Preston McNees Specialty Woodworking, Inc. v. The Daniel Co. (Danco), Inc.

CourtCourt of Appeals of Tennessee
DecidedFebruary 13, 2015
DocketE2014-01004-COA-R3-CV
StatusPublished

This text of Preston McNees Specialty Woodworking, Inc. v. The Daniel Co. (Danco), Inc. (Preston McNees Specialty Woodworking, Inc. v. The Daniel Co. (Danco), Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Preston McNees Specialty Woodworking, Inc. v. The Daniel Co. (Danco), Inc., (Tenn. Ct. App. 2015).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE November 24, 2014 Session

PRESTON MCNEES SPECIALTY WOODWORKING, INC. ET AL. v. THE DANIEL CO. (DANCO), INC.

Appeal from the Circuit Court for Washington County No. 30781 Thomas J. Seeley, Jr., Judge

No. E2014-01004-COA-R3-CV - Filed February 13, 2015

This case involves the proper interpretation of a contract between a general contractor and a subcontractor. The trial court determined that the subcontractor was entitled to recover additional sums above the original contract price based on the doctrine of equitable estoppel. The general contractor timely appealed. Having determined that the scope of the parties’ contract covered the work in question and that the doctrine of equitable estoppel does not apply in this matter, we vacate the trial court’s judgment.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court Vacated; Case Remanded

T HOMAS R. F RIERSON, II, J., delivered the opinion of the Court, in which D. M ICHAEL S WINEY and J OHN W. M CC LARTY, JJ., joined.

Bill W. Petty and Micha Buffington, Knoxville, Tennessee, for the appellant, The Daniel Co. (DANCO), Inc.

Thomas D. Dossett, Kingsport, Tennessee, for the appellee, Preston McNees Specialty Woodworking, Inc. d/b/a Preston Woodworking.

OPINION

I. Factual and Procedural Background

The plaintiff, Preston McNees Specialty Woodworking, Inc. d/b/a Preston Woodworking (“Preston”), filed the present action against The Daniel Co. (DANCO), Inc. (“DANCO”), seeking compensation for work that Preston performed on a construction project wherein DANCO was the general contractor and Preston was a subcontractor. In 2010, Preston submitted a bid to supply certain woodwork regarding a project for the College of Medicine Student Center at East Tennessee State University. When preparing its bid, Preston relied in part upon the project manual (“Manual”) that had been prepared by Fisher + Associates (“Fisher”), the project architect and designer.

The Manual expressly provided for “[s]hop finishing of all natural finish interior woodwork” and stated that “fabrication, including assembly, finishing, and hardware application” should be complete before shipment to the project site. In a section entitled “Shop Finishing,” the Manual provided in pertinent part:

B. General: Finish architectural woodwork at fabrication shop as specified in this Section. Defer only final touchup, cleaning, and polishing until after installation.

C. General: Shop finish transparent-finished interior architectural woodwork at fabrication shop as specified in this Section.

***

E. Transparent Finish: Comply with requirements indicated below for grade, finish system, staining, and sheen, with sheen measured on 60- degree gloss meter per ASTM D 523.

4. Staining: Match Architect’s sample.

Preston prepared and submitted its bid, which consisted of a base amount of $82,961, with an additional $12,605 to be added for three bays of study rooms. Preston’s bid stated that “All wood items are sent to field unfinished, ready to stain by others prior to installation.” DANCO selected Preston as the subcontractor for the aforementioned work.

On November 22, 2010, Preston and DANCO executed a “Standard Form of Agreement Between Contractor and Subcontractor,” otherwise identified as AIA 1 Document A401-1997 (“Subcontract”). This Subcontract provides that Preston will perform the casework and millwork for the project for a total price of $95,566. The Subcontract also provides that the work will be performed “as specified in the Project Manual dated June 18, 2010, Drawings, and addenda thereto, prepared by Fisher + Associates . . . .” The

1 American Institute of Architects.

-2- Subcontract further states:

1.1 The Subcontract Documents consist of (1) this Agreement; (2) the Prime Contract, consisting of the Agreement between the Owner and Contractor and the other Contract Documents enumerated therein; (3) Modifications issued subsequent to the execution of the Agreement between the Owner and Contractor, whether before or after the execution of this Agreement; (4) other documents listed in Article 16 of this Agreement; and (5) Modifications to this Subcontract issued after execution of this Agreement. These form the Subcontract, and are as fully a part of the Subcontract as if attached to this Agreement or repeated herein. The Subcontract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. An enumeration of the Subcontract Documents, other than Modifications issued subsequent to the execution of this Agreement, appears in Article 16.

Article 16 lists no additional documents.

