California Energy Resources Conservation and Development Commission v. Bonneville Power Administration

754 F.2d 1470, 1985 U.S. App. LEXIS 29282
CourtCourt of Appeals for the Ninth Circuit
DecidedMarch 4, 1985
Docket83-7181
StatusPublished
Cited by29 cases

This text of 754 F.2d 1470 (California Energy Resources Conservation and Development Commission v. Bonneville Power Administration) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
California Energy Resources Conservation and Development Commission v. Bonneville Power Administration, 754 F.2d 1470, 1985 U.S. App. LEXIS 29282 (9th Cir. 1985).

Opinions

Sneed, Circuit Judge:

Petitioner California Energy Resources Conservation and Development Commission (CEC) challenges transactions between the Bonneville Power Administration (BPA) and two northwest electric utilities that took place in 1983. Petitioner seeks a declaratory judgment that the transactions constituted a sale of electric power by BPA at a rate below that authorized by the established rate structure, and that BPA was therefore required to undertake statutorily-mandated ratemaking proceedings before entering into the transactions.

We find that, under the circumstances of this case, BPA was not required to follow ratemaking procedures. We therefore deny petitioner’s request for a declaratory judgment.

I.

STATEMENT OF THE CASE

A. Background

Respondent BPA is a federal government agency that markets power from hydroelectric projects and other federally-owned sources of electric power in the Pacific Northwest. BPA’s operations are governed by the Pacific Northwest Electric Power Planning and Conservation Act, 16 U.S.C. §§ 839 — 839h (1982) (the Regional Act). The Regional Act requires BPA to set rates that cover its costs and also return the federal investment in BPA’s facilities “over a reasonable period of years,” Id. § 839e(a)(l). The Act prescribes proce: dures for setting and modifying rates. The procedures include notice in the Federal Register, hearings, and decision on the record. See id. § 839e(i). Rates must be approved by the Federal Energy Regulatory Commission (FERC) before they become effective. Id. § 839e(a)(2). Rate determinations and other final agency actions are subject to judicial review in this court. See id. § 839f(e).

Petitioner CEC is an agency of the State of California responsible for formulation and implementation of energy policies. See Cal.Pub.Res.Code §§ 25200, 25216. CEC is interested in BPA rates and the availability of BPA power because California electric utilities purchase a substantial amount of power from BPA.

This case, like the accompanying case of Portland General Electric Co. v. Johnson, 754 F.2d 1475 (9th Cir.1985), arises from the BPA’s efforts to market surplus electric power during a period of unexpectedly high supply and unexpectedly low demand. Portland General Electric contains a more detailed explanation of the surrounding circumstances. Briefly, at the beginning of 1983, BPA found itself with a large surplus of marketable electric power and a severe shortfall in revenues. Abnormally high stream flows were filling BPA’s reservoirs to capacity, but sales were off due to a downturn in the national and regional economies. If BPA could not find ways of increasing its sales, it faced the prospect of spilling water over its dams without utilizing the energy that that water could produce, while having to defer interest and amortization payments to the United States Treasury.

The Trojan nuclear power plant (Trojan) is jointly owned by BPA, the Portland General Electric Company (PGE), and the Pacific Power & Light Company (PP & L). BPA owns 30 percent of the plant, PGE [1472]*1472owns 67.5 percent, and PP & L owns 2.5 percent. Trojan produces electric power at an average variable cost of approximately 0.6 cents per kilowatt-hour.

B. The Challenged Transactions

With BPA’s reservoirs projected to soon be in a “spill” condition, its marginal cost for producing hydroelectric power in 1983 was much lower than the 0.6 cents per kilowatt-hour that it cost to run Trojan. Additional hydroelectric power was virtually free; it represented the utilization of energy that would otherwise be lost. Therefore, simple economics mandated that Trojan be shut down and the power that it produced be replaced with hydroelectric power from BPA. Such a shutdown and replacement would generate savings for all of Trojan’s owners, as well as additional revenues for BPA.

Significant cost savings could only be achieved if Trojan were shut down completely. Simply reducing its output would not produce savings proportional to the reduction. Therefore, for the savings to be achieved, PGE and PP & L, as well as BPA, would have to replace their power from Trojan with hydroelectric power from BPA’s dams.

For BPA, replacing its 30 percent share of the Trojan output with hydroelectric power was a purely internal matter, but for PGE and PP & L the replacement required a purchase of power from BPA at BPA’s rates. BPA’s rate schedule then in effect, however, did not reflect its extremely low marginal cost of producing power under spill conditions. Although the schedule contained a rate that applied specifically to short-term sales under spill conditions, that rate was 0.9 cents per kilowatt-hour, greater than the cost of running Trojan. At that rate, PGE and PP & L would obviously be unwilling to replace Trojan’s output with BPA power. The shutdown could therefore be arranged only if the cost of BPA power to PGE and PP & L could be reduced.

