Pope v. United States

76 Ct. Cl. 64, 1932 U.S. Ct. Cl. LEXIS 498, 1932 WL 2110
CourtUnited States Court of Claims
DecidedMarch 7, 1932
DocketNo. K-336
StatusPublished
Cited by13 cases

This text of 76 Ct. Cl. 64 (Pope v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pope v. United States, 76 Ct. Cl. 64, 1932 U.S. Ct. Cl. LEXIS 498, 1932 WL 2110 (cc 1932).

Opinion

Booth, Chief Justice,

delivered the opinion:

The plaintiff entered into a written contract on December 8, 1924, to construct for the defendant a subterranean tunnel. The tunnel when completed was to be about 8,600 feet in length, 6 feet in diameter inside measurement, and was located 40 feet beneath the surface of the earth. Construction work was to be completed within 24 months from December 24, 1924, and payment for performance was to be made upon a unit price basis. During the course of performance innumerable disagreements arose between the contractor and the Government officials in charge of the work, much ill feeling obtained, and the record is replete with charges and countercharges respecting the efficiency and honesty of the contractor and the Government inspectors. In fact, this unfortunate situation makes it difficult to reconcile an acutely disputatious record, and from the standpoint of fact ascertain accurately as to the right. The suspicions of the inspectors may have rendered them at times unduly prejudiced and too willing to ascribe evil motives to the contractor; in fact, this very situation brought about or occasioned discord among the inspectors themselves. On the other hand, the contractor’s entertainment of disrespect for the inspectors and their ability may have led to a course of conduct where accusations of mistakes were not justified.

We have gone carefully over the entire record and from it deduced the findings made. The first item in suit consists of a claim for dry packing and filling the dry pack with grout. Dry packing is a process resorted to in order to fill up existing space or cavities. Eocks of a prescribed size are compactly placed in the cavities in sufficient quantity to fill [79]*79the space, and thereafter grouted, i.e., a composition of cement, sand, and water, known as grout, is pumped into and upon the rocks so as to completely fill up the voids and open spaces appearing necessarily in the rock packing. This form of construction serves to produce a solidified mass affording substantial support from the pressure and weight of the earth material from above.

Paragraph 58 of the specifications provided in part as follows:

“ 58. Excavation in twrmel and end structures. — The excavation under this section includes all the work of this class necessary in the tunnel and for the end structures as shown on the drawings. The excavation in the tunnel shall be made within the prescribed limits as shown on the drawings and as described in these specifications. The contractor shall make all excavation in the tunnel in accordance with reference lines £A’, 1B ’, and 1 C ’ as shown on the drawing and described in paragraph number 33 but with the understanding that no excavation removed beyond the ‘ B 5 line will be paid for.”

The “A” line indicates the minimum thickness of concrete that made up the tunnel proper, and the “ B ” line, extending six inches beyond the walls of the tunnel, was the outer limit of excavation; any excavation made beyond the “ B ” line was to be at the contractor’s expense. In other words, for pay purposes, the “ B ” line limited the size of the hole ” into which the tunnel was to be constructed. In excavating this prescribed area the contractor necessarily produced excess excavation, i.e., of course it was physically impossible to excavate so as to prevent cavities beyond the “ B ” line and prevent materials from falling in from the sides of the excavation. The contractor was well aware of this fact and obligated himself to remove without pay all such excess excavation. For the purpose of reckoning pay the “ B ” line is one of primary importance. Paragraph 62 of the specifications is as follows:

“ 62. Dry packing and grouting in twrmel. — No dry packing will be allowed except where necessary over the crown of the tunnel arch, in which case clean, sound stones shall be used for packing and the spaces between such packing [80]*80shall be thoroughly filled with grout, pumped into place, consisting of 1 part of portland cement and 2 parts of fine building sand mixed with a suitable amount of water.
“ Dry packing will be paid for by the cubic yard at the price bid by the contractor, the actual amount being determined by measuring the spaces so filled.
“ Grouting will be paid for by the number of bags of cement used in the grout, pumped into place and at the price bid by the contractor.”

In constructing the side walls, as well as the arch of the tunnel, cavities were left beyond the “ B ” line, and these voids or vacant spaces give rise to the controversy over this item in suit. Preliminary borings made by the Government officials indicated the character of materials to be excavated and it was known by the parties to the contract that a portion of the tunnel would pass through rock and another portion through soft earth. In. what was known as the “ rock section ” no timbers were to be used to support the excavated portion, the solidity of the rock being relied upon for this purpose. In the soft earth section timbers of prescribed dimensions were to be employed to support the excavation, and this portion of the work was known as the “timbered section.” The contractor, with respect to the “ timbered section ”, was ordered to dry pack and grout over the crown of the arch of the tunnel. He did dry pack the cavities over the crown of the arch, and into this dry packing as placed, pumped grout which consumed 13,891 bags of cement. He was not paid for anywhere near this amount of cement, and claims pay for the difference between the payments made to him and what he alleges he should have received under the contract at the rate of $3.00 per bag. The issue narrows under the contract and record in the case to the accuracy and correctness of measurements made to ascertain the amount of grout which should be paid for under the contract. Specification 62, quoted above, clearly contemplated the use of dry packing and grout if, in the opinion of the Government officials, it became necessary. There was no obligatory provision with respect to its use; if it was used the specification provided a basis of payment therefor. The question of the quantity of dry pack and [81]*81grout and the method of ascertaining the same are fixed in specification 62. Where it was to be used was also fixed, but discretion as to its user was reposed by the contract in the supervising officials of the Government. Paragraph 21 of the contract exacted the approval of the contracting officer of the order of work adopted by the contractor. As previously observed, line “ B ” was by the drawings and plans extended around the concrete walls of the tunnel 6 inches from the same. When it came to dry packing and grouting the cavities over the crown of the tunnel arch the contractor inserted pipes in the center of the arch and along the side walls of the tunnel which extended some 4y2 or 5 feet above the arch through which he intended to pump grout therein. The contracting officer declined to approve this method and ordered the pipes to extend no farther than 6 inches above the crown of the arch, evidently believing that no contract authority appeared to do otherwise.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sornsin Construction Co. v. State
26 Cont. Cas. Fed. 83,215 (Montana Supreme Court, 1978)
The Len Company and Associates v. The United States
385 F.2d 438 (Court of Claims, 1967)
Alamo Construction Co. v. United States
86 F. Supp. 845 (Court of Claims, 1949)
Orino v. United States
77 F. Supp. 938 (Court of Claims, 1948)
Diamond v. United States
98 Ct. Cl. 428 (Court of Claims, 1943)
Pope v. United States
86 Ct. Cl. 18 (Court of Claims, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
76 Ct. Cl. 64, 1932 U.S. Ct. Cl. LEXIS 498, 1932 WL 2110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pope-v-united-states-cc-1932.