Point East Condominium Owners' Ass'n v. Cedar House Associates Co.

663 N.E.2d 343, 104 Ohio App. 3d 704
CourtOhio Court of Appeals
DecidedJune 19, 1995
DocketNo. 67408.
StatusPublished
Cited by22 cases

This text of 663 N.E.2d 343 (Point East Condominium Owners' Ass'n v. Cedar House Associates Co.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Point East Condominium Owners' Ass'n v. Cedar House Associates Co., 663 N.E.2d 343, 104 Ohio App. 3d 704 (Ohio Ct. App. 1995).

Opinion

James M. Porter, Judge.

Plaintiff-appellant, Point East Condominium Owners’ Association, Inc. (“Point East”), appeals from the trial court’s granting of summary judgment in favor of defendants-appellees Cedar House Associates Company (“Cedar House”), Davis Development Group (a.k.a. “Davis Construction”), and E.B. Katz Plumbing Company (“Katz”). Plaintiffs claims arose out of the 1986-1987 damage resulting from leaking sprinkler systems in the common ceiling areas of the Point East Condominium. For the reasons hereinafter stated, we find merit to the appeal, reverse and remand for further proceedings.

Cedar House was an Ohio corporation formed by Larry Davis, Norman Adler and Arnold King, who acted as partners in 1977 to develop the Point East Condominium project at 27500 Cedar Road in Beachwood, Ohio. The three partners transferred the underlying real estate to Cedar House to develop the project. Davis was the chief executive officer of Davis Construction, which became the general contractor on the project. Construction began in 1977 and ultimately resulted in the erection of a ten-story building consisting of a two-floor penthouse containing eight individual penthouse condominium units, and eight floors containing eighty-six individual condominium units with various common areas. Katz was the subcontractor to Davis Construction that installed the fire suppression sprinkler system at issue in the case.

Cedar House contracted with Davis Construction to construct the condominium buildings. Because of the partner relationship among the principals (“it was a mom and pop kind of thing”), no formal written contract was ever signed. However, a Project Manual was issued by Cedar House to the general contractor, Davis Construction, and the subcontractors, which set forth the relationships between the parties and the specifications and requirements for construction. The Project Manual also contains standard AIA Document A201, General Condi *709 tions of the Contract for Construction, typically used in construction projects. The parties treated the Project Manual as though it were the general contract specifying the obligations between and among the respective parties, including the subcontractors, which performed under Davis Construction’s full-time project manager. Project Manual provisions relevant to the issues in this case will be discussed more fully where appropriate throughout this opinion.

Davis Construction entered into a formal purchase order subcontract for $300,000 with Katz, dated November 21, 1978, to install the fire suppression sprinkler system. The purchase order contained the following provision:

“You [Katz] are to assume as to your work, the same responsibility toward the owner as our general contract imposes upon us. This relationship and similarity of obligation shall also include terms of payment, cleaning up and disposal of waste material.”

Although the purchase orders to subcontractors and suppliers were issued in the name of Davis Construction, all primary decisions as to the wording of the subcontracts and as to issues arising on the job site were made jointly by “all three partners,” Davis, Adler and King. Among the decisions made by the partners was the decision to change the original specifications for the fire suppression sprinkler system from black steel piping to copper piping.

The first phase of construction involving the construction of the shell of the building was completed in 1978. In December 1979, Cedar House filed its Declaration of Condominium Ownership, pursuant to R.C. 5311.08, thereby creating the Point East Condominium Owners’ Association. However, from 1979 through September 30, 1985, defendants Cedar House and Davis Construction maintained control of the board of managers of the association by appointing four of the six members of that board pursuant to Ohio’s condominium laws. During that six-year period, the board consisted of Davis, Adler, King and their family members. During this period, Cedar House engaged DAK Management Company to manage the property until the association came into existence. DAK stood for Davis, Adler and King, who were the partners.

