected recommended decision and the parties filed their exceptions to her recommendations, the Commission issued its final order that incorporated and adopted the corrected recommended decision except as expressly modified or disapproved. The Commission's final order approved a revenue increase of $61.2 million. The appeal and cross-appeals are taken directly from that order. See NMSA 1978, § 62-11-1 (1993) ("Any party to any proceeding before the [C]ommission may file a notice of appeal in the [S]upreme [C]ourt asking for a review of the [C]ommission's final orders.").

B. Legal Principles Governing Rate Cases

{8} We next set forth the general legal principles which apply to the setting of retail electric rates by the Commission. The Commission has the general and exclusive power to regulate a public utility's rates under NMSA 1978, Section 62-6-4(A) (2003). A utility's rates are generally based upon the utility's revenue requirement, the traditional elements of which are "(1) determination of the costs of the operation, (2) determination of the rate base which is the value of the property minus accrued depreciation, and (3) determination of the rate of return." Hobbs Gas Co. v. N.M. Pub. Serv. Comm'n

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
444 P.3d 460, Counsel Stack Legal Research, https://law.counselstack.com/opinion/public-service-company-of-new-mexico-v-new-mexico-public-regulation-nm-2019.