Pioneer Civil Construction, LLC v. Ingevity Arkansas, LLC

CourtDistrict Court, W.D. Arkansas
DecidedMarch 3, 2023
Docket1:22-cv-01034
StatusUnknown

This text of Pioneer Civil Construction, LLC v. Ingevity Arkansas, LLC (Pioneer Civil Construction, LLC v. Ingevity Arkansas, LLC) is published on Counsel Stack Legal Research, covering District Court, W.D. Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pioneer Civil Construction, LLC v. Ingevity Arkansas, LLC, (W.D. Ark. 2023).

Opinion

IN THE UNITED STATES DISTRICT COURT WESTERN DISTRICT OF ARKANSAS EL DORADO DIVISION

PIONEER CIVIL CONSTRUCTION, LLC PLAINTIFF

v. Case No. 1:22-cv-1034

INGEVITY ARKANSAS, LLC; and INGEVITY CORPORATION DEFENDANTS

ORDER

Before the Court is Plaintiff’s Motion to Dismiss Amended Counterclaim.1 ECF No. 47. 0F Defendants have responded. ECF No. 51. The Court finds the matter ripe for consideration. I. BACKGROUND Plaintiff Pioneer Civil Construction, LLC (“Pioneer”) is an Arkansas limited liability company. Defendant Ingevity Arkansas, LLC (“Ingevity AR”) is a Delaware limited liability company registered to do business in Arkansas, and Defendant Ingevity Corporation (“Ingevity Corp.”) is a Delaware corporation with its principal place of business in South Carolina. In the fall of 2021, Pioneer placed a bid to Ingevity AR to perform certain work for construction of an asphalt road within Ingevity AR’s facility in Crossett, Arkansas. Pioneer was later selected to build the road. The agreement for the work Pioneer was to perform for Ingevity AR is documented in a Revised Purchase Order #4502392369 (“Purchase Order”) dated October 4, 2021. ECF No. 14-1. The Purchase Order references “Ingevity Terms and Conditions” (“Terms and Conditions”), a separate document that puts forth additional requirements of the contract. The parties now dispute whether those Terms and Conditions are included in the contract for Pioneer’s construction work at Ingevity AR’s facility in Crossett.

1 Plaintiff previously filed a Motion to Dismiss (ECF No. 31) Defendants’ initial Counterclaim (ECF No. 19). Defendants filed a subsequent Amended Counterclaim. ECF No. 43. Therefore, Plaintiff’s prior Motion to Dismiss Defendants’ Counterclaim (ECF No. 31) is hereby MOOT. Pioneer alleges that Ingevity Corp. ceased to pay invoiced charges for the construction project in November 2021. Pioneer further alleges that it would have completed the project by the end of 2021 absent the delays caused by Ingevity AR. Defendants allege that Pioneer had submitted invoices for work it had not completed. In early January 2022, Ingevity AR terminated

its contract with Pioneer for the construction of the asphalt road and barred Pioneer from accessing the Crossett facility. Defendants allege that the termination resulted from Pioneer’s failure to adhere to workplace safety requirements and that Pioneer’s work on the asphalt road was defective and did not adhere to the construction standards set forth in the contract. Pioneer alleges that these safety standards were not part of the overall contract and were applied retroactively to Pioneer’s construction work. On May 9, 2022, Pioneer filed its first complaint against Defendants in the Circuit Court of Ashley County, Arkansas. ECF No. 3. Pioneer alleged alternative claims of breach of contract, promissory estoppel, unjust enrichment, and interference with business expectancy. Pioneer’s original complaint attached the now disputed “Terms and Conditions” document. Id. at p. 18-26.

On May 10, 2022, Pioneer sent a cease-and-desist letter to Ingevity AR to prevent it from further deconstruction of the asphalt road Pioneer had built in the Crossett facility. On May 13, 2022, Pioneer filed a Motion for Preliminary Injunction or Temporary Restraining Order (ECF No. 22- 1), seeking to prevent Defendants from any further demolition of the asphalt road, to allow Pioneer to access the remaining road and road materials to gather evidence for its claims, and to require Defendants to preserve any remaining material from the asphalt road. A hearing was held on that motion on May 19, 2022, at which Defendants chose not to participate. At the hearing, the president of Pioneer, Lance Griffin, testified to his understanding that the Terms and Conditions were a part of the contract for constructing the asphalt road.2 ECF No. 21-4, p. 33-35. At the 1F conclusion of the hearing, the State court indicated it would grant Pioneer’s request for an injunction so that it could gather evidence necessary for its claims. Id. at p. 43-50. Pioneer later provided that court with an order simply stating that the requested injunction was granted without detailing the specifics of the injunction. ECF No. 2-1, p. 74-75. On June 13, 2022, Defendants removed the matter to this Court pursuant to 28 U.S.C. § 1332 diversity jurisdiction.3 ECF No. 2. Defendants later moved to have the preliminary 2F injunction imposed by the State court reversed or modified. ECF No. 31. The Court granted Defendants’ request to modify the injunction after finding that the state court injunction did not meet federal standards. ECF No. 53. The modified injunction entered by the Court placed a time limit on which Pioneer had to access the Crossett facility to obtain whatever evidence it needed for its claims. ECF No. 54. On July 12, 2022, Pioneer filed its Amended Complaint. ECF No. 14. In its amended complaint, Pioneer alleges that the Terms and Conditions were not properly incorporated into the Purchase Order and overall contract. Id. at p. 2-3. Pioneer brings five claims in the alternate: a claim for breach of contract in which the Purchase Order is the full extent of the contract, a claim for breach of contract in which the Terms and Conditions are determined to be properly incorporated into the contract, a claim for promissory estoppel, a claim for unjust enrichment, and a claim for tortious interference with contract. Id. at p. 10-16. Defendants filed a motion to dismiss Plaintiff’s claims (ECF No. 18), which the Court later denied (ECF No. 56).

