Public Citizen, Inc. v. FERC

92 F.4th 1124
CourtCourt of Appeals for the D.C. Circuit
DecidedFebruary 16, 2024
Docket22-1251
StatusPublished
Cited by16 cases

This text of 92 F.4th 1124 (Public Citizen, Inc. v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Public Citizen, Inc. v. FERC, 92 F.4th 1124 (D.C. Cir. 2024).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued October 10, 2023 Decided February 16, 2024

No. 22-1251

PUBLIC CITIZEN, INC., PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

NOPETRO LNG, LLC, INTERVENOR

On Petition for Review of Orders of the Federal Energy Regulatory Commission

Nandan M. Joshi argued the cause for petitioner. With him on the briefs was Scott L. Nelson.

Elizabeth F. Benson and Ankit Jain were on the brief for amici curiae Citizens for Pennsylvania’s Future, et al. in support of petitioner.

Moneen Nasmith, Elizabeth Livingston de Calderon, Jordan Luebkemann, and Bradley Marshall were on the brief for amici curiae North Port St. Joe Project Area Committee, Inc., et al. in support of petitioner. 2

Matthew J. Glover, Senior Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. On the brief were Matthew R. Christiansen, General Counsel, Robert H. Solomon, Solicitor, and Anand Viswanathan, Attorney. Robert M. Kennedy, Jr. entered an appearance.

Jennifer L. Key argued the cause for intervenor and adopts the respondent’s brief.

Jeremy C. Marwell and Christopher J. Terhune were on the brief for amicus curiae New Fortress Energy Inc. in support of respondent.

Before: KATSAS, PAN, and GARCIA, Circuit Judges.

Opinion for the Court filed by Circuit Judge GARCIA.

GARCIA, Circuit Judge: In 2021, Nopetro LNG, LLC (“Nopetro”) sought to build a liquefied natural gas (“LNG”) facility in Port St. Joe, Florida. Nopetro requested a ruling from the Federal Energy Regulatory Commission that the planned facility falls outside the Commission’s regulatory jurisdiction under Section 3 of the Natural Gas Act. The Commission granted Nopetro’s request and issued a declaratory order, which it sustained on rehearing. Public Citizen, a nonprofit consumer-advocacy organization, seeks review of the Commission’s determination. Before oral argument, however, the Commission informed us—and Nopetro confirmed—that Nopetro had abandoned its plans to build the facility. We therefore dismiss Public Citizen’s petition for review as moot and vacate the Commission’s orders. 3

I. Section 3 of the Natural Gas Act governs the import and export of natural gas, as well as the construction and operation of certain LNG facilities. See 15 U.S.C. § 717b. Section 3(e)(1) of the Act gives the Commission “exclusive authority to approve or deny an application for the siting, construction, expansion, or operation of an LNG terminal.” Id. § 717b(e)(1). In April 2021, Nopetro filed a petition for a declaratory order with the Commission. In relevant part, the petition requested a ruling that the company’s proposed LNG facility in Port St. Joe falls outside the Commission’s Section 3(e)(1) jurisdiction because, in Nopetro’s view, the facility does not meet the statutory definition of an “LNG terminal.” See id. § 717a(11). In March 2022, the Commission issued a declaratory order to that effect. After Public Citizen requested rehearing, the Commission issued a second order in July 2022 that sustained its initial determination. Public Citizen filed a petition for review of those orders on behalf of its members who live and work in the Port St. Joe community. Those members claim that they would suffer economic, environmental, and aesthetic injuries if Nopetro were to build the facility. We granted Nopetro leave to intervene in the appeal. On October 2, 2023, after the parties completed briefing, the Commission informed us that a senior Nopetro official stated publicly in July 2023 that the company would “no longer pursue the [Port St. Joe project] due to market conditions.” Commission Oct. 2, 2023 Letter at 1 (cleaned up). We directed Nopetro to clarify its plans and to take a position on whether the case was moot. Nopetro explained that it “currently is not pursuing the Port St. Joe project and has no current plans to do so in the future.” Nopetro Oct. 4, 2023 Letter. But Nopetro 4

stated that “its plans could change” and suggested the appeal was therefore not moot. Id. The Commission’s order, Nopetro noted, could also “apply with respect to other Nopetro projects.” Id. In supplemental briefing, Public Citizen similarly argued that Nopetro’s changed plans do not moot the appeal. The Commission suggested that we “could” conclude that the case is moot, but it did not take a firm position on the issue. Commission Oct. 6, 2023 Letter. At oral argument, Nopetro confirmed that it stopped pursuing the project “due to market conditions,” including “the price of natural gas.” Oral Arg. Tr. 52:15–53:8. The company then clarified that, even if the price increased, it would still “need to find the right off-taker” to purchase the LNG before it considered resurrecting the project. Id. 53:3–54:10. Nopetro also revealed that it does not own—nor does it have “an option” in place “to lease”—the land on which the facility would be built. Id. 54:10–19. II. Derived from Article III, the mootness doctrine ensures that federal courts decide only “actual, ongoing controversies.” Honig v. Doe, 484 U.S. 305, 317 (1988). Under this doctrine, “[e]ven where litigation poses a live controversy when filed,” a federal court must “refrain from deciding [the dispute] if ‘events have so transpired that the decision will neither presently affect the parties’ rights nor have a more-than- speculative chance of affecting them in the future.’” Clarke v. United States, 915 F.2d 699, 701 (D.C. Cir. 1990) (en banc) (quoting Transwestern Pipeline Co. v. FERC, 897 F.2d 570, 575 (D.C. Cir. 1990)). This rule ensures that federal courts respect the bounds of their constitutionally assigned role. Among other salutary purposes, it protects courts from rendering impermissible advisory opinions. See Nat’l Black 5

Police Ass’n v. District of Columbia, 108 F.3d 346, 349 (D.C. Cir. 1997). Although no party has urged us to do so, we hold that we lack jurisdiction over this appeal because it is moot. See Noel Canning v. NLRB, 705 F.3d 490, 496 (D.C. Cir. 2013) (“[F]ederal courts . . . must assure themselves of jurisdiction over any controversy they hear, regardless of the parties’ failure to assert any jurisdictional question.”). A. We first address the appropriate standard for evaluating mootness in this case. The ordinary standard is the one identified above: A case is moot if a “decision will neither presently affect the parties’ rights nor have a more-than- speculative chance of affecting them in the future.” Transwestern Pipeline Co., 897 F.2d at 575. One exception to that rule exists for cases in which a party voluntarily ceases the challenged activity. When the exception applies, the case remains live unless it is “absolutely clear the allegedly wrongful behavior could not reasonably be expected to recur.” Friends of the Earth, Inc. v. Laidlaw Env’t Servs. (TOC), Inc., 528 U.S. 167, 190 (2000). Here, given Nopetro’s unilateral decision to discontinue its plans for the Port St. Joe project, Public Citizen argues that the more demanding voluntary- cessation standard governs our analysis. We disagree.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
92 F.4th 1124, Counsel Stack Legal Research, https://law.counselstack.com/opinion/public-citizen-inc-v-ferc-cadc-2024.