Pittsburgh, Cincinnati, Chicago & St. Louis Railway Co. v. Hoffman

107 N.E. 315, 57 Ind. App. 431, 1914 Ind. App. LEXIS 142
CourtIndiana Court of Appeals
DecidedDecember 23, 1914
DocketNo. 8,322
StatusPublished
Cited by37 cases

This text of 107 N.E. 315 (Pittsburgh, Cincinnati, Chicago & St. Louis Railway Co. v. Hoffman) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pittsburgh, Cincinnati, Chicago & St. Louis Railway Co. v. Hoffman, 107 N.E. 315, 57 Ind. App. 431, 1914 Ind. App. LEXIS 142 (Ind. Ct. App. 1914).

Opinion

Caldwell, P. J.

Trial by jury, verdict for appellee for $5,000 from which $1,500 was remitted, and judgment rendered for the residue. The complaint is in two paragraphs. Error is assigned on the overruling of the demurrer to each.

The averments of the first paragraph necessary to determine its sufficiency against objections urged, are substantially as follows: January 25, 19.11, appellant, in the process of double tracking its railroad, was constructing over Simmons Creek west of Dublin a concrete double arch bridge. The work consisted of such double arches and a cinder fill thereon, and was being performed by an independent contractor. The bridge on its completion was designed to support the existing track on the north and an additional track to be laid on the south. In order that traffic might not be interrupted, the south half of the bridge was built first. On said day the south half of the double arches had been completed, the fill made thereon, and a temporary track about 1,000 feet in length extending across [435]*435the south half of the work and joining the existing track at each end, was being used for the passage of trains while the old bridge supporting the existing line of road on the north was being removed, and the north half of the work constructed. In making the fill over the south half of the arches, a crib was constructed by the use of railroad ties to support the north wall of such fill while the north half of the work was being done. On said day the concrete work of the north half was nearing completion. Appellee was employed as a watchman by the independent contractor. His duties as such watchman were that he should remain on and about the bridge during the nighttime, and care for the same, and also that he should look after and keep fire in certain stationary engines, which were being used in constructing the work. It is alleged that said temporary track was crooked, uneven and not well ballasted. About 5:30 o’clock on the morning of said day, and before the arrival of the force of men engaged in said work, appellant ran a west bound passenger train over the temporary track at the rate of forty miles per hour. By reason of the condition of the track, the train did not run smoothly, but swayed and rocked. Appellant at the time was in the line and performance of his duty at a point on the north half of said arches, five to seven feet north of the temporary track, which, by reason of the fill, was seven or eight feet above him, and thereupon, while the train was being carelessly and negligently operated over the uneven track, a large lump of coal fell from the tender of the engine drawing the train, and struck appellee on the head and seriously injured him. It is alleged that appellant was guilty of negligence in loading the coal in the tender, and in operating the train at a high rate of speed over the defective track, and that as a result the lump of coal was thrown from the tender against appellee injuring him, as aforesaid. It is alleged also that appellant knew and that appellee did not know of the negligence as pleaded.

[436]*436The second paragraph of complaint does not differ materially from the first. It contains additional matter that there was in force a general rule and order made by appellant that trains should not be operated over the temporary track at a speed exceeding fifteen miles per hour.

Against the sufficiency of the first paragraph of complaint it is argued that the paragraph does not disclose that appellee’s duties required him to be on the incompleted bridge; that it does disclose that he was there for purposes of his own; that as a consequence, it does not appear that appellant owed appellee any duty to exercise care respecting him. It is argued also that the accident and injury resulted from-dangers and risks incident to appellee’s employment and known to him, which dangers and risks were therefore assumed by him.

1. 2. 3. As indicated, it is alleged in the paragraph that appellee was employed as a watchman, and that it was a part of his duty under such employment to be on and about the bridge, and to care for same during the nighttime. It is specifically alleged that appellee received his injuries while discharging such duties, and it therefore sufficiently appears that appellee’s duty rather than some purpose of his own accounted for his presence. He was, therefore, rightfully on the bridge. Being rightfully on the bridge, appellant was chargeable with notice of his whereabouts. Jackson v. Galveston, etc., R. Co. (1897), 90 Tex. 372, 38 S. W. 745. Appellee being rightfully near the track, and appellant being chargeable with notice of his presence, because it was chargeable with notice of the presence of all persons who might be rightfully near the track, it follows that appellant owed appellee the duty to use ordinary care to avoid injuring him, and that if it failed to do so, it was thereby guilty of negligence. Such being the case, the averments contained in the paragraph— that appellant, with knowledge of the facts, negligently loaded the. coal by piling it up above the top [437]*437of the tender, in the absence of safeguards to prevent it from falling, and so that it would fall and be thrown from the tender by the motion of the engine, and that, as aforesaid, appellant negligently ran said loaded engine over said defective track at said high rate of speed — are sufficient as a charge of negligence. Fletcher v. Baltimore, etc., R. Co. (1897), 168 U. S. 135, 18 Sup. Ct. 35, 42 L. Ed. 411; Gulf, etc., R. Co. v. Wood (1901), 63 S. W. (Tex. Civ. App.) 164; Cleveland, etc., R. Co. v. Berry (1899), 152 Ind. 607, 616, 53 N. E. 415, 46 L. R. A. 33; 33 Cyc. 779.

