Simms v. Heskett, Unpublished Decision (9-18-2000)

CourtOhio Court of Appeals
DecidedSeptember 18, 2000
DocketCase No. 00 CA 20.
StatusUnpublished

This text of Simms v. Heskett, Unpublished Decision (9-18-2000) (Simms v. Heskett, Unpublished Decision (9-18-2000)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Simms v. Heskett, Unpublished Decision (9-18-2000), (Ohio Ct. App. 2000).

Opinion

This is an appeal from an Athens County Common Pleas Court judgment, upon a bench trial, in favor of Danny Simms, plaintiff below and appellee herein, on his claim against Steve Heskett, defendant below and appellant herein. The following errors are assigned for our review:

FIRST ASSIGNMENT OF ERROR:

"THE TRIAL COURT ERRED IN OVERRULING DEFENDANT'S MOTION FOR A DIRECTED VERDICT AT THE CLOSE OF PLAINTIFF'S CASE IN CHIEF."

SECOND ASSIGNMENT OF ERROR:

"THE TRIAL COURT'S JUDGMENT IN FAVOR OF PLAINTIFF ON THE COMPLAINT AS NOT SUPPORTED BY SUFFICIENT EVIDENCE AND WAS AGAINST THE MANIFEST WEIGHT OF THE EVIDENCE."

THIRD ASSIGNMENT OF ERROR:

"THE TRIAL COURT'S JUDGMENT IN FAVOR OF PLAINTIFF ON THE COUNTERCLAIM WAS NOT SUPPORTED BY SUFFICIENT EVIDENCE AND WAS AGAINST THE MANIFEST WEIGHT OF THE EVIDENCE."

A brief summary of the facts pertinent to this appeal is as follows. Appellee owns real estate near Nelsonville in Athens County, Ohio. He decided several years ago to build a structure on the property that would be both a "home as well as a garage." Appellee contacted a retired builder, Bennie Glenn, to see if he would take on the project. Mr. Glenn came up with a proposed building plan, but he and appellee were unable to come to terms on a price. Appellee was then approached by appellant who was one of the workers that Mr. Glenn would have hired for the project had his proposal been accepted. Appellant offered, on his own, to build appellee a "pole barn" for the sum of $51,900. The offer was accepted by appellee and the two of them entered into a contract on December 4, 1997 for construction of the proposed building.

It appears that the working relationship between these two men was contentious from the outset. Appellee admitted that there were a number of altercations between them and explained that this was because the building was erected in a "hap-hazard" manner with "slip shot work." Appellant claimed, on the other hand, that appellee insisted on controlling everything that was done to the building and supervised him and his workers "[d]ay by day, minute by minute." In any event, after appellant completed work on the project, there were considerable problems with the structure which other workers had to be brought in to correct.

Appellee filed suit on July 31, 1998, claiming that he had a contract with both appellant and Mr. Glenn and that they had breached that contract by "stopp[ing] construction of the building prior to [its] completion." He further alleged that the part of the pole barn which had been finished was "negligently constructed." Appellee demanded compensatory damages in the amount of $51,900.

Mr. Glenn filed an answer denying that he was ever a party to the construction contract.1 Appellant then filed his own answer denying liability and raising numerous affirmative defenses. He also filed a counterclaim alleging that appellee still owed him $4,500 for "services and material provided" in construction of the building and that appellee had also retained and converted his tools and other personal property valued at $1,000. Appellant asked for compensatory damages on these claims in the amount of $5,500. A reply was filed by appellee denying those allegations.

The matter proceeded to a bench trial on January 28, 1999, at which time appellee testified that he believed his contract had been with Mr. Glenn and that appellant was merely serving as Mr. Glenn's agent. In support of that claim, he proffered copies of checks that had been issued in both of their names for draws during construction.

Appellee also adduced considerable evidence regarding the structural problems with the pole barn. First, he testified that the building was not completed according to specification and that certain "interior walls" were never installed. Second, with respect to the completed portion of the pole barn, appellee asserted that it was so riddled with structural deficiencies as to render it virtually "[u]nusable." He described a number of defects, including the roof, soffits, drywall, etc., but the most severe problem appears to have been with the poles that were used to support the barn. Appellee related that the structure was intended to be built using "twelve [12] foot poles" sunk three (3) feet into the ground. Instead, appellant substituted ten (10) foot poles which he allegedly only sunk six (6) to twelve (12) inches. This resulted in insufficient support for the building, and the building began to sink into the ground thereby putting stress on the remaining structure and causing damage thereto.

