Albuquerque Bernalillo County Water Utility Authority v. New Mexico Public Regulation Commission

2010 NMSC 013, 229 P.3d 494, 148 N.M. 21
CourtNew Mexico Supreme Court
DecidedMarch 19, 2010
Docket31,268, 31,273
StatusPublished
Cited by91 cases

This text of 2010 NMSC 013 (Albuquerque Bernalillo County Water Utility Authority v. New Mexico Public Regulation Commission) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Albuquerque Bernalillo County Water Utility Authority v. New Mexico Public Regulation Commission, 2010 NMSC 013, 229 P.3d 494, 148 N.M. 21 (N.M. 2010).

Opinions

OPINION

MAES, Justice.

{1} Albuquerque Bernalillo County Water Utility Authority (ABCWUA) and New Mexico Industrial Energy Consumers (NMIEC) appeal from the Final Order of the New Mexico Public Regulation Commission (the PRC), claiming that the PRC improperly awarded an emergency fuel and purchased power cost adjustment clause to the Public Service Company of New Mexico (PNM) under NMSA 1978, Section 62-8-7(E)(l) (2003, as amended through 2007) and 17.9.550.1 to 550.17 NMAC (Recompiled 12/30/2001) (hereinafter Rule 550). We affirm the Final Order of the PRC.

I. FACTS AND PROCEDURAL HISTORY

{2} On February 21, 2007, PNM filed a rate case with the PRC seeking a rate increase and a fuel and purchased power cost adjustment clause (FPPCAC) pursuant to Section 62-8-7(E)(l) and Rule 550. A FPPCAC “flow[s] through to the users of electricity the increases or decreases in Applicable Fuel and Purchased Power costs,” Rule 550.6(D) NMAC and, therefore, “provide[s] for the stability of utility earnings when electric fuel costs and purchased power costs are rising and permit[s] prompt credits to customers when electric fuel costs and purchased power costs are declining.” Rule 550.6(B). Rule 550.17(A)(l)-(3) provides that “[n]o utility shall have a FPPCAC included in its tariff’ unless the utility demonstrates that

(1) the cost of fuel and purchased power are a significant percentage of the total cost of service;
(2) the cost of fuel and purchased power contains costs which periodically fluctuate and cannot be precisely determined in a rate case;
(3) the utility’s fuel and purchased power policies and practices are designed to assure that electric power is generated and purchased at the lowest reasonable cost.

See also § 62 — 8—7(E)(1) (providing that FPPCACs must be “consistent with the purposes of the Public Utility Act, including serving the goal of providing reasonable and proper service at fair, just and reasonable rates to all customer classes”).

{3} The PRC assigned the case to a hearing examiner. See NMSA 1978, § 8-8-4(C)(3)(a) (1998). On March 6, 2008, following extensive discovery and two weeks of hearings, the hearing examiner issued a Recommended Decision, which included proposed findings and a recommendation that PNM’s request for a FPPCAC should be denied because PNM had failed to fulfill the regulatory requirements set forth in Rule 550. Specifically, the hearing examiner found that (1) it is doubtful whether PNM’s fuel and purchased power costs constitute a significant percentage of the total cost of service, (2) PNM failed to establish that its fuel mix “consists of fuels with volatile or [fluctuating] prices” and that “its fuel and purchased power costs are so unpredictable that they cannot be calculated in a rate case and call for an FPPCAC instead,” and (3) the proposed FPPCAC fails to provide reasonable and proper service at fair, just and reasonable rates and is not designed to ensure that electric power is generated and purchased at the lowest reasonable cost. See Rule 550.17(A)(l)-(3). Thirteen days later, PNM filed exceptions to the Recommended Decision, claiming, in relevant part, that it was entitled to a FPPCAC under Rule 550. See 1.2.2.37(C)(1)(a) NMAC (09/01/2008).

{4} On March 20, 2008, PNM and the International Brotherhood of Electrical Workers, Local No. 611, filed a joint motion requesting an Emergency FPPCAC.1 Attached to the joint motion was the affidavit of Charles N. Eldred, Executive Vice President and Chief Financial Officer of PNM. Eldred averred that, following the issuance of the Recommended Decision rejecting PNM’s request for a FPPCAC, PNM’s credit rating was downgraded, its stock price hit a fifty-two week low, and it was unable “to access the commercial paper market” or “to issue long term debt.” Eldred expressed his belief that a FPPCAC “is absolutely necessary if PNM is to avoid further deterioration of its credit rating to junk bond status.”

