Portland General Electric Company v. Peter Johnson, Administrator of the Bonneville Power Administration, Intalco Aluminum Corporation, Intervenors

754 F.2d 1475, 1985 U.S. App. LEXIS 29284
CourtCourt of Appeals for the Ninth Circuit
DecidedMarch 4, 1985
Docket83-7546
StatusPublished
Cited by24 cases

This text of 754 F.2d 1475 (Portland General Electric Company v. Peter Johnson, Administrator of the Bonneville Power Administration, Intalco Aluminum Corporation, Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Portland General Electric Company v. Peter Johnson, Administrator of the Bonneville Power Administration, Intalco Aluminum Corporation, Intervenors, 754 F.2d 1475, 1985 U.S. App. LEXIS 29284 (9th Cir. 1985).

Opinions

SNEED, Circuit Judge:

Petitioner Portland General Electric Company (PGE) challenges reduced-rate sales of electric power by the Bonneville Power Administration (BPA) to BPA’s direct service industrial customers that took place in 1983.1 Petitioner alleges that BPA failed to follow ratemaking procedures mandated by the Pacific Northwest Electric Power Planning and Conservation Act, 16 U.S.C. §§ 839-839h (1982).

We find that petitioner had standing to bring this action, that the action is timely, and that the petitioner is not barred from bringing this action by failure to raise its objections before the agency. On the merits, we find that under the circumstances of this case BPA was not required to follow ratemaking procedures.

I.

STATEMENT OF THE CASE

A. Background

Respondent BPA is a federal government agency that markets power from federal [1477]*1477hydroelectric projects and other federally-owned sources of electric power in the Pacific Northwest. BPA’s operations and statutory mandate are discussed in detail in Central Lincoln Peoples’ Util. Dist. v. Johnson, 686 F.2d 708 (9th Cir.1982), rev’d sub nom. Aluminum Co. of America v. Central Lincoln Peoples’ Util. Dist., — U.S. —, 104 S.Ct. 2472, 81 L.Ed.2d 301 (1984), and Central Lincoln Peoples’ Util. Dist. v. Johnson, 735 F.2d 1101 (9th Cir.1984). We present here only the essential facts necessary to understand this case.

BPA sells power to public utilities and other public entities, to private, investor-owned utilities, and to direct service industrial customers (DSI’s). The public and private utilities purchase power for resale to consumers. The DSI’s, primarily aluminum manufacturers, purchase power directly for their own use.

Petitioner Portland General Electric Company (PGE) and intervenors Intalco Aluminum Corporation (Intalco), Martin Marietta Aluminum, Inc., (Martin Marietta) and Pennwalt Corporation (Pennwalt) are all BPA customers. PGE is an investor-owned utility. Intalco, Martin Marietta, and Pennwalt are DSPs; they have intervened on the side of respondent BPA.

The Pacific Northwest Electric Power Planning and Conservation Act, 16 U.S.C. §§ 839-839h (1982) (hereinafter referred to as the Regional Act), requires BPA to fix rates for electric power that are sufficient both to meet BPA’s costs and to recoup the federal investment in its facilities “over a reasonable number of years.” 16 U.S.C. § 839e(a). The Act prescribes procedures for establishing or revising rates. The required procedures include publication of notice of proposed rates in the Federal Register, public hearings, and decision on the record. See 16 U.S.C. § 839e(i). New rates must be approved by the Federal Energy Regulatory Commission (FERC) before they become effective. Id. § 839e(a)(2). Rate determinations and other final agency actions are subject to judicial review in this court. See id. § 839f(e).

A fundamental fact necessary to an understanding of this case is that the amount of power that BPA has to sell at any given moment depends on stream flows in the Columbia River basin. These streamflows cannot be predicted with precision. Therefore, BPA sells power under two different basic types of contracts. “Firm” power is sold under long-term contracts. The amount of firm power sold is within the amount that BPA expects to have available under even the most adverse streamflow conditions. “Nonfirm” power is sold on a short-term basis when available power exceeds BPA’s firm commitments.

BPA’s contracts with its DSI customers fall into a special third category. The DSI’s receive, their power under twenty-year contracts, and in that sense their power is “firm.” Unlike utilities that serve residential customers, however, the DSI’s can tolerate unexpected interruptions of their power. Therefore, part of the power that BPA sells to the DSPs serves as a reserve which BPA may call on in the event that an emergency threatens its ability to serve its other firm customers. See 16 U.S.C. §§ 839a(17), 839e(d)(l)(A); Aluminum Co. of America, — U.S. at—, 104 S.Ct. at 2481. The “interruptible” nature of BPA’s service to the DSPs places that service in an intermediate category between firm and nonfirm. The Regional Act requires that the rates that BPA charges the DSPs be adjusted to reflect the interruptible nature of the service that the DSPs receive. See id. § 839e(c)(3).

B. The Transactions at Issue

At the beginning of 1983, BPA found itself with a projected surplus of marketable electric power for the coming year, and with projected revenues insufficient to meet its costs. Abnormally high stream flows were filling BPA’s reservoirs to capacity, but demand was less than previously forecast, due to a general downturn in the national and regional economies.

Sales of both firm and nonfirm power were less than projected. ■ In addition to the general decrease in demand caused by [1478]*1478the economic recession, the same high stream flows that were filling BPA’s reservoirs were also filling the reservoirs of public utilities that had hydroelectric facilities of their own, thus further decreasing their need for BPA power. Further, BPA’s sales to utilities in the Southwest were only a small fraction of what BPA had projected. Finally, because of a slack demand for aluminum, most of the DSPs had cut back their operations and were purchasing only about one-half of the power available to them under their long-term contracts with BPA.

