This text of 652 P.2d 1200 (General Telephone Co. of the Southwest v. Corporation Commission) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Telephone Co. of the Southwest v. Corporation Commission, 652 P.2d 1200, 98 N.M. 749 (N.M. 1982).

Opinion

OPINION

FEDERICI, Justice.

In 1980, General Telephone of the Southwest (GTSW), filed an application with the New Mexico State Corporation Commission (SCC) requesting that tariff charges proposed by GTSW become effective December 31, 1980. The proposed changes in the tariffs were to produce additional intrastate revenues of $2,280,201.00. The SCC suspended the proposed changes pending investigation and hearings pursuant to N.M. Const., Art. XI, §§ 7 and 8. Before any hearings were held, the SCC informally advised GTSW that it had arrived at a revenue deficiency of $694,545.00. The parties stipulated to a rate design allocating the $694,545.00 deficiency, with GTSW reserving the right to contest the deficiency proposed by the SCC.

The SCC approved the intervention of the Lea County Board of County Commissioners, the City of Hobbs, the City of Loving-ton, the City of Eunice and the City of Jal (Intervenors). The Intervenors sought to produce evidence that the quality of service provided by GTSW in the areas represented by the Intervenors was inadequate.

Hearings were conducted in April and May of 1981, and GTSW and the SCC each presented expert witnesses who testified as to GTSW’s revenue requirements. The Intervenors presented evidence of quality of service through customers of GTSW and through an expert witness.

The SCC entered its final order on June 1, 1981, concluding that the rates proposed by GTSW were unreasonable and that such rates should only be increased by $694,-545.00. GTSW filed its petition for an order of removal to this Court, which petition was granted. The cause was submitted to this Court in final form in February 1982.

In these removal proceedings, GTSW presents the following points:

1. The SCC’s use of “estimated” separation factors to arrive at GTSW’s rate base and expenses was arbitrary and capricious and contravenes the mandate of N.M.Const., Art. XI, § 7, that “due consideration shall be given to the * * * investment and expenditure as a- whole within the State.”
2. The SCC’s determination of GTSW’s cash working capital was arbitrary and capricious and radically departs from past practice without reasonable justification in the record.
3. The SCC’s determination of GTSW’s net operating income by trending both local and intrastate toll service revenues was arbitrary, capricious and not supported by credible evidence.
4. The SCC erred in its determination of GTSW’s federal income tax expense through the use of the “double leverage” theory.
5. The SCC’s application of the “double leverage” theory to determine the appropriate rate of return on the value of GTSW’s invested capital resulted in rates which are unreasonably low and confiscatory, thereby denying GTSW due process of law prescribed by the Fourteenth Amendment to the Constitution of the United States and N.M.Const., Art. II, § 20.
6. The SCC’s application of the “double leverage” theory to determine GTSW’s appropriate rate of return on the value of its invested capital in New Mexico denied GTSW the equal protection of the laws under the Fourteenth Amendment.
7. The SCC’s application of the “double leverage” theory to determine a reasonable rate of return, and the corresponding adjustment to fixed charges (interest) taken as a deduction in calculating federal income tax for ratemaking purposes, was not supported by the record and was, in fact, contrary to the evidence.
8. The SCC arbitrarily refused to recognize over $2 billion in GTE common equity in its application of the double leverage theory.
9. The rate of return granted by the SCC was so low as to result in confiscation of GTSW’s property in violation of the Fourteenth Amendment to the Constitution of the United States and N.M. Const., Art. II, § 20 and was wholly contrary to the evidence.
10. The SCC improperly considered the “expert testimony” of its staff witness in arriving at a rate of return for GTSW.
11. The SCC had no authority to penalize a utility for reasons relating to quality of service in a ratemaking proceeding and, in any event, in purporting to do so the SCC violated GTSW’s right to due process of law.

The SCC rejected GTSW’s toll-leveling adjustment which resulted in a mismatch of test period revenues, investment and expenses, by utilizing end-of-period investment and expenses with average period return. The SCC adopted an adjustment designed to provide a proper matching for test period purposes.

