Pioneer Civil Construction, LLC v. Ingevity Arkansas, LLC

District Court, W.D. Arkansas·Decided November 9, 2023·No. 1:22-cv-01034·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT WESTERN DISTRICT OF ARKANSAS EL DORADO DIVISION

PIONEER CIVIL CONSTRUCTION, LLC PLAINTIFF

v. Case No. 1:22-cv-1034

INGEVITY ARKANSAS, LLC; and INGEVITY CORPORATION DEFENDANTS

ORDER

Before the Court is Plaintiff-Counter Defendant Pioneer Civil Construction’s (“Pioneer”) Motion for Sanctions. ECF No. 87. Defendants-Counter Plaintiffs Ingevity Arkansas, LLC and Ingevity Corporation (collectively “Ingevity”) responded. ECF No. 102. Pioneer replied. ECF No. 110. The Court finds the matter ripe for consideration. I. BACKGROUND In fall 2021, Ingevity sought bids for a construction project (the “Project”) within its facility in Crossett, Arkansas (the “Plant”). The Project sought to build an asphalt road for 18-wheelers to use before loading or unloading material within the Ingevity Plant. In October 2021, Ingevity selected Pioneer’s bid for the Project and entered into a contract for its construction. Pioneer finished its construction work on the Project on November 1, 2021. Ingevity employee Amy Bantly inspected and approved the final construction. Shortly after Pioneer completed its work on the Project, concerns and disagreement arose regarding the build quality of the road and Pioneer’s adherence to the Project specifications. In early December 2021, Pioneer president Lance Griffin (“Griffin”) offered to drill core samples of the asphalt road for Ingevity to confirm Pioneer’s adherence to the Project specifications. ECF No. 102-5, p. 2-3. Griffin states that no Ingevity personnel arrived at the scheduled time for the samples to be taken and that he left the Plant after waiting for an hour. Id. at p. 3-4. Griffin states that Ingevity personnel contacted him shortly afterward seeking to conduct the test but that he told them he would only return to do so at a charge of $2,000 per core sample. Id. at p. 4. Griffin did not take any core samples that day. Ingevity subsequently hired Terracon Consultants, Inc. (“Terracon”) to take core samples

of the asphalt road. Terracon took four samples on December 16, 2021. Griffin was present for this testing. Terracon issued a report (ECF No. 102-3) on December 27, 2021 stating that two of the core samples did not meet Project specifications for asphalt thickness. Terracon did not preserve the core samples and did not attach any photographs or field logs to the report. Ingevity hired Diversified Construction & Design, L.L.C. (“Diversified”) to take additional core samples of the asphalt road. Diversified took four samples on January 6, 2022. Ingevity personnel present1 when Diversified took those samples allege that three of the samples indicated 0F that the road did not meet Project specifications. Diversified did not preserve the samples and did not create a written report or opinion on the samples. The only documentation of Diversified’s testing is photographs of the holes in the road from which the core samples were taken. On January 4, 2022, Ingevity ordered Pioneer to suspend its work and barred Pioneer and its employees from accessing the Plant, citing Pioneer’s noncompliance with safety standards. On January 10, 2022, Ingevity terminated Pioneer from the Project, citing Pioneer’s allegedly noncompliant safety ratings and procedures as well as various safety violations. On January 12, 2022, counsel for Pioneer sent an email (ECF No. 87-11) to Ingevity stating Pioneer’s position that it is entitled to the remaining unpaid portions of the Project contract. Pioneer and Ingevity

1 Ingevity asserts that Griffin was present when Diversified took its samples of the asphalt road. However, the evidence Ingevity cites for support, the deposition testimony of Ike Kotey, in no way indicates that Griffin was present for that testing. ECF No. 102-4. continued to communicate in the following months regarding their positions as to the Project contract and what payments were owed to whom. ECF Nos. 41-1, 41-2, 41-3, & 41-4. Ingevity personnel state that they began noticing visually apparent defects in the Project road as early as February 2022. Ingevity eventually hired Terracon to do an analysis of the road

to determine whether it was constructed in compliance with the Project specifications. Terracon initiated this analysis on April 4, 2022, which included pulling four more core samples from the asphalt road. Ingevity asserts that all four core samples indicated that the road did not meet Project specifications for asphalt or aggregate base thickness. Terracon later issued a report of its findings (ECF No. 87-12) but did not preserve the core samples or any field logs or photographs of its testing. In late April 2022, four Ingevity employees collectively determined that the asphalt road constructed by Pioneer needed to be replaced. On May 5, 2022, counsel for Pioneer informed an Ingevity representative that they did not accept a previous proposal to resolve the dispute and requested information regarding whether the Ingevity representative was authorized to accept

service on behalf of Ingevity. ECF No. 87-17. On May 6, 2022, LA Construction submitted a bid to demolish and rebuild the Project asphalt road, which Ingevity accepted. LA Construction began its work to demolish the asphalt road early on May 9, 2022, and substantially completed the work by the end of that day. That same day, Pioneer filed its initial complaint against Ingevity in the Ashley County, Arkansas Circuit Court. ECF No. 3. Pioneer alleged alternate claims of breach of contract, promissory estoppel, unjust enrichment, and interference with business expectancy. Id. Pioneer issued a Cease-and-Desist letter to Ingevity on May 10, 2022, demanding that it halt all demolition of the asphalt road. Ingevity complied and LA Construction stopped its work. A small section of the asphalt road remained and the material from the demolished portions were placed into piles. Pioneer filed a Motion for Preliminary Injunction in the Ashley County Circuit Court on May 13, 2022, seeking that Ingevity be ordered to preserve all evidence of the Project road built

by Pioneer and to provide Pioneer with reasonable access to the Plant. ECF No. 21-1. The Circuit Court granted Pioneer’s motion for the injunction, ordering Ingevity to preserve all evidence of the Project road and to permit Pioneer access to that evidence. ECF No. 4; ECF No. 21-4, p. 42- 50. On June 13, 2022, Ingevity removed the action to this Court pursuant to 28 U.S.C. § 1441(b), alleging diversity jurisdiction pursuant to 28 U.S.C. § 1332. ECF No. 2, p. 1-3. Pioneer subsequently filed a motion for this Court to enforce the injunction issued by the state court, arguing that Ingevity was not abiding by the injunction. ECF No. 16. The Court held that the state court injunction was still in force upon removal pursuant to 28 U.S.C. § 1450, but also found that Ingevity’s conditions for accessing the Plant were not unreasonable and that Pioneer had not demonstrated why it could not comply with those conditions. ECF No. 37.

Ingevity then filed a motion to modify or reverse the state court injunction, arguing that the injunction was deficient under the Federal Rules of Civil Procedure. ECF No. 34. On October 11, 2022, the Court granted Ingevity’s request to modify the injunction, ordering that the injunction’s requirement that the asphalt road evidence be preserved would elapse forty-five (45) days from the date of that order. ECF Nos. 53 & 54.

Free access — add to your briefcase to read the full text and ask questions with AI

Pioneer Civil Construction, LLC v. Ingevity Arkansas, LLC, (W.D. Ark. 2023).

Pioneer Civil Construction, LLC v. Ingevity Arkansas, LLC (Pioneer Civil Construction, LLC v. Ingevity Arkansas, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related