Gardens of Bay Landing Condominiums v. Flair Builders, Inc.

645 N.E.2d 82, 96 Ohio App. 3d 353, 1994 Ohio App. LEXIS 3351
CourtOhio Court of Appeals
DecidedAugust 8, 1994
DocketNo. 65875.
StatusPublished
Cited by13 cases

This text of 645 N.E.2d 82 (Gardens of Bay Landing Condominiums v. Flair Builders, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gardens of Bay Landing Condominiums v. Flair Builders, Inc., 645 N.E.2d 82, 96 Ohio App. 3d 353, 1994 Ohio App. LEXIS 3351 (Ohio Ct. App. 1994).

Opinion

*356 Spellacy, Judge.

Plaintiff-appellant Gardens of Bay Landing Condominiums appeals the grant of summary judgment in favor of defendants-appellees Flair Builders, Inc., William Dorsky & Associates, and Andreano & Associates in a negligent construction action. Default judgment was entered against two other defendants.

Appellant assigns the following errors for review:

“I. The Trial lower [sic] court’s grant of summary judgment in favor of the appellees was improper because genuine issues of material fact exist, warranting reversal.

“II. There is/are genuine issue(s) of material fact as to when appellant’s causes of action in tort against all appellees arose under Sec. 2305.09(D) R.C.

“HI. There is a genuine issue of material fact as to when appellant’s cause of action for fraud against Flair Builders, Inc. arose under Sec. 2305.09(C) R.C.

“IV. There is a genuine issue of material fact as to when appellant’s causes of action against appellees, for damage to property, arose under Sec. 2305.131 R.C.

“V. There are genuine issues of material fact as to what damages appellants are entitled to recover from appellees, based on their conduct.

“VI. The condominium association is the proper party to bring an action for damages to the common areas on behalf of the unit owners.”

The judgment of the trial court is affirmed in part and reversed in part.

I

Appellant is an eighty-unit condominium complex composed of five buildings located in Westlake, Ohio. Flair Builders was the builder, developer, and vendor of the development. Dorsky was the architectural firm and Andreano performed engineering services.

Construction of the buildings known as H, I, L, M, and N, began in 1980. The Declaration of Condominium Ownership, Bylaws of the Association and maps for buildings H and I were filed on December 31,1980. The filings for the remaining buildings took place on June 3, 1981. The city of Westlake issued certificates of occupancy for all the buildings on August 22, 1982.

On October 22, 1985, the unit owners gained control of the Association’s Board of Managers. A few days before, on October 16, damaged concrete caused by a cracked cementitious floor underlayment was discovered in one unit and replaced. On August 20 and October 15, 1986, identical damage to concrete floors required repair in two other units. All of this underlayment failure occurred on the second floor of three of the buildings. More damage was discovered in 1989 and 1990. *357 In August 1990, appellant hired an engineering firm to inspect the buildings and was informed that most, if not all, of the floors would need to be replaced. A second engineer found structural deficiencies in the framing, flooring, and foundation.

On May 9, 1991, appellant filed suit against Flair Builders alleging negligent construction and breach of fiduciary duty. It later added the other defendants. Appellant amended its second complaint to allege that defendant Andreano had negligently prepared plans, specifications, and negligently designed a lake improvement project.

After entering default judgment against two of the defendants who failed to answer, the trial court granted the summary judgment motions of the remaining defendants. Appellant appeals from those rulings.

II

In its first assignment of error, appellant contends the trial court erred by granting summary judgment as questions of material fact exist regarding when the causes of action arose, whether those causes of action are barred by the statute of limitations, and what damages may be recovered. Appellant presents no further discussion on this issue. This argument is so general it defies any resolution upon appeal. Appellant has not pointed to any specific error or supported its argument with any authority or citations to the record. See App.R. 12(A)(2) and 16(A)(7).

Appellant’s first assignment of error is overruled.

III

In its second assignment of error, appellant contends that there are genuine issues of material fact which exist such that it was error for the trial court to resolve the case by summary judgment. Appellant argues the issue of when its causes of action in tort arose under R.C. 2305.09(D) is disputed, requiring a determination by the factfinder at trial. Appellant maintains its cause of action could have accrued in 1985 when the first cracked cement floor was exposed and replaced or when it hired engineers in 1990 and was told the construction was defective. Appellant argues this is a material fact which is not yet determined, requiring reversal.

Civ.R. 56(C) provides that summary judgment is proper if the trial court determines that:

“(1) No genuine issue as to any material fact remains to be litigated; (2) the moving party is entitled to judgment as a matter of law; and (3) it appears from the evidence that reasonable minds can come to but one conclusion, and viewing *358 such evidence most strongly in favor of the party against whom the motion for summary judgment is made, that conclusion is adverse to that party.” Temple v. Wean United, Inc. (1977), 50 Ohio St.2d 317, 327, 4 O.O.3d 466, 472, 364 N.E.2d 267, 274.

Summary judgment is a procedural device designed to terminate litigation and to avoid a formal trial where there is nothing to try. Norris v. Ohio Std. Oil Co. (1982), 70 Ohio St.2d 1, 24 O.O.3d 1, 433 N.E.2d 615. Summary judgment is not appropriate where the facts are subject to reasonable dispute when viewed in a light favorable to the nonmoving party. Mers v. Dispatch Printing Co. (1985), 19 Ohio St.3d 100, 104, 19 OBR 261, 264, 483 N.E.2d 150, 154.

An action for the failure of a builder to perform in a workmanlike manner is a tort sounding in negligence and is governed by the four-year statute of limitations found in R.C. 2305.09. Benson v. Dorger (1972), 33 Ohio App.2d 110, 115, 62 O.O.2d 176, 179, 292 N.E.2d 919, 922. Unless damage is immediate, the cause of action does not accrue until actual injury occurs or damage ensues. Velotta v. Leo Petronzio Landscaping, Inc. (1982), 69 Ohio St.2d 376, 23 O.O.3d 346, 433 N.E.2d 147, paragraph two of the syllabus. The judiciary will determine when a cause of action arose for purposes of statutes of limitations unless the triggering event is defined by the legislature. O’Stricker v. Jim Walter Corp. (1983), 4 Ohio St.3d 84, 4 OBR 335, 447 N.E.2d 727, paragraph one of the syllabus.

In Cincinnati Ins. Co. v. Alcorn

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
645 N.E.2d 82, 96 Ohio App. 3d 353, 1994 Ohio App. LEXIS 3351, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gardens-of-bay-landing-condominiums-v-flair-builders-inc-ohioctapp-1994.