Once construction of the shell was completed in 1978, Cedar House began selling individual condominium suites (“units”) to private owners under written contracts entitled “Point East Condominium Sales — Purchase Agreement.” Each such purchase agreement provided that Cedar House would undertake to construct and finish the individual owner’s suites according to designs and layouts provided by the purchaser. A portion of the “finishing” construction included the extension of the sprinkler system lines from the main system to the ceiling areas above the individual suites. Consequently, as new suites were sold and custom finished, Katz would extend the sprinkler system piping to the new units. Katz’s installation work began in October 1978 and the entire system to all suites was *710 not completed until January 13, 1988. Each purchase agreement in Section 26 also contained a limited warranty covering defects in material and workmanship for two years in the common areas and for twelve months in the units. These warranties were required by R.C. 5311.25(E).

In October 1980, leaks developed in several sprinkler heads in portions of the common area sprinkler system. Grunau, the sprinkler head manufacturer, retained a metallurgist, Marvin Evans, to investigate the cause of the leaks. By a letter report dated December 1, 1980, Evans found that the valve seats on the sprinkler heads leaked because of corrosion and that “the most probable source of this corrosion is the residual soldering flux used to join the copper piping of the system.” There is no evidence that the board of managers, then controlled by Cedar House and Davis Construction, ever received a copy of this letter in 1980 or 1981. After this investigation, defendants concurred that the 1980 leaks were caused by corrosion in the sprinkler heads. The sprinkler heads in the affected areas were replaced. It was thought at the time that any leaking problems with the sprinkler system had been corrected.

Subsequently, in 1987, “a systemic pattern of leaks” developed in the horizontal piping that had been installed subsequent to 1980 in common area ceilings above the individual units. Plaintiff was notified of these leaks by Cedar House on October 15, 1987, when Norman Adler delivered a letter to plaintiffs board of managers advising the board of the conditions. In that letter, Adler informed plaintiff that engineering reports received by defendants had “indicated corrosion in the pipe due to foreign particles resting on the inside of the surface of the pipe,” and that defendants “cannot discount the possibility that there may be continuing corrosion in the pipe which may cause some additional leakages.”

Plaintiff commenced this action on September 30, 1988 1 against defendants Cedar House, Davis Construction and Katz for breach of contract, breach of express and implied warranty and negligence. It was claimed that the defective sprinkler system caused damage to plaintiffs property, diminished the value of the condominium and required expenses to repair or avoid the losses resulting from further leaking. Plaintiff, Point East Condominium Owners’ Association, claims standing to bring the action pursuant to R.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Poppe Law Office v. Orick
2013 Ohio 5662 (Ohio Court of Appeals, 2013)
Wallace v. Golden Comb, Inc.
2013 Ohio 5320 (Ohio Court of Appeals, 2013)
Sivit v. Village Green of Beachwood, L.P.
2013 Ohio 103 (Ohio Court of Appeals, 2013)
Gruger v. Diversified Air Sys., 07-Ma-52 (6-30-2008)
2008 Ohio 3403 (Ohio Court of Appeals, 2008)
Dunn v. Bruzzese
874 N.E.2d 1221 (Ohio Court of Appeals, 2007)
Cline v. Writsel, 06ca25 (5-30-2007)
2007 Ohio 2720 (Ohio Court of Appeals, 2007)
Ramirez v. Shagawat, Unpublished Decision (3-4-2004)
2004 Ohio 1001 (Ohio Court of Appeals, 2004)
Barlay v. Yoga's Drive-Thru, Unpublished Decision (12-30-2003)
2003 Ohio 7164 (Ohio Court of Appeals, 2003)
AgGrow Oils, L.L.C. v. National Union Fire Insurance
276 F. Supp. 2d 999 (D. North Dakota, 2003)
Seifer v. PHE, Inc.
196 F. Supp. 2d 622 (S.D. Ohio, 2002)
Bowshier v. Chrysler Financial Corp.
144 F. Supp. 2d 919 (S.D. Ohio, 2001)
Statler Arms, Inc. v. APCOA, Inc.
700 N.E.2d 415 (Cuyahoga County Common Pleas Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
663 N.E.2d 343, 104 Ohio App. 3d 704, Counsel Stack Legal Research, https://law.counselstack.com/opinion/point-east-condominium-owners-assn-v-cedar-house-associates-co-ohioctapp-1995.