Appellee's testimony concerning the alleged defects in the building was corroborated by several other witnesses. Charles Wachenschwanz, a roofer with twenty-one (21) years experience in the construction trade, testified that he was asked to examine the building and he found "the posts sinking, " the "soffit[s] falling down" and the plywood coming loose. In particular, he noted that the roof sheeting was not nailed down correctly and that the shingles did not properly overlap. Mr. Wachenschwanz described the potential damage that this could cause and opined that the building was not constructed in a workmanlike manner.

Similarly, Lou Dunnels (a laborer and carpenter in the construction trade with seven (7) years experience) noted that he had examined the building and found that the sheet metal had not been properly attached to the walls, that the "soffits were in bad shape" and that the building appeared to be "settling." He also explained that posts for a pole barn must "typically" be sunk four (4) feet into the ground and that poles anchored only six (6) inches deep would be subject to moving. Mr. Dunnels concluded that in his opinion, the structure was not built in a workmanlike manner.

Appellee related that in addition to the $51,900 contract price, he expended some $20,000 for materials to shore up the pole barn once construction was finished.2 He also hired several workers to make repairs to the structure. Peter Tomlin testified that he helped put up a wall and braced some posts to stabilize the building and was paid roughly $640 for his work.3 Danny Roland testified that he worked approximately 100 hours, and his girlfriend approximately 24 hours, for appellee at $10 per hour to repair drywall and patch the roof.

At the conclusion of appellee's case in chief, appellant moved for a directed verdict arguing that there was no evidence of a contract between the two of them. He cited to the emphatic testimony given by appellee that his contract had been with Mr. Glenn rather than with him. The trial court denied the motion ruling that there was "enough evidence to get beyond [it]."

Mr. Glenn testified on his own behalf and was insistent that there had been no contract between him and appellee. Glenn stated that his rejected proposal ended his direct involvement with the project. Appellant acted on his own behalf when he approached appellee with his building proposal. Mr. Glenn admitted that the checks for construction draws were made payable to both he and appellant and that he had given appellant permission to endorse his signature to those checks. He explained, however, that this was simply to facilitate payment to appellant and that he never made any claim to that money. There was also no evidence introduced below to show that Mr. Glenn ever received any sort of remuneration for the construction project.4

Appellant testified on his own behalf and asserted that he had, in fact, satisfied his obligations under the contract despite what was said by his former client.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jaworowski v. Medical Radiation Consultants
594 N.E.2d 9 (Ohio Court of Appeals, 1991)
Benson v. Dorger
292 N.E.2d 919 (Ohio Court of Appeals, 1972)
Barkley v. Barkley
694 N.E.2d 989 (Ohio Court of Appeals, 1997)
Ohio Valley Bank v. Copley
699 N.E.2d 540 (Ohio Court of Appeals, 1997)
Floyd v. United Home Improvement Center, Inc.
696 N.E.2d 254 (Ohio Court of Appeals, 1997)
Kouns v. Pemberton
617 N.E.2d 701 (Ohio Court of Appeals, 1992)
State v. Caldwell
607 N.E.2d 1096 (Ohio Court of Appeals, 1992)
Cole v. Complete Auto Transit, Inc.
696 N.E.2d 289 (Ohio Court of Appeals, 1997)
Keeton v. Telemedia Co. of Southern Ohio
648 N.E.2d 856 (Ohio Court of Appeals, 1994)
Fitzgerald v. Mayfield
584 N.E.2d 13 (Ohio Court of Appeals, 1990)
Barton v. Ellis
518 N.E.2d 18 (Ohio Court of Appeals, 1986)
Stewart v. B.F. Goodrich Co.
623 N.E.2d 591 (Ohio Court of Appeals, 1993)
Bentley v. Stewart
594 N.E.2d 1061 (Ohio Court of Appeals, 1992)
Gte North, Inc. v. Carr
618 N.E.2d 249 (Ohio Court of Appeals, 1993)
Lin v. Gatehouse Construction Co.
616 N.E.2d 519 (Ohio Court of Appeals, 1992)
Kobza v. General Motors Corp.
580 N.E.2d 47 (Ohio Court of Appeals, 1989)
Production Credit Association v. Hedges
621 N.E.2d 1360 (Ohio Court of Appeals, 1993)
Thornton v. Parker
654 N.E.2d 1282 (Ohio Court of Appeals, 1995)
Gardens of Bay Landing Condominiums v. Flair Builders, Inc.
645 N.E.2d 82 (Ohio Court of Appeals, 1994)
Rogers v. Hill
706 N.E.2d 438 (Ohio Court of Appeals, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Simms v. Heskett, Unpublished Decision (9-18-2000), Counsel Stack Legal Research, https://law.counselstack.com/opinion/simms-v-heskett-unpublished-decision-9-18-2000-ohioctapp-2000.