BPA met this problem by arranging to purchase from PGE and PP & L their “scheduling rights” to Trojan for the period January 21-April 30, 1983. The purchase of the scheduling rights enabled BPA to shut down Trojan, thereby requiring PGE and PP & L to purchase power from BPA. The purchase price for the scheduling rights was set at 13.1 million dollars. The cost to PGE and PP & L of replacement power from BPA at 0.9 cents per kilowatt-hour was 15.5 million dollars. Therefore, the net cost to PGE and PP & L was only 2.4 million dollars, or approximately fifteen percent of the nominal 15.5 million-dollar cost of replacement power. Thus, the average net price for the replacement power was approximately 0.14 cents per kilowatt-hour (fifteen percent of the nominal 0.9-cent rate), compared to the 0.6-cent cost of running Trojan. At that rate, PGE and PP & L saved money from the Trojan shutdown, but BPA still profitted from the transactions because its cost of generating the replacement power was near zero.

During the shutdown, BPA initiated procedures for the formulation of new rates. See 48 Fed.Reg. 4027 (1983); 48 Fed.Reg. 12,777 (1983). The proposed new rates included a special “nuclear displacement” rate of 0.3 cents per kilowatt-hour, applicable to situations such as that that led to the challenged transactions. See Bonneville Power Administration, U.S. Dept, of Ener: gy, Administrator’s Record of Decision, 1983 Final Rate Proposal, at D-45 (Sept. 1983). The nuclear displacement rate was designed to make ad hoc arrangements such as BPA’s purchase of Trojan scheduling rights unnecessary, but, because of the lengthy ratemaking process, the new rates were not scheduled to go into effect until November 1,1983, six months after the end of the Trojan shutdown.

C. CEC’s Objections

CEC objects to the transactions relating to the Trojan shutdown on the grounds that they constituted a modification of BPA’s rate structure without adherence to ratemaking procedures mandated by the Regional Act. As already mentioned, CEC [1473]*1473seeks a declaratory judgment that the transactions are unlawful.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alcoa, Inc. v. Bonneville Power Administration
698 F.3d 774 (Ninth Circuit, 2012)
Bell v. Bonneville Power Administration
340 F.3d 945 (Ninth Circuit, 2003)
Association of Public Agency Customers, Inc. v. Bonneville Power Administration, Aluminum Company of America Elf Atochem North America Columbia Aluminum Corporation Columbia Falls Aluminum Company Kaiser Aluminum & Chemical Corporation Intalco Aluminum Corporation Northwest Aluminum Company Reynolds Metals Company Vanalco Incorporated, Respondents-Intervenors. Utility Reform Project Kevin Bell v. Bonneville Power Administration, Association of Public Agency Customers, Inc., an Unincorporated Association v. Bonneville Power Administration, Utility Reform Project Kevin Bell v. Bonneville Power Administration, Aluminum Company of America Elf Atochem North America Columbia Aluminum Corporation Columbia Falls Aluminum Company Kaiser Aluminum & Chemical Corporation Intalco Aluminum Corporation Northwest Aluminum Company Reynolds Metals Company Vanalco Incorporated, Respondents-Intervenors. Association of Public Agency Customers, Inc., an Unincorporated Association, Northwest Conservation Act Coalition, Petitioner-Intervenor v. Bonneville Power Administration, Aluminum Company of America Elf Atochem North America Columbia Aluminum Corporation Columbia Falls Aluminum Company Kaiser Aluminum & Chemical Corporation Intalco Aluminum Corporation Northwest Aluminum Company Reynolds Metals Company Vanalco Incorporated, Respondents-Intervenors. Public Power Council, Northwest Conservation Act Coalition, Petitioner-Intervenor v. Bonneville Power Administration, Aluminum Company of America Elf Atochem North America Columbia Aluminum Corporation Columbia Falls Aluminum Company Kaiser Aluminum & Chemical Corporation Intalco Aluminum Corporation Northwest Aluminum Company Reynolds Aluminum Reynolds Metals Company Vanalco Incorporated, Respondents-Intervenors
126 F.3d 1158 (Ninth Circuit, 1997)
Conservation v. Johnson
783 F.2d 858 (Ninth Circuit, 1986)
Sample v. Johnson
771 F.2d 1335 (Ninth Circuit, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
754 F.2d 1470, 1985 U.S. App. LEXIS 29282, Counsel Stack Legal Research, https://law.counselstack.com/opinion/california-energy-resources-conservation-and-development-commission-v-ca9-1985.