Pro Tech Industries v. URS Corporation

CourtCourt of Appeals for the Eighth Circuit
DecidedJuly 27, 2004
Docket03-3329
StatusPublished

This text of Pro Tech Industries v. URS Corporation (Pro Tech Industries v. URS Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pro Tech Industries v. URS Corporation, (8th Cir. 2004).

Opinion

United States Court of Appeals FOR THE EIGHTH CIRCUIT ___________

No. 03-3329 ___________

Pro Tech Industries, Inc., d/b/a Fusion * Seal Corporation, * * Appellant, * * Appeal from the United States v. * District Court for the Eastern * District of Missouri. URS Corporation, d/b/a URS Group, * Inc.; American Home Assurance * Company, * * Appellees. * ___________

Submitted: April 13, 2004 Filed: July 27, 2004 ___________

Before MORRIS SHEPPARD ARNOLD, RILEY, and COLLOTON, Circuit Judges. ___________

RILEY, Circuit Judge.

This appeal asks whether the parties should be compelled to arbitrate a dispute. The parties clearly agreed to arbitrate, and the dispute falls squarely within their broad arbitration agreement. However, Pro Tech Industries, Inc. (Pro Tech) contends the agreement to arbitrate is unenforceable because (1) URS Corporation (URS) failed to make a required demand for arbitration of Pro Tech’s claims, and URS thereby waived its right to arbitrate, and (2) Pro Tech cannot now afford to arbitrate, rendering the arbitration agreement unconscionable.1 The district court2 compelled arbitration and dismissed the lawsuit. Because the issue of waiver is for the arbitrator to decide and because the issue whether Pro Tech can afford the cost of arbitration is “speculative,” we affirm, adhering to the strong federal policy favoring arbitration, see Dean Witter Reynolds, Inc. v. Byrd, 470 U.S. 213, 217 (1985), and Federal Arbitration Act, 9 U.S.C. §§ 1-16.

I. BACKGROUND In December 2001, Pro Tech, a Missouri corporation, agreed to provide URS, a Texas corporation, with pipe, pipe fittings, pipe fusion, and leak testing for an environmental reclamation facility being built at the White Sands Test Facility operated by NASA (White Sands project). URS was the general contractor on the White Sands project, let bids for the pipe work, selected Pro Tech for the work, and negotiated with Pro Tech.

The parties memorialized the terms of this joint undertaking in a written agreement (Agreement). Under the Agreement, URS and Pro Tech agreed to arbitrate “[a]ll claims, disputes and other matters . . . arising out of, or relating to” the Agreement. A choice-of-law provision, included in twelve-point bold-face type, specified that the subcontract agreement “shall be interpreted, construed and governed under the laws of . . . Texas.” In the event of a dispute, the Agreement

1 Pro Tech’s notice of appeal suggests it is appealing the decision of the district court dismissing without prejudice Pro Tech’s claims against American Home Assurance Company. Pro Tech failed to raise this claim in their initial brief before this court. “Claims not raised in an initial brief are waived, and we generally do not consider issues raised for the first time on appeal in a reply brief.” Mahaney v. Warren County, 206 F.3d 770, 771 n.2 (8th Cir. 2000) (citation omitted). We see no reason to depart from our rules in this case. 2 The Honorable Rodney W. Sippel, United States District Judge for the Eastern District of Missouri. -2- mandates “[n]otice of demand for arbitration shall be filed in writing with the other party to [the] Agreement in accordance with the rules of the American Arbitration Association.”

In July 2002, a dispute arose, ultimately leading URS to invoke the arbitration provision. The dispute stemmed from Pro Tech removing its equipment and personnel from the White Sands project and ceasing to provide any further services, notwithstanding substantial work remaining under the Agreement. This occurred despite URS having paid Pro Tech in excess of $424,000 of the $471,071 total contract price. In November 2002, Pro Tech filed an action in Missouri state court, claiming (1) URS owed Pro Tech money under the Agreement; (2) Pro Tech was entitled to additional compensation for performing extra work not included in the Agreement; and (3) URS coerced Pro Tech into providing this extra work. Pro Tech sought compensatory damages in excess of $200,000 and punitive damages in excess of $2,000,000. URS removed the case to the federal district court on diversity grounds.