Following execution of the Subcontract, Preston prepared shop drawings, which set out the details regarding the work Preston was to perform. The front page of the shop drawings contains a typed statement by Preston that “trim and plywood to be stained as per provided sample. (Stain sample to follow).” This front page additionally bears the approval stamp of DANCO as well as the approval stamp of Fisher. There also appears a handwritten note, signed by Mr. Fisher, which states: “Wood stain to match approved door sample.” DANCO returned the shop drawings to Preston on June 6, 2011, with a transmittal sheet stating, “Wood stain to match enclosed door sample.”

Sam Preston, President of Preston Woodworking, testified that when the shop drawings were returned with the notations regarding stain color, he contacted Tom Daniel at DANCO and reminded him that Preston’s bid was for unfinished wood. According to Mr. Preston, Mr. Daniel explained that the architect required the woodwork to be shop-finished; Mr. Preston claimed he was previously unaware of this fact. Mr. Preston related that he subsequently submitted a price for this finish work of $13,994, with no negative response from Mr. Daniel. Mr. Preston stated that Preston had not yet begun finishing of the woodwork, such that Mr. Daniel could have opted to accept the additional cost or allow the woodwork to be delivered unfinished for the original contract price.

Preston sent a change request to DANCO on August 21, 2011, wherein Mr. Preston detailed the additional cost of $13,994 to stain and finish the woodwork. Mr. Preston

-3- explained that he discussed this additional cost with Mr. Daniel in great detail. He admitted, however, that the change order was never signed by anyone at DANCO. Preston submitted a stain sample to the architect and received approval for same. Although Preston was instructed to begin installation on August 22, 2011, it was unable to comply due to conditions at the job site. Eventually, Preston’s on-site work began on August 29, 2011.

Preston submitted a pay application on August 25, 2011, which included the original contract price of $95,556, plus an addition of $13,994 for the submitted change order.2 As such, the pay application reflected a total revised contract price of $109,550. Through that pay application, Preston requested a partial payment for its work, which Preston indicated was thirty-eight percent complete. Preston submitted a subsequent pay application on September 23, 2011, demonstrating the original contract price plus additional costs of $21,639 and claiming a total revised contract price in the amount of $117,195. Two subsequent pay applications were sent on October 25, 2011, and November 8, 2011, also reflecting the “revised” contract sum of $117,195. Mr. Preston testified that DANCO was slow in making payments and never questioned the extra charges until approximately November 8, 2011, after Preston’s work was substantially complete. Consequently, Mr. Preston sent a memo to DANCO and Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dick Broadcasting Company, Inc. of Tennessee v. Oak Ridge FM, Inc.
395 S.W.3d 653 (Tennessee Supreme Court, 2013)
Kafozi v. Windward Cove, LLC
184 S.W.3d 693 (Court of Appeals of Tennessee, 2005)
Mike Allmand v. Jon Pavletic
292 S.W.3d 618 (Tennessee Supreme Court, 2009)
Staubach Retail Services-Southeast, LLC v. H.G. Hill Realty Co.
160 S.W.3d 521 (Tennessee Supreme Court, 2005)
Osborne v. Mountain Life Insurance Co.
130 S.W.3d 769 (Tennessee Supreme Court, 2004)
Whitehaven Community Baptist Church v. Holloway
973 S.W.2d 592 (Tennessee Supreme Court, 1998)
VanBebber v. Roach
252 S.W.3d 279 (Court of Appeals of Tennessee, 2007)
Bob Pearsall Motors, Inc. v. Regal Chrysler-Plymouth, Inc.
521 S.W.2d 578 (Tennessee Supreme Court, 1975)
Doe v. HCA Health Services of Tennessee, Inc.
46 S.W.3d 191 (Tennessee Supreme Court, 2001)
Consumer Credit Union v. Hite
801 S.W.2d 822 (Court of Appeals of Tennessee, 1990)
Union Carbide Corp. v. Huddleston
854 S.W.2d 87 (Tennessee Supreme Court, 1993)
Callahan v. Town of Middleton
292 S.W.2d 501 (Court of Appeals of Tennessee, 1954)
Planters Gin Co. v. Federal Compress & Warehouse Co.
78 S.W.3d 885 (Tennessee Supreme Court, 2002)
Farmers-Peoples Bank v. Clemmer
519 S.W.2d 801 (Tennessee Supreme Court, 1975)
GRW Enterprises, Inc. v. Davis
797 S.W.2d 606 (Court of Appeals of Tennessee, 1990)
McCarty v. McCarty
863 S.W.2d 716 (Court of Appeals of Tennessee, 1992)
Guiliano v. Cleo, Inc.
995 S.W.2d 88 (Tennessee Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Preston McNees Specialty Woodworking, Inc. v. The Daniel Co. (Danco), Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/preston-mcnees-specialty-woodworking-inc-v-the-dan-tennctapp-2015.