MOUNTAIN STATES ETC. v. Dept. of Pub. Serv.

624 P.2d 481
CourtMontana Supreme Court
DecidedFebruary 5, 1981
Docket80-099
StatusPublished
Cited by1 cases

This text of 624 P.2d 481 (MOUNTAIN STATES ETC. v. Dept. of Pub. Serv.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MOUNTAIN STATES ETC. v. Dept. of Pub. Serv., 624 P.2d 481 (Mo. 1981).

Opinion

624 P.2d 481 (1981)

MOUNTAIN STATES TELEPHONE AND TELEGRAPH COMPANY, a Colorado Corporation, Plaintiff and Appellant,
v.
The DEPARTMENT OF PUBLIC SERVICE REGULATION, Montana Public Service Commission et al., Defendants and Respondents.

No. 80-99.

Supreme Court of Montana.

Submitted January 12, 1981.
Decided February 5, 1981.
Rehearing Denied March 4, 1981.

*482 Hughes, Bennett, Kellner & Sullivan, Helena, J. Walter Hyer, III, argued, Denver, Colo., for plaintiff and appellant.

Calvin K. Simshaw, argued, M.P.S.C., Helena, James C. Paine, Montana Consumer Counsel, Helena, John Allen, argued, Consumer Counsel, Helena, for defendants and respondents.

HASWELL, Chief Justice.

This is an appeal by Mountain States Telephone & Telegraph Company (Mountain Bell) from a judgment of the District Court in a utility rate case. The Montana Public Service Commission (PSC) granted Mountain Bell an annual rate increase totalling $3,097,000 as compared to the $11.83 million sought. The District Court concurred. We affirm.

Mountain Bell petitioned the PSC for utility rate increases that would generate $11.83 million additional yearly revenues from its Montana customers. PSC granted interim rate increases of $2,326,000 pending its final decision which are not at issue in this appeal. PSC's final order granted Mountain Bell an annual revenue increase of $3,097,000 in increased charges for its services to its Montana customers.

Mountain Bell petitioned the District Court of Lewis and Clark County for judicial review of PSC's final order pursuant to the Montana Administrative Procedures Act. Subsequently Mountain Bell elected to proceed under Montana Public Utilities Act (Section 69-3-401, MCA et seq). The District Court's pretrial order narrowed the issues to two: (1) PSC's application of the "double leverage" adjustment in determining the cost of capital in Mountain Bell's rate base, (2) PSC's "NARUC" tax adjustment.

The District Court received the transcript of proceedings before the PSC, heard additional evidence, and remanded the case to the PSC for reconsideration on the basis of the additional evidence. The PSC reconsidered, affirmed its previous final order, and returned the case to the District Court. The District Court affirmed PSC's final order holding (1) that the "double leverage" concept was lawful, was applied within the statutory authority of the PSC, and was supported by substantial evidence, and (2) that the "NARUC" tax adjustment was within the statutory authority of the PSC and was supported by substantial evidence.

Mountain Bell appealed from the judgment of the District Court, abandoning the issue of the "NARUC" tax adjustment.

The sole issue on appeal is the legality of PSC's "double leverage" adjustment in determining the cost of capital in Mountain Bell's rate base.

Before considering the arguments of Mountain Bell, an understanding of the capital structure of Mountain Bell and its parent company, AT&T is necessary. The "double leverage" adjustment, as applied here, is premised on the PSC's consideration of the parent-subsidiary financial relationship and its effect on the cost of capital in Mountain Bell's rate base.

It is a basic principle of utility regulation that a utility is entitled to receive a fair and reasonable rate of return on its investment in plant and equipment used to provide its services to the public. In determining a fair and reasonable rate of return, it is necessary to determine what it costs the utility to secure the required capital to finance its operations. This "cost of capital" approach to utility ratemaking involves determining the composite cost of the several types of the utility's capital, properly weighted on the basis of an appropriate *483 capital structure. New England Telephone & Telegraph Co. v. Public Utility Commission (1978), Me., 390 A.2d 8, 32. The "cost of capital" involves not only the interest the utility must pay on its borrowed capital (debt), but also the cost of attracting purchasers of its common stock (equity). A regulatory commission such as the PSC must authorize utility rates sufficient to cover the utility's cost of debt and cost of equity, but no more, or the utility's customers will be paying excessive rates for the services the utility provides.

In this case Mountain Bell's capital structure as reflected in its books indicates that it is funded 44.65% by borrowed funds (debt) and 55.35% by sale of its common stock (equity). Because Mountain Bell is partially financed by debt and partially financed by equity, Mountain Bell's common stockholders are said to be "leveraged" to the extent that the cost of its debt is less than the (weighted) cost of its capital. In other words, Mountain Bell's common stockholders are "leveraged" because Mountain Bell is paying less interest on its borrowed funds than the return it makes on the use of its borrowed funds. This is leverage # 1.

But in this case there is a second or "double leverage" enjoyed by the common stockholders of AT&T arising out of the parent-subsidiary relationship between AT&T and Mountain Bell. When this case was heard by the PSC, AT&T owned 88.55% of the common stock of Mountain Bell, with the balance being held by minority stockholders. Thus the common stockholders of AT&T are "double leveraged": first, because the cost of debt in AT&T's capital structure is less than the return it makes on the use of its borrowed funds; and second because it derives the benefit of similar leverage in Mountain Bell's own capital structure by reason of its 88.55% ownership of Mountain Bell's common stock.

The PSC found that if the "cost of capital" in Mountain Bell's rate base was considered in isolation without regard to the "double leverage" enjoyed by AT&T's common stockholders, it would result in an excessive return to AT&T's common stockholders at the expense of Montana utility ratepayers. To correct this inequity, the PSC applied a "double leverage" adjustment in determining the "cost of capital" in Mountain Bell's rate base.

In summary form, the PSC applied the "double leverage" adjustment in this manner:

(1) PSC determined that the capital structure of Mountain Bell was composed of 45.65% debt (borrowed funds) and 55.35% equity (common stock) as reflected in its books.

(2) PSC determined that an 11.25% return on the capital invested in Mountain Bell was a fair and reasonable rate of return.

(3) PSC determined that if Mountain Bell had been funded in the open market the weighted cost of Mountain Bell's capital would have been 9.47%, figured as follows:

                      % of                     Weighted
Type  of Capital   Capitalization      Cost       Cost
Debt                 44.65%       X   7.26%  =   3.24%
Common Stock         55.35%       X  11.25%  =   6.23%
                    _______                      _____
                    100.00%                      9.47%

(4) PSC determined that 88.55% of Mountain Bell's equity is owned by AT&T whose weighted cost of capital is 9.86% figured as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

General Telephone Co. of the Southwest v. Corporation Commission
652 P.2d 1200 (New Mexico Supreme Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
624 P.2d 481, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mountain-states-etc-v-dept-of-pub-serv-mont-1981.