According to BPA’s forecasts, if additional sales could not be arranged, its hydroelectric facilities would be in a “spill condition” through much of 1983. That is, water would have to be spilled over dams, without generating electric power, in order to maintain reservoirs at safe levels for flood-control purposes. At the same time, projected shortfalls in revenues would require BPA to defer interest and amortization payments to the United States Treasury.

The rates in effect at the time had been established in a ratemaking proceeding during the spring and summer of 1982, and had gone into effect under temporary FERC approval on October 1, 1982. See 20 F.E.R.C. fl 61, 359 (1982). BPA’s DSI customers, under rate schedule “IP-2,” were paying approximately 2.6 cents per kilowatt-hour for power purchased under their long-term contracts. At the same time, nonfirm power was available for short-term purchase by other customers, under schedule “NF-2,” at approximately 1.1 cents per kilowatt-hour.

BPA concluded that it could increase its revenues, and stimulate the regional economy, by making power available to the DSI’s at the lower, nonfirm (NF-2) rate for purchases in excess of their current demand. If, as anticipated, the availability of reduced-rate power induced the DSI’s to restart idle production lines, then badly-needed jobs would be created and BPA would profit from the sale of energy that would otherwise be wasted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sierra Club v. Pruitt
293 F. Supp. 3d 1050 (N.D. California, 2018)
Portland General v. Bpa
Ninth Circuit, 2007
Association of Public Agency Customers, Inc. v. Bonneville Power Administration, Aluminum Company of America Elf Atochem North America Columbia Aluminum Corporation Columbia Falls Aluminum Company Kaiser Aluminum & Chemical Corporation Intalco Aluminum Corporation Northwest Aluminum Company Reynolds Metals Company Vanalco Incorporated, Respondents-Intervenors. Utility Reform Project Kevin Bell v. Bonneville Power Administration, Association of Public Agency Customers, Inc., an Unincorporated Association v. Bonneville Power Administration, Utility Reform Project Kevin Bell v. Bonneville Power Administration, Aluminum Company of America Elf Atochem North America Columbia Aluminum Corporation Columbia Falls Aluminum Company Kaiser Aluminum & Chemical Corporation Intalco Aluminum Corporation Northwest Aluminum Company Reynolds Metals Company Vanalco Incorporated, Respondents-Intervenors. Association of Public Agency Customers, Inc., an Unincorporated Association, Northwest Conservation Act Coalition, Petitioner-Intervenor v. Bonneville Power Administration, Aluminum Company of America Elf Atochem North America Columbia Aluminum Corporation Columbia Falls Aluminum Company Kaiser Aluminum & Chemical Corporation Intalco Aluminum Corporation Northwest Aluminum Company Reynolds Metals Company Vanalco Incorporated, Respondents-Intervenors. Public Power Council, Northwest Conservation Act Coalition, Petitioner-Intervenor v. Bonneville Power Administration, Aluminum Company of America Elf Atochem North America Columbia Aluminum Corporation Columbia Falls Aluminum Company Kaiser Aluminum & Chemical Corporation Intalco Aluminum Corporation Northwest Aluminum Company Reynolds Aluminum Reynolds Metals Company Vanalco Incorporated, Respondents-Intervenors
126 F.3d 1158 (Ninth Circuit, 1997)
Pacific Northwest Generating Cooperative v. Brown
822 F. Supp. 1479 (D. Oregon, 1993)
California Energy Commission, Puget Sound Power & Light Company, Washington Water Power Company ("Wwp"), Petitioner-Intervenor v. Bonneville Power Administration U.S. Department of Energy, Association of Public Agency Customers Public Power Council Public Utility District No. 1 of Chelan County, Washington Pacificorp, Dba Pacific Power & Light Company ("Pacific") Public Utility District No. 2 of Grant County, Washington Western Public Agencies Group ("Wpag") Montana Power Company City of Seattle, City Light Department ("City") Public Generating Pool ("Pgp") Eugene Water & Electric Board ("Eweb") Director Service Industrial Customers ("Dsis"), Respondent-Intervenor. Pacific Northwest Generating Company ("Pngc") v. Bonneville Power Administration U.S. Department of Energy United States of America, Vanalco Inc. Aluminum Company of America Columbia Falls Aluminum Company, Washington Water Power Company ("Wwp") Puget Sound Power and Light Company, Petitioner-Intervenor v. Bonneville Power Administration, Portland General Electric Company Association of Public Agency Customers Arco Montana Power Company Public Generating Pool ("Pgp") Eugene Water & Electric Board ("Eweb") Non-Generating Public Utilities ("Ngpu"), Respondent-Intervenor. California Public Utilities Commission, Puget Sound Power and Light Company the Department of Water & Power of the City of Los Angeles Public Service Department of the City of Burbank Public Service Department of the City of Glendale Water & Power Department of the City of Pasadena San Diego Gas & Electric Company and Southern California Edison Company Pacific Gas and Electric Company, Petitioner-Intervenor v. Bonneville Power Administration U.S. Department of Energy, Pacific Power & Light Company Eugene Water & Electric Board ("Eweb") Public Generating Pool ("Pgp") Northwest Power Planning Council Direct Service Industrial Customers ("Dsis"), Respondent-Intervenor
909 F.2d 1298 (Ninth Circuit, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
754 F.2d 1475, 1985 U.S. App. LEXIS 29284, Counsel Stack Legal Research, https://law.counselstack.com/opinion/portland-general-electric-company-v-peter-johnson-administrator-of-the-ca9-1985.