{5} The Emergency FPPCAC differed materially from the FPPCAC previously submitted to the hearing examiner. Specifically, the Emergency FPPCAC contained the following conditions suggested by the Attorney General and the PRC’s Utility Division Staff (Staff): “(a) ... prior approval of purchased power agreements (‘PPAs’) with terms greater than one year; (b) replacement power due to plant outages [would] not be recovered through the FPPCAC; and, (c) demand charges [would] not be recovered through the FPPCAC.” Additionally, the Emergency FPPCAC contained other

conditions which are designed to mitigate the impact on customer bills during peak periods and provide additional incentives to PNM management to control costs to the extent they are controllable. Among them are that the fuel factor charged pursuant to the Emergency FPPCAC will be capped at $.01 per [kilowatt] and that replacement power costs due to plant availability lower than a weighted average plant availability factor cannot be recovered without prior approval of the [PRC]. Also included in the Emergency FPPCAC is a condition that all costs recovered through it will be subject to audit and refund if the costs are determined by the [PRC] to have been imprudently incurred.

{6} In light of the serious financial concerns raised by PNM, the PRC established the following expedited procedural schedule for the consideration and review of the Emergency FPPCAC.

Public Notice March 31, 2008
PNM Direct Testimony March 28, 2008
Deadline for intervention April 8, 2008
StaffTntervenor Testimony PNM Rebuttal Testimony April 9, 2008 April 14, 2008
Hearing April 15, 2008

Additionally, the PRC severed the Emergency FPPCAC from the underlying rate case, reasoning that “the Emergency FPPCAC essentially is a new FPPCAC that is significantly different from the FPPCAC [previously] proposed by PNM” and that “the record [in the rate case] is now closed.”2 Although the PRC established a new docket number for the Emergency FPPCAC, No. 08-00092-UT, it noted that it would, “of course, take administrative notice of any evidence relevant to the Joint Motion and the Emergency FPPCAC that is in [the rate case] to the extent permitted by 17.1.2.37(D) NMAC.” The PRC also ordered PNM to address certain issues in its direct testimony and suspended the implementation of the Emergency FPPCAC “until and including May 7, 2008.”

{7} ABCWUA and NMIEC filed objections to the expedited procedural schedule and a joint motion for extension of time, requesting sixty days from the filing of PNM’s direct testimony to file a response. Essentially, they requested “that the deadline for the fifing of their testimony be extended to at least May 27, 2008, or approximately 48 days beyond the original April 9 deadline.” ABCWUA and NMIEC claimed that the expedited procedural schedule did “not allow the Staff and Intervenors sufficient time to propound discovery and adequately analyze PNM’s responses before the fifing deadline for their own testimony,” thereby effectively denying them due process of law. The PRC entered a procedural order extending the deadline five days, to April 14.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bourdon v. Vigil
New Mexico Court of Appeals, 2025
Greenham v. Greenham-Rodriguez
New Mexico Court of Appeals, 2023
Flora v. Village of Corrales
New Mexico Court of Appeals, 2023
Beecher Carlson Ins. Serv. v. Catechis
New Mexico Court of Appeals, 2023
Franklin v. N.M. Dep't of Pub. Safety
New Mexico Court of Appeals, 2022
Elephant Butte Irrigation Dist. v. N.M. Water Quality Control Comm'n
516 P.3d 231 (New Mexico Court of Appeals, 2022)
Citizens for Fair Rates & the Env't v. NMPRC
New Mexico Supreme Court, 2022
City of Las Cruces v. N.M. Pub. Regul. Comm'n
New Mexico Supreme Court, 2021
Benavidez v. Bernalillo Cnty. Bd. of Comm'rs
2021 NMCA 029 (New Mexico Court of Appeals, 2020)
Abrams v. Martinez
New Mexico Court of Appeals, 2019
N.M. Indus. Energy Consumers v. N.M. Pub. Regulation Comm'n
2019 NMSC 015 (New Mexico Supreme Court, 2019)
Public Serv. Co. of N.M. v. N.M. Pub. Regulation Comm'n
2019 NMSC 012 (New Mexico Supreme Court, 2019)
Ronna Lyn Ueber v. Anthony James Ueber
Court of Appeals of Tennessee, 2019

Cite This Page — Counsel Stack

Bluebook (online)
2010 NMSC 013, 229 P.3d 494, 148 N.M. 21, Counsel Stack Legal Research, https://law.counselstack.com/opinion/albuquerque-bernalillo-county-water-utility-authority-v-new-mexico-public-nm-2010.