Elliott v. Fosdick & Hilmer, Inc.

460 N.E.2d 257, 9 Ohio App. 3d 309, 9 Ohio B. 575, 1983 Ohio App. LEXIS 11075
CourtOhio Court of Appeals
DecidedFebruary 9, 1983
Docket82-03-0034
StatusPublished
Cited by16 cases

This text of 460 N.E.2d 257 (Elliott v. Fosdick & Hilmer, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elliott v. Fosdick & Hilmer, Inc., 460 N.E.2d 257, 9 Ohio App. 3d 309, 9 Ohio B. 575, 1983 Ohio App. LEXIS 11075 (Ohio Ct. App. 1983).

Opinion

Ziegel, J.

On July 3,1980, plaintiffs-appellants, Philip W. and Donna L. Elliott, filed their complaint for damages and loss of consortium arising out of an injury which Philip W. Elliott (hereinafter “plaintiff”) received on September 21, 1978, while working as a plumber for Miami University as a result of the alleged negligence of the appellees, Fosdick & Hilmer, Inc., Wente Construction Company, and General Telephone Company. That complaint was amended on July 11, 1980. Thereafter, each of these appellees moved for summary judgment. After a proper hearing, the trial court sustained each of these motions and rendered final judgment for these appellees, from which judgment this appeal is taken.

Appellants assert that in sustaining the motions for summary judgment, the trial court committed error as follows:

“1. The Court erred in holding that Revised Code of Ohio Section 2305.131 was applicable to the facts in this case.
“2. The Court erred in rejecting ‘The Delayed Damage Theory.’
“3. The Judgment, below, is contrary to Section 2305.09(D) of the Revised Code of Ohio.
“4. The Judgment, below, is contrary to Section 2305.09(C) of the Revised Code of Ohio.
“5. The Court, below, erred as to the Defendant, General Telephone Company, in holding that it did not have a duty to *310 the Plaintiff and that the elements of foreseeability are lacking.”

The first three of these assignments of error apply equally to the appellees, Fosdick & Hilmer, Inc. (“Fosdick & Hilmer”) and Wente Construction Company (“Wente”). Each of them involves the question of which statute of limitations is applicable to the facts of this case, and they will accordingly be considered together. The trial court held that R.C. 2305.131 applied. That section provides:

“No action to recover damages for any injury to property, real or personal, or for bodily injury or wrongful death, arising out of the defective and unsafe condition of an improvement to real property, nor any action for contribution or indemnity for damages sustained as a result of said injury, shall be brought against any person performing services for or furnishing the design, planning, supervision of construction, or construction of such improvement to real property, more than ten years after the performance or furnishing of such services and construction. This limitation does not apply to actions against any person in actual possession and control as owner, tenant, or otherwise of the improvement at the time the defective and unsafe condition of such improvement constitutes the proximate cause of the injury or damage for which the action is brought.”

As between appellants and the ap-pellees, Fosdick & Hilmer and Wente, there is no material dispute as to the facts. In about 1940, certain underground ducts connecting certain buildings on the Miami University campus were constructed. By 1978, the use of these ducts had been abandoned. At that time, the university determined to use one of these ducts to extend a gas line from one building to another. The work was being done by the university itself, using its own hired help, of which plaintiff was one. In 1967 and 1968, an underground high voltage electric line was installed connecting certain buildings on the campus. Fosdick & Hilmer, a consulting engineering firm, prepared the drawings for and supervised the construction of this project. Wente did the construction work on the project.

During the construction, it was noted that the route for the underground work specified in the Fosdick & Hilmer drawings was quite close to a large walnut tree, so that if the project proceeded as planned, the tree would have been destroyed. It being university policy to preserve these large trees, the route was varied so that there was a twenty-foot variance between the route as it appeared on the drawings and its location in the ground. After the project was completed sometime in 1968, as required, on July 24, 1969, Fosdick & Hilmer filed its “as built” drawings with the State Architect’s office. These filed drawings, however, did not show the variance caused by the dogleg made necessary in order to avoid the walnut tree.