URS moved to dismiss and to compel arbitration, citing the Agreement’s arbitration provision. The district court held the arbitration provision was enforceable and Pro Tech’s claims against URS were subject to that arbitration provision. The court granted URS’s motion to compel arbitration, but refused to dismiss Pro Tech’s claims. Instead, the district court stayed the case, pending the outcome of arbitration. The district court advised the parties that, if neither party initiated arbitration within thirty days of the court’s order, the court would deem that failure to be a novation of the contract and a waiver of the right to arbitrate.

Within thirty days of the district court’s order, URS served its demand for arbitration on Pro Tech and filed the demand with the American Arbitration Association (AAA). The demand asserted a claim by URS against Pro Tech and requested that Pro Tech pursue any claims against URS in arbitration. Pro Tech

-3- subsequently moved to vacate the district court’s order asserting URS’s demand was not sufficient to initiate arbitration of Pro Tech’s claims, and URS had therefore waived its right to arbitrate those claims. Pro Tech also moved to bar arbitration of all claims, contending it did not have the financial resources to participate in arbitration. Because of this alleged poverty, Pro Tech asked the district court to declare the arbitration provision unconscionable.

The district court denied Pro Tech’s motion to vacate, concluding URS had not waived its right to arbitrate Pro Tech’s claims. The district court also denied Pro Tech’s motion to bar arbitration of all claims, concluding the costs did not render the Agreement unconscionable. The district court dismissed Pro Tech’s claims, holding the parties’ dispute must be resolved by arbitration pursuant to the Agreement’s arbitration provision. Pro Tech appeals.

Pro Tech presents three reasons why it should not be forced to arbitrate its claims against URS: (1) URS waived its right to compel arbitration; (2) URS’s demand for arbitration was insufficient; and (3) the arbitration provision is unenforceable, because Pro Tech cannot now afford arbitration. We first ask whether these contentions are “gateway matters” that courts, not arbitrators, must decide. Green Tree Fin. Corp. v. Bazzle, 539 U.S. 444, ___, 123 S. Ct. 2402, 2407 (2003) (holding courts must decide “certain gateway matters, such as whether the parties have a valid arbitration agreement at all or whether a concededly binding arbitration clause applies to a certain type of controversy”).

II. DISCUSSION We review de novo the district court’s decision to compel arbitration. See Keymer v. Mgt. Recruiters Int’l., Inc., 169 F.3d 501, 504 (8th Cir. 1999). “Factual findings are reviewed for clear error.” Faber v. Menard, Inc., 367 F.3d 1048, 1051 (8th Cir. 2004) (quoting Dobbins v. Hawk’s Enters., 198 F.3d 715, 717 (8th Cir. 1999)). We recognize an agreement to arbitrate is a matter of contract, and “is a way

-4- to resolve those disputes–but only those disputes–that the parties have agreed to submit to arbitration.” First Options of Chicago, Inc. v. Kaplan, 514 U.S. 938, 943 (1995).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dean Witter Reynolds Inc. v. Byrd
470 U.S. 213 (Supreme Court, 1985)
At&T Technologies, Inc. v. Communications Workers
475 U.S. 643 (Supreme Court, 1986)
First Options of Chicago, Inc. v. Kaplan
514 U.S. 938 (Supreme Court, 1995)
Green Tree Financial Corp.-Alabama v. Randolph
531 U.S. 79 (Supreme Court, 2000)
Howsam v. Dean Witter Reynolds, Inc.
537 U.S. 79 (Supreme Court, 2002)
Green Tree Financial Corp. v. Bazzle
539 U.S. 444 (Supreme Court, 2003)
Dominium Austin Partners v. Emerson
248 F.3d 720 (Eighth Circuit, 2001)
Steve R. Faber v. Menard, Inc.
367 F.3d 1048 (Eighth Circuit, 2004)
In Re Firstmerit Bank, N.A.
52 S.W.3d 749 (Texas Supreme Court, 2001)
In Re the Marriage of Smith
115 S.W.3d 126 (Court of Appeals of Texas, 2003)
AutoNation USA Corp. v. Leroy
105 S.W.3d 190 (Court of Appeals of Texas, 2003)
Pearce v. Pearce
824 S.W.2d 195 (Court of Appeals of Texas, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Pro Tech Industries v. URS Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pro-tech-industries-v-urs-corporation-ca8-2004.