Pope v. United States

76 Ct. Cl. 64, 1932 U.S. Ct. Cl. LEXIS 498, 1932 WL 2110
United States Court of Claims·Decided March 7, 1932·No. No. K-336·Published·Cited by 13 cases

Opinion

Booth, Chief Justice,

delivered the opinion:

The plaintiff entered into a written contract on December 8, 1924, to construct for the defendant a subterranean tunnel. The tunnel when completed was to be about 8,600 feet in length, 6 feet in diameter inside measurement, and was located 40 feet beneath the surface of the earth. Construction work was to be completed within 24 months from December 24, 1924, and payment for performance was to be made upon a unit price basis. During the course of performance innumerable disagreements arose between the contractor and the Government officials in charge of the work, much ill feeling obtained, and the record is replete with charges and countercharges respecting the efficiency and honesty of the contractor and the Government inspectors. In fact, this unfortunate situation makes it difficult to reconcile an acutely disputatious record, and from the standpoint of fact ascertain accurately as to the right. The suspicions of the inspectors may have rendered them at times unduly prejudiced and too willing to ascribe evil motives to the contractor; in fact, this very situation brought about or occasioned discord among the inspectors themselves. On the other hand, the contractor’s entertainment of disrespect for the inspectors and their ability may have led to a course of conduct where accusations of mistakes were not justified.

We have gone carefully over the entire record and from it deduced the findings made. The first item in suit consists of a claim for dry packing and filling the dry pack with grout. Dry packing is a process resorted to in order to fill up existing space or cavities. Eocks of a prescribed size are compactly placed in the cavities in sufficient quantity to fill [79] the space, and thereafter grouted, i.e., a composition of cement, sand, and water, known as grout, is pumped into and upon the rocks so as to completely fill up the voids and open spaces appearing necessarily in the rock packing. This form of construction serves to produce a solidified mass affording substantial support from the pressure and weight of the earth material from above.

Paragraph 58 of the specifications provided in part as follows:

“ 58. Excavation in twrmel and end structures. — The excavation under this section includes all the work of this class necessary in the tunnel and for the end structures as shown on the drawings. The excavation in the tunnel shall be made within the prescribed limits as shown on the drawings and as described in these specifications. The contractor shall make all excavation in the tunnel in accordance with reference lines £A’, 1B ’, and 1 C ’ as shown on the drawing and described in paragraph number 33 but with the understanding that no excavation removed beyond the ‘ B 5 line will be paid for.”

The “A” line indicates the minimum thickness of concrete that made up the tunnel proper, and the “ B ” line, extending six inches beyond the walls of the tunnel, was the outer limit of excavation; any excavation made beyond the “ B ” line was to be at the contractor’s expense. In other words, for pay purposes, the “ B ” line limited the size of the hole ” into which the tunnel was to be constructed. In excavating this prescribed area the contractor necessarily produced excess excavation, i.e., of course it was physically impossible to excavate so as to prevent cavities beyond the “ B ” line and prevent materials from falling in from the sides of the excavation. The contractor was well aware of this fact and obligated himself to remove without pay all such excess excavation. For the purpose of reckoning pay the “ B ” line is one of primary importance. Paragraph 62 of the specifications is as follows:

“ 62. Dry packing and grouting in twrmel. — No dry packing will be allowed except where necessary over the crown of the tunnel arch, in which case clean, sound stones shall be used for packing and the spaces between such packing [80] shall be thoroughly filled with grout, pumped into place, consisting of 1 part of portland cement and 2 parts of fine building sand mixed with a suitable amount of water.
“ Dry packing will be paid for by the cubic yard at the price bid by the contractor, the actual amount being determined by measuring the spaces so filled.
“ Grouting will be paid for by the number of bags of cement used in the grout, pumped into place and at the price bid by the contractor.”

Free access — add to your briefcase to read the full text and ask questions with AI

Pope v. United States, 76 Ct. Cl. 64, 1932 U.S. Ct. Cl. LEXIS 498, 1932 WL 2110 (cc 1932).

76 Ct. Cl. 64 (Pope v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sornsin Construction Co. v. State
26 Cont. Cas. Fed. 83,215 (Montana Supreme Court, 1978)
The Len Company and Associates v. The United States
385 F.2d 438 (Court of Claims, 1967)
Alamo Construction Co. v. United States
86 F. Supp. 845 (Court of Claims, 1949)
Orino v. United States
77 F. Supp. 938 (Court of Claims, 1948)
Diamond v. United States
98 Ct. Cl. 428 (Court of Claims, 1943)
Pope v. United States
86 Ct. Cl. 18 (Court of Claims, 1937)