Eldeco, Inc. v. Charleston County School District

642 S.E.2d 726, 372 S.C. 470, 2007 S.C. LEXIS 77
CourtSupreme Court of South Carolina
DecidedMarch 5, 2007
Docket26280
StatusPublished
Cited by43 cases

This text of 642 S.E.2d 726 (Eldeco, Inc. v. Charleston County School District) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eldeco, Inc. v. Charleston County School District, 642 S.E.2d 726, 372 S.C. 470, 2007 S.C. LEXIS 77 (S.C. 2007).

Opinion

Chief Justice TOAL.

This appeal arises out of a contract dispute between Appellant Eldeco, Inc. (“Eldeco”) and Respondents Charleston County School District (“CCSD”) and Skanska USA Building, Inc. (“Skanska”) 1 . Eldeco alleged that Skanska breached the parties’ contract by failing to award certain electrical work in a new school building to Eldeco. Eldeco also alleged that CCSD intentionally interfered in the contractual relationship between Eldeco and Skanska. The trial court found in favor of Skanska and CCSD. Eldeco appeals and we affirm.

Factual/Procedural Background

CCSD began construction of a new high school building (“the Project”) in Mt. Pleasant, South Carolina in 2002. Skanska was the general contractor for the Project and hired Eldeco as an electrical subcontractor. At the time the parties entered into their respective contracts, the Project called for the construction of the school building as specified in the contract documents, which included an unfinished area for vocational training.

After construction of the Project began, CCSD decided to complete the vocational training area (“Culinary Arts Upfit”) and add additional classroom space on either side of the school building (“Classroom Additions”). CCSD asked Skanska to provide a pricing estimate for the Culinary Arts Upfit and the Classroom Additions. As part of the pricing estimate, Skanska asked Eldeco to provide an estimate for the electrical work required for the Culinary Arts Upfit and the Classroom Additions. Eldeco submitted an estimate of $442,000.00.

Following the school board’s approval for the additional work, CCSD formally requested pricing from Skanska. Skanska submitted its formal pricing quote which included Eldeco’s official price for the Classroom Additions electrical work in the amount of $881,855.94. CCSD objected to the *475 adjusted price, and Eldeco eventually lowered the price to $720,000.00. Eldeco also submitted a pricing quote for the Culinary Arts Upfit electrical work of $248,311.76. At the request of CCSD, Skanska obtained pricing from another electrical contractor. Mt. Pleasant Mechanical submitted a price for the Classroom Additions in the amount of $348,812.00 and for the Culinary Arts Upfit in the amount of $229,340.00. Upon instructions from CCSD, Skanska subcontracted with Mt. Pleasant Mechanical to perform the additional electrical work.

Eldeco filed suit against Mt. Pleasant Mechanical, 2 Skanska, and CCSD. Eldeco sought recovery against Skanska for breach of contract on the basis of Skanska’s failure to award Eldeco the electrical work in the Classroom Additions and the Culinary Arts Upfit. 3 Eldeco sought recovery against CCSD for tortious interference with contractual relations and intentional interference with prospective contractual relations. As grounds for these claims, Eldeco alleged that CCSD interfered with Eldeco’s contract with Skanska by instructing Skanska to hire Mt. Pleasant Mechanical, Inc. for the additional electrical work.

A jury trial began in April 2005. At the conclusion of Eldeco’s case, the trial judge directed a verdict in favor of CCSD. At the conclusion of all evidence, the trial judge denied Skanska’s motion for directed verdict. At that point, the parties agreed to dismiss the jury and allow the trial court to determine whether the term “Work” as defined in the contract documents included the Classroom Additions and Culinary Arts Upfit. According to their agreement, if the trial judge determined that the Classroom Additions and Culinary Arts Upfit were within the definition of “Work,” the trial court would award damages to Eldeco in the amount of $120,270.00. However, if the additional work fell outside of the definition, no damages would be awarded.

*476 The trial court ultimately concluded that the definition of “Work” did not include the Classroom Additions and Culinary Arts Upfit. Accordingly, no damages were awarded. Eldeco appealed, and this Court certified the case from the court of appeals pursuant to Rule 204(b), SCACR. Eldeco raises the following issues for review:

I. Did the trial court err in finding the Classroom Additions and Culinary Arts Upfit were not included in the definition of “Work” as provided in the contract documents?

II. Did the trial court err in directing a verdict in favor of CCSD as to Eldeco’s tort causes of action?

Law/Analysis

I. Eldeco’s Claim Against Skanska

Eldeco argues the trial court erred in finding the Classroom Additions and Culinary Arts Upfit were not included in the definition of “Work” as provided in the contract documents. We disagree.

A cause of action for breach of contract seeking money damages is an action at law. South Carolina Fed. Sav. Bank v. Thornton-Crosby Dev. Co., Inc., 310 S.C. 232, 235, 423 S.E.2d 114, 116 (1992). “In an action at law, on appeal of a case tried without a jury, the findings of fact of the judge will not be disturbed upon appeal unless found to be without evidence which reasonably supports the judge’s findings.” Townes Assoc. Ltd. v. City of Greenville, 266 S.C. 81, 86, 221 S.E.2d 773, 775 (1976).

The contract between CCSD and Skanska provided:

1.1.3 THE WORK

The term “Work” means the construction and services required by the Contract Documents, whether completed or partially completed, and includes all other labor, materials, equipment and services provided or to be provided by the Contractor to fulfill the Contractor’s obligations. The Work may constitute the whole or a part of the Project.

1.1.4 THE PROJECT

*477 The Project is the total construction of which the Work performed under the Contract Documents may be the whole or a part and which may include construction by other Contractors and by the Owner’s own forces including persons or entities under separate contracts not administered by the Construction Manager.

6.1.3 OWNER’S RIGHT TO PERFORM CONSTRUCTION WITH OWN FORCES AND TO AWARD OTHER CONTRACTS

The Owner reserves the right to perform construction or operations related to the Project with the Owner’s own forces, which include persons or entities under separate contracts not administered by the Construction Manager. The Owner further reserves the right to award other contracts in connection with other portions of the Project or other construction or operations on the site under Conditions of the Contract identical or substantially similar....

The subcontract between Skanska and Eldeco provided:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brandi Clarkson v. J. King Real Estate, LLC
Court of Appeals of South Carolina, 2025
Charleston CW, LLC v. Charleston Animal Society
Court of Appeals of South Carolina, 2025
Thorne Research, Inc. v. Davachi
D. South Carolina, 2024
Wadford v. Cooper
D. South Carolina, 2024
ARO-D Enterprises, LLC v. Tiger Enterprises
Court of Appeals of South Carolina, 2024
Paul Branco v. Hull Storey Retail
Supreme Court of South Carolina, 2023
John Harbin v. April Blair
Court of Appeals of South Carolina, 2022
Hall v. UBS Financial Services Inc.
Supreme Court of South Carolina, 2021
Bakala v. Krupa
D. South Carolina, 2021

Cite This Page — Counsel Stack

Bluebook (online)
642 S.E.2d 726, 372 S.C. 470, 2007 S.C. LEXIS 77, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eldeco-inc-v-charleston-county-school-district-sc-2007.