Powell v. TPI Petroleum, Inc.

510 F.3d 818, 2007 U.S. App. LEXIS 29792, 2007 WL 4531482
CourtCourt of Appeals for the Eighth Circuit
DecidedDecember 27, 2007
Docket07-1009
StatusPublished
Cited by10 cases

This text of 510 F.3d 818 (Powell v. TPI Petroleum, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Powell v. TPI Petroleum, Inc., 510 F.3d 818, 2007 U.S. App. LEXIS 29792, 2007 WL 4531482 (8th Cir. 2007).

Opinion

*821 WOLLMAN, Circuit Judge.

TPI Petroleum, Inc. (TPI), appeals from the judgment against it in a breach-of-contract case arising from TPI’s removal of four underground storage tanks (the tanks) from realty it leased from David Powell, Sr. TPI argues that, inter alia, the evidence presented in the case was insufficient to prove breach or damages. We affirm the judgment with respect to the breach issue and reverse and remand for a new trial on the damages issues.

I. Background

Over a twenty-year period beginning in April 1983, TPI and its predecessor leased realty from Powell and his predecessor for use as a gas station. When TPI’s predecessor took possession of the property, it remodeled the existing gas station and replaced the fuel system and tanks. In 2003, TPI elected not to exercise its final renewal option under the lease and notified Powell that it intended to remove the fuel system, including the tanks. Powell disputed TPI’s claimed ownership of the tanks and insisted that they remain with the realty. Following failed negotiations between the parties, TPI removed the tanks and had them destroyed.

Powell filed suit for breach of contract, complaining that the lease forbade TPI’s removal of the tanks. The provisions of the lease prohibited waste, incorporated the law of fixtures, and addressed what additions and removals the lessee could make with respect to the property. The tanks were explicitly listed as items that could be added, but were not listed as items that could be removed. The district court entered judgment on the jury’s general verdict for Powell and denied TPI’s combined motions for judgment as a matter of law and a new trial.

II. Analysis

A. Motion for Judgment as a Matter of Law

As a threshold issue, Powell asserts that TPI waived post-trial consideration and appellate review of the issues con-tened in its motion for judgment as a matter of law (JAML) made at the close of Powell’s evidence by failing to move for JAML again at the close of all evidence. We review for abuse of discretion the district court’s decision to consider TPI’s post-trial motion for JAML. Minn. Supply Co. v. Raymond Corp., 472 F.3d 524, 535 (8th Cir.2006).

TPI’s motion clearly falls within the BE & K exception to our requirement that a motion for JAML under Federal Rule of Civil Procedure 50(a) be made at the close of all evidence in order to be renewed post-trial under the version of Federal Rule of Civil Procedure 50(b) in effect at the time of TPI’s motion. 1 The BE & K exception rests on the district court’s indication that the motion would not be waived, the short time before the close of all evidence, the small number of new witnesses following the motion, and the lack of additional evidence offered by the non-movant. 2 BE & K Constr. Co. v. United Bhd. of Carpenters & Joiners of Am., 90 F.3d 1318, 1325 (8th Cir.1996). In Raymond, we held that the exception applied when the district court flatly denied the Rule 50(a) motion without taking it under advisement, one day and two witnesses *822 remained before the close of all evidence, and the district court considered the Rule 50(b) motion on the merits. 472 F.3d at 535-36. In this case, the district court unequivocally deferred ruling on TPI’s Rule 50(a) motion hours before the close of all evidence and explicitly permitted Powell to file a supporting brief to respond to the motion and to the single witness following it. The facts in this case therefore fall more clearly within the BE & K exception than did those in Raymond.

Powell also argues for the first time on appeal that TPI’s Rule 50(a) motion for JAML failed adequately to specify the law and facts defining the issues on which it sought judgment. Powell’s argument lacks merit, and we need not consider it further.

We agree with the district court that TPI did not waive its JAML issues, and we turn to the merits.

B. Breach of Contract

To prevail on a breach-of-contract claim, a plaintiff must prove (1) the existence of a valid agreement; (2) the defendant’s breach of that agreement; and (3) the plaintiffs damages resulting from the breach. Foreman Sch. Dist. No. 25 v. Steele, 347 Ark. 193, 61 S.W.3d 801, 807 (2001). TPI does not dispute the validity of the lease, contesting only issues relating to the elements of breach and damages.

1. Weight of the Evidence

TPI contends that Powell’s evidence was insufficient to prove that TPI’s removal of the tanks breached the lease agreement. TPI presented this argument in its initial Rule 50(a) motion for JAML. We agree with the district court’s conclusion that JAML is inappropriate here because there is sufficient evidence to support a finding of breach, and thus decision on the issue would require weighing the evidence and assessing credibility.

Alternatively, TPI argued in its motion for a new trial that because the evidence overwhelmingly supported the conclusion that the tanks were trade fixtures, the jury ignored its instruction on trade fixtures when it issued its general verdict in Powell’s favor. We review for abuse of discretion, and where, as here, “the basis of the motion for a new trial is that the jury’s verdict is against the weight of the evidence, the district court’s denial of the motion is virtually unassailable on appeal.” Wash. Solutions, Inc. v. PDQ Mfg., 395 F.3d 888, 892 (8th Cir.2005) (internal quotation omitted). Accordingly, we hold that the district court did not abuse its discretion in denying the motion for a new trial on the issue of breach.

First, we agree with the district court that the evidence did not overwhelmingly indicate that the tanks were trade fixtures. Applying Arkansas’s test for determining whether an object is a fixture, and thus part of the lessor’s realty, or a trade fixture, and thus the lessee’s chattel, we consider (1) whether the tanks were annexed to Powell’s realty, (2) whether they were appropriate for or adapted to the realty’s use, and (3) the objective intention of TPI’s predecessor at the time of annexation. Pledger v. Halvorson, 324 Ark. 302, 921 S.W.2d 576, 577-78 (1996). Intent is paramount and is inferred from the nature of the object and the mode of its annexation, the relationship between the parties, and the object’s purpose. Id. at 578.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hagen v. Siouxland Obstetrics & Gynecology, P.C.
23 F. Supp. 3d 991 (N.D. Iowa, 2014)
Tarek Al-Birekdar v. Chrysler Group, LLC
499 F. App'x 641 (Eighth Circuit, 2013)
Shaw Hofstra & Associates v. Ladco Development, Inc.
673 F.3d 819 (Eighth Circuit, 2012)
Heimlicher v. Steele
615 F. Supp. 2d 884 (N.D. Iowa, 2009)
McCabe v. Mais
580 F. Supp. 2d 815 (N.D. Iowa, 2008)
Shaw Group, Inc. v. Marcum Ex Rel. Estate of Marcum
516 F.3d 1061 (Eighth Circuit, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
510 F.3d 818, 2007 U.S. App. LEXIS 29792, 2007 WL 4531482, Counsel Stack Legal Research, https://law.counselstack.com/opinion/powell-v-tpi-petroleum-inc-ca8-2007.