When the 1978 project was being planned, plaintiff and his co-workers obtained these 1969 drawings and studied them. Plaintiff alleges that acting in reliance upon these drawings, while using a jackhammer to open another duct, he struck the high voltage electrical line, causing him severe bodily injuries.

Appellants contend that the applicable statute of limitations is R.C. 2305.10 which provides that the action shall be brought within two years after the cause accrued. They point out that the cause of action accrued on the date of injury, to wit: September 21,1978, and that the action was brought on July 11, 1980, well within the two-year limit. Reliance is placed on Velotta v. Les Petronzio Landscaping, Inc. (1982), 69 Ohio St. 2d 376 [23 O.O.3d 346], paragraph two of the syllabus:

“When negligence does not immediately result in damages, a cause of action for damages does not accrue until actual injury or damage ensues.”

In the case before us, Wente did not *311 do any work on any Miami University duct project after 1968. Fosdick & Hilmer’s connection with that project ceased at least when it filed its “as built” drawings with the State Architect on July 24, 1969. The trial judge based his decision on the finding that time started to run for statute of limitations purposes when these appellees performed the act which might be construed as negligent, a date no later than July 24,1969, obviously more than ten years before July 3, 1980. In their second assignment of error, appellants, per Velotta, urge September 21, 1978, as the date on which time started to run.

Ordinarily, the statute of limitations as to torts does not begin to run until the tort is complete, and the tort is not complete until there has been an invasion of a legally protected interest. Kunz v. Buckeye Union Ins. Co. (1982), 1 Ohio St. 3d 79, 81. Statutes of limitations, however, are creatures of the legislature, and it is within the province of the General Assembly to specify whatever time it wishes for the statutes to begin running. Vance v. St. Vincent Hospital (1980), 64 Ohio St. 2d 36 [18 O.O.3d 216]. R.C. 2305.131 provides that “[n]o action * * * shall be brought against any person performing services for or furnishing the design, planning, supervision of construction, or construction of such improvement to real property, more than ten years after the performance or furnishing of such services and construction.” Thus, where a tort is committed in the process of improving real estate, for statute of limitations purposes time begins to run when the activity in connection with that improvement took place.

The applicability of R.C. 2305.131 was not discussed in Velotta. There, plaintiffs bought a new residence from the defendant, the vendor-builder, in 1970. There were no warranties in connection with this purchase.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schmitz v. Natl. Collegiate Athletic Assn.
2016 Ohio 8041 (Ohio Court of Appeals, 2016)
Barker v. Strunk, Unpublished Decision (3-5-2007)
2007 Ohio 884 (Ohio Court of Appeals, 2007)
Stenglein v. Nelson, Unpublished Decision (10-24-2003)
2003 Ohio 5709 (Ohio Court of Appeals, 2003)
Fritz v. Bruner Cox, L.L.P.
756 N.E.2d 740 (Ohio Court of Appeals, 2001)
Johnson v. BP Exploration & Oil, Inc.
685 N.E.2d 275 (Ohio Court of Appeals, 1996)
Point East Condominium Owners' Ass'n v. Cedar House Associates Co.
663 N.E.2d 343 (Ohio Court of Appeals, 1995)
Holmes v. Community College of Cuyahoga County
647 N.E.2d 498 (Ohio Court of Appeals, 1994)
Cincinnati Insurance v. Alcorn
631 N.E.2d 1125 (Ohio Court of Appeals, 1993)
Best v. Energized Substation Service, Inc.
623 N.E.2d 158 (Ohio Court of Appeals, 1993)
Cincinnati Ins. Co. v. Wylie
549 N.E.2d 1198 (Ohio Court of Appeals, 1988)
Deeds v. American Security
528 N.E.2d 1308 (Ohio Court of Appeals, 1987)
Richards v. Gold Circle Stores
501 N.E.2d 670 (Ohio Court of Appeals, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
460 N.E.2d 257, 9 Ohio App. 3d 309, 9 Ohio B. 575, 1983 Ohio App. LEXIS 11075, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elliott-v-fosdick-hilmer-inc-ohioctapp-1983.