The SCC rejected the separation ratios recommended by GTSW since those ratios distorted test period operations by reflecting only the average relationship between interstate and intrastate operations during the test period. The SCC accepted a methodology which annualized separation ratios for purposes of the test period.

The SCC rejected GTSW’s federal income tax calculation in favor of a calculation derived by utilizing GTSW’s double leverage capital structure and cost of debt at December 31, 1980, so as to be more reflective of the actual taxes required to be paid by GTSW.

The SCC rejected GTSW’s proposed cash working capital allowance derived by means of the arbitrary formula approach. The SCC accepted a cash working capital allowance based upon a methodology that gives more recognition to the existence of time lags which work in favor of the company as well as those which work against it, and thus is more reflective of the actual cash working capital requirements of GTSW.

The SCC considered the evidence regarding cost of common equity capital and determined from that evidence that the zone of reasonableness for a fair rate of return on common equity lay between 13.8% and 16%. In determining the actual point within the zone at which rates should be set, the SCC indicated that the inadequate service being rendered by GTSW required a return at the low end of the zone, i.e., 13.8%. However, the SCC provided an incentive to GTSW to improve service by indicating that a higher return within the zone is proper when adequate service is being provided.

The SCC rejected any adjustment to the return on equity for market pressure, market break, and flotation costs, since the record indicated that such an adjustment would provide excessive revenues to GTSW and that GTSW would incur no costs for which the adjustment was intended to compensate.

The SCC rejected use of GTSW’s booked capital structure and instead opted for a double leveraged capital structure in order that the ultimate stockholders of GTSW, i.e., the investors in the marketplace, would earn no more on their equity investment in GTSW than the market cost of equity. The SCC determined that such a capital structure was necessary to prevent discrimination against companies which do not engage in double leveraging as well as to prevent excessive returns at the expense of ratepayers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

El Paso Elec. Co. v. N.M. Pub. Regul. Comm'n
New Mexico Supreme Court, 2026
Public Serv. Co. of N.M. v. N.M. Pub. Regulation Comm'n
2019 NMSC 012 (New Mexico Supreme Court, 2019)
Qwest Corp. v. New Mexico Public Regulation Commission
2006 NMSC 042 (New Mexico Supreme Court, 2006)
New Mexicans for Free Enterprise v. City of Santa Fe
2006 NMCA 007 (New Mexico Court of Appeals, 2005)
In Re Citizens Utilities Co.
769 A.2d 19 (Supreme Court of Vermont, 2000)
PNM Gas Services v. New Mexico Public Utility Commission
1 P.3d 383 (New Mexico Supreme Court, 2000)
Zia Natural Gas Co. v. New Mexico Public Utility Commission
2000 NMSC 011 (New Mexico Supreme Court, 2000)
US West v. Utilities and Transp. Com'n
949 P.2d 1337 (Washington Supreme Court, 1998)
US West Communications, Inc. v. Utilities & Transportation Commission
949 P.2d 1337 (Washington Supreme Court, 1997)
U S West Communications, Inc. v. New Mexico State Corp. Commission
1997 NMSC 031 (New Mexico Supreme Court, 1997)
Matter of Held Orders of US West
943 P.2d 1007 (New Mexico Supreme Court, 1997)
AA Oilfield Service, Inc. v. New Mexico State Corp. Commission
881 P.2d 18 (New Mexico Supreme Court, 1994)
US West Communications, Inc. v. New Mexico State Corp. Commission
865 P.2d 1192 (New Mexico Supreme Court, 1993)
Mountain Fuel Supply Co. v. Public Service Commission
861 P.2d 414 (Utah Supreme Court, 1993)
Hobbs Gas Co. v. New Mexico Public Service Commission
858 P.2d 54 (New Mexico Supreme Court, 1993)
Mountain States Telephone & Telegraph Co. v. New Mexico State Corp.
715 P.2d 1332 (New Mexico Supreme Court, 1986)
Rates & Charges of Mountain States Tel. & Tel.
715 P.2d 1332 (New Mexico Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
652 P.2d 1200, 98 N.M. 749, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-telephone-co-of-the-southwest-v-corporation-commission-nm-1982.