4. 5. In a case where the principle of assumption of risk applies, the person subjected to such principle is held to assume the risk incident to the enterprise, when properly equipped and conducted, and in addition, he assumes all risks growing out of defects or dangers of which he had either actual or constructive knowledge, and which he understands and appreciates although such additional risks have their origin in the negligence of the one who in the particular matter sustains to him the relation of master or other contractual relation. As matter of pleading in negligence cases, a general allegation of plaintiffs want of knowledge respecting the defect and consequent danger complained of is sufficient, unless specific facts disclosed by the complaint overcome such general averment. Such general allegation negatives not only actual but also constructive knowledge. Terre Haute, etc., Traction Co. v. Young (1914), 56 Ind. App. 25, 104 N. E. 780; Diamond Block Coal Co. v. Cuthbertson (1906), 166 Ind. 290, 76 N. E. 1060.

6. [438]*4387. 8. [439]*4399. [437]*437The negligence charged here in the first paragraph of complaint is respecting the loading of the coal on the tender, and the manner of operating the engine over the defective track. It is averred that appellee had no knowledge of appellant’s alleged negligent acts as averred in the paragraph, and there being no specific facts pleaded which nullify the general allegation, the paragraph [438]*438is sufficient as against the criticism now under consideration, even if the element of “assumption of risk” were involved in this action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bituminous Fire & Marine Insurance Co. v. Culligan Fyrprotexion, Inc.
437 N.E.2d 1360 (Indiana Court of Appeals, 1982)
Kroger Co. v. Haun
379 N.E.2d 1004 (Indiana Court of Appeals, 1978)
Meadowlark Farms, Inc. v. Warken
376 N.E.2d 122 (Indiana Court of Appeals, 1978)
Old Town Development Company v. Langford
349 N.E.2d 744 (Indiana Court of Appeals, 1976)
Gregory v. White Truck & Equipment Co., Inc.
323 N.E.2d 280 (Indiana Court of Appeals, 1975)
Farmer v. Werner Transportation Company
284 N.E.2d 861 (Indiana Court of Appeals, 1972)
Anderson v. J. C. Penney Co.
272 N.E.2d 621 (Indiana Court of Appeals, 1971)
Collins v. Grabler
263 N.E.2d 201 (Indiana Court of Appeals, 1970)
Yingst, Spec. Admin. v. Pratt
220 N.E.2d 276 (Indiana Court of Appeals, 1966)
STALLINGS v. Dick
210 N.E.2d 82 (Indiana Court of Appeals, 1965)
Pfisterer v. Grisham
210 N.E.2d 75 (Indiana Court of Appeals, 1965)
Michel v. Forde
191 N.E.2d 507 (Indiana Court of Appeals, 1963)
Thompson v. Pickle
191 N.E.2d 53 (Indiana Court of Appeals, 1963)
Baker v. Coca Cola Bottling Works
177 N.E.2d 759 (Indiana Court of Appeals, 1961)
New York, Chicago & St. Louis Railroad v. Henderson
146 N.E.2d 531 (Indiana Supreme Court, 1957)
Kempf v. Himsel
98 N.E.2d 200 (Indiana Court of Appeals, 1951)
McCague v. New York, Chicago & St. Louis Railroad
71 N.E.2d 569 (Indiana Supreme Court, 1947)
Pierce v. Clemens
46 N.E.2d 836 (Indiana Court of Appeals, 1943)
Emhardt v. Perry Stadium, Inc.
46 N.E.2d 704 (Indiana Court of Appeals, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
107 N.E. 315, 57 Ind. App. 431, 1914 Ind. App. LEXIS 142, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pittsburgh-cincinnati-chicago-st-louis-railway-co-v-hoffman-indctapp-1914.