Portland Utilities Construction v. Chase Creek

CourtCourt of Appeals of Tennessee
DecidedMay 14, 1997
DocketM2002-02886-COA-R3-CV
StatusPublished

This text of Portland Utilities Construction v. Chase Creek (Portland Utilities Construction v. Chase Creek) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Portland Utilities Construction v. Chase Creek, (Tenn. Ct. App. 1997).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE October 8, 2003 Session

PORTLAND UTILITIES CONSTRUCTION COMPANY, LLC v. CHASE CREEK, LLC ET AL.

Appeal from the Chancery Court for Davidson County No. 99-2471-I Irvin H. Kilcrease, Jr., Chancellor

No. M2002-02886-COA-R3-CV - Filed April 7, 2004

A utilities contractor sued a subdivision developer for payment for work it performed on the subdivision’s infrastructure. The court found that the developer was obligated to honor its contract by paying for work with a value of $313,829. The court also found that the developer was entitled to an offset of $55,955 for damages resulting from defects in the contractor’s performance. The developer argues on appeal that the trial court erroneously declined to grant it additional offsets. We affirm the trial court.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed and Remanded

PATRICIA J. COTTRELL, J., delivered the opinion of the court, in which WILLIAM C. KOCH , JR., P.J., M.S., and FRANK G. CLEMENT , JR., J., joined.

T. Turner Snodgrass, Nashville, Tennessee, for the appellants, Chase Creek, LLC and Travelers Casualty and Surety Company of America.

Joe A. Conner, Sheri A. Fox, Chattanooga, Tennessee, for the appellee, Portland Utilities Construction Company, LLC.

OPINION

I. A CONSTRUCTION CONTRACT

This case arose from a contract executed on May 14, 1997, between owner-developer Chase Creek, L.L.C., (“the developer”) and Portland Utilities Construction Company, L.L.C. (“the contractor”). The developer planned to build a residential subdivision on 43 lots that were partly within Davidson County and partly within Williamson County. The terms of the contract obligated Portland to remove two barns from the property, to remove a pond by filling it with compacted onsite materials, and to install storm drains, water lines, sewer lines, and electrical conduit. Grading of the roads was also included in the contract, but paving was to be done by another contractor. Grading and preparation of the lots themselves were also to be done by other contractors. The contract at issue did not identify a general contractor for the project, but the evidence suggests that the developer and its agent Patrick Malone performed that function.

Although the contract included a lump-sum price for “site preparation,” the parties refer to it as a unit price contract. Items such as excavation of solid rock and backfilling were to be charged on the basis of the quantities required, because there was no way to determine in advance exactly how many cubic yards of solid rock would have to be removed or how many tons of crushed stone would be needed for backfilling. Payment was to be made biweekly as work was completed. The contract did not contain a liquidated damages provision or a guaranteed completion date.

The plans for the project were approved by the State of Tennessee in July of 1997, and work began shortly thereafter. It did not take long for problems to arise. The contractor initially made Kepley & Sons its subcontractor for excavation, road grading, and pond compaction.1 After the first week, Kepley’s crew only worked on the project sporadically, and in November of 1997, Chase Creek requested that the subcontractor be removed for absenteeism and for overstating the quantity of rock it had excavated. Portland agreed, and decided to complete the work with its own employees.

Unfortunately, new problems arose. According to Chase Creek, most of those problems resulted from the contractor’s failure to do the work correctly the first time, leading to delays and to additional expenses for repairing or redoing defective work. Portland denied that it was at fault, and pointed instead to a number of other factors, including alleged errors by surveyors, engineers, and other contractors. The proof showed that construction of houses on individual lots began as early as April of 1998 and continued during the infrastructure work. Portland claimed that the combined effects of unusually wet weather and heavy construction traffic on graded but unpaved roads caused massive erosion, forcing it to regrade the same roads three or four times.

The infrastructure work took far longer than the developer thought reasonable, and far more solid rock had to be removed than was anticipated. Although the owner of Portland Utilities testified that storm sewers, water lines and storm drains were “pretty well finished” by June 1998, additional road work was still needed and electrical conduit still had to be installed. Portland continued to work on the site until May of 1999. Final approval of its work was subsequently obtained, but Chase Creek stopped making payments to Portland after August 1998.

1 Ernest W oodcock, Portland’s principal owner, testified that Kenny Kepley originally intended to bid on the Chase Creek contract, but could not procure a required bond. Kepley contacted Portland and asked that company to furnish the bond and to act as the general utilities contractor, with Kepley doing the actual work. The proof shows that the developer was fully aware of this arrangement.

-2- The contractor submitted a final bill to the developer for a remaining balance of over $300,000. Chase Creek declined to make any payment. On May 20, 1999, the contractor sent a notice of non-payment to the developer. On June 10, 1999, notices of mechanics and materialmen’s liens were filed with the Register of Deeds of both Davidson and Williamson County.

II. COURT PROCEEDINGS

On August 30, 1999, Portland Utilities filed a Complaint in the Chancery Court of Davidson County asking the court to order Chase Creek to pay it the balance which it was entitled to for materials it provided and work it completed for the developer.2 Travelers Casualty and Surety Company of America was later added as a defendant pursuant to Tenn. Code Ann. § 66-11-142.

Chase Creek filed an Answer on October 5. The developer alleged that the contractor’s claims were based upon materials which were not incorporated into the project or not documented, included work that was necessary only to correct the contractor’s own mistakes, and included work which was of no benefit to the project. Chase Creek also counter-complained for additional expenses it incurred in finishing or correcting Portland’s work, as well as for lost profits and interest expense allegedly arising from the contractor’s delays.

The hearing of the matter began on May 6, 2002, and took three days in all. Ernest Woodcock, owner of Portland Utilities, was the primary witness for the plaintiff. His testimony was consistent with that of five of his supervisors who worked on the project as to the necessity to repeat certain work because of errors in the plans and damage caused by other contractors.

The defendant’s chief witness was Patrick Malone, a homebuilder and former real estate agent who supervised the project for Chase Creek, and was one of the developer’s three owners. Mr. Malone recited a long litany of grievances against Portland and of the costs he incurred as a result of delays in the completion of those parts of the project that were Portland’s responsibility. On cross-examination, he reluctantly acknowledged that errors and delays by other contractors may have contributed to the difficulties Portland experienced.

For example, Mr. Malone admitted that the plans given to Portland showed a road width of 29 feet. As we noted above, the contractor had to grade the same roads more than once because of damage caused by a combination of heavy rains and construction traffic.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

V. L. Nicholson Co. v. Transcon Investment & Financial Ltd.
27 Cont. Cas. Fed. 80,250 (Tennessee Supreme Court, 1980)
Heyer-Jordan & Associates, Inc. v. Jordan
801 S.W.2d 814 (Court of Appeals of Tennessee, 1990)
Airline Construction, Inc. v. Barr
807 S.W.2d 247 (Court of Appeals of Tennessee, 1990)
ACG, INC. v. Southeast Elevator, Inc.
912 S.W.2d 163 (Court of Appeals of Tennessee, 1995)
Minor v. Minor
863 S.W.2d 51 (Court of Appeals of Tennessee, 1993)
Moore Construction Co. v. Clarksville Department of Electricity
707 S.W.2d 1 (Court of Appeals of Tennessee, 1986)
Nelson ex rel. Brasfield v. Richardson
626 S.W.2d 702 (Court of Appeals of Tennessee, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
Portland Utilities Construction v. Chase Creek, Counsel Stack Legal Research, https://law.counselstack.com/opinion/portland-utilities-construction-v-chase-creek-tennctapp-1997.