2 The Terms and Conditions were also introduced as Exhibit 7 at the hearing. ECF No. 21-4, p. 97-105. 3 No party disputes that there is complete diversity between the parties or that the amount in controversy exceeds $75,000. Accordingly, the Court is satisfied that it has subject matter jurisdiction pursuant to 28 U.S.C. § 1332. On July 26, 2022, Defendants filed their first Answer and Counterclaim to Pioneer’s Amended Complaint. ECF No. 19. Pioneer filed a motion to dismiss Defendants’ initial counterclaim in its entirety. ECF No. 31. Defendants subsequently filed an Amended Answer and Counterclaim. ECF No. 43. Defendants’ amended answer alleges that Pioneer should never have

been awarded the contract to construct the asphalt road because its accumulated safety violations from prior projects made it ineligible to work at Defendants’ facility. Id. at p. 29-30. Defendants also allege that Pioneer was awarded the contract despite its safety record and despite not being the lowest bidder because of kickbacks that Lance Griffin offered to one of Defendants’ prior employees who was a project manager. Id. Defendants further allege that Pioneer’s construction of the asphalt road was beset by multiple failures prior to the contract’s termination and that an evaluation of the road afterward indicated that all of Pioneer’s work needed to be demolished and replaced. Id. at pg. 31-41. Defendants assert eight claims against Pioneer related to the formation and performance of the contract to construct the asphalt road: breach of contract, negligence, breach of warranty, civil conspiracy, fraudulent inducement, negligent misrepresentation, tortious

interference with contract, and unjust enrichment. Id. at p. 41-51. Defendants seek restitution, compensatory damages, punitive damages, attorney’s costs and fees, and pre- and post-judgment interest. Id. at p. 52. On September 13, 2022, Pioneer filed the instant motion to dismiss Defendants’ counterclaim in its entirety. ECF No. 47.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Carton v. General Motors Acceptance Corp.
611 F.3d 451 (Eighth Circuit, 2010)
Ajm Express v. H & S Transportation
53 F.3d 1282 (Fifth Circuit, 1995)
Hutson v. Cummins Carolinas, Inc.
314 S.E.2d 19 (Court of Appeals of South Carolina, 1984)
Hinds v. Elms
595 S.E.2d 855 (Court of Appeals of South Carolina, 2004)
Troutman v. Facetglas, Inc.
316 S.E.2d 424 (Court of Appeals of South Carolina, 1984)
Cartee v. Lesley
350 S.E.2d 388 (Supreme Court of South Carolina, 1986)
Brown Ex Rel. Estate of Brown v. Stewart
557 S.E.2d 676 (Court of Appeals of South Carolina, 2001)
Quail Hill, LLC v. County of Richland
692 S.E.2d 499 (Supreme Court of South Carolina, 2010)
Eldeco, Inc. v. Charleston County School District
642 S.E.2d 726 (Supreme Court of South Carolina, 2007)
Arkansas Appliance Distributing Co. v. Tandy Electronics, Inc.
730 S.W.2d 899 (Supreme Court of Arkansas, 1987)
Ingersoll-Rand Co. v. El Dorado Chemical Co.
283 S.W.3d 191 (Supreme Court of Arkansas, 2008)
Pridgen v. Ward
705 S.E.2d 58 (Court of Appeals of South Carolina, 2010)
Cricket Cove Ventures, LLC v. Gilland
701 S.E.2d 39 (Court of Appeals of South Carolina, 2010)
Earthscapes Unlimited, Inc. v. Ulbrich
703 S.E.2d 221 (Supreme Court of South Carolina, 2010)
JASDIP Properties SC, LLC v. Estate of Richardson
720 S.E.2d 485 (Court of Appeals of South Carolina, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Pioneer Civil Construction, LLC v. Ingevity Arkansas, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pioneer-civil-construction-llc-v-ingevity-arkansas-llc-arwd-2023.