Phoenix Iron Co. v. United States

39 Ct. Cl. 526, 1904 U.S. Ct. Cl. LEXIS 26, 1903 WL 845
CourtUnited States Court of Claims
DecidedNovember 7, 1904
DocketNo. 22784
StatusPublished
Cited by5 cases

This text of 39 Ct. Cl. 526 (Phoenix Iron Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phoenix Iron Co. v. United States, 39 Ct. Cl. 526, 1904 U.S. Ct. Cl. LEXIS 26, 1903 WL 845 (cc 1904).

Opinion

WeldoN, J.,

delivered the opinion of the court:

The claimant is a corporation created under the laws of the State of Pennsylvania, and on the 26th of March, 1900, made a contract with the defendants for the steel framework for the new Government Printing Office in the city of Washington, which contract and specifications are made a part of the petition as Exhibit A.

By the terms of the contract the United States was required to furnish claimant with necessary drawings. The claimant was required to make its own shop drawings, and to furnish the engineer of the defendants with copies for comparison. Such detailed drawings were furnished by the United States at various times, the first on May 3, 1900, and the last on May 15,1901.

, By the terms of the contract the defendants were to pay certain specific prices for the different kinds and quality of material used in the construction of the building, and the material furnished and work done was subject to a rigid inspection by the engineer of the defendants and his decision as to quality and quantity was to be final. The work was to be commenced within sixty days after the notification of the approval of the contract and completed within six months from that time.

The contract was not completed within the time, which [537]*537ended on the 16th day of January, 1901, the time having been extended, but was delayed in its completion until about the 23d day of June, A. D. 1901.

It is expressly provided by the-terms of the agreement “ that time shall be considered as an essential feature of this contract, and that in case of failure upon the part of the party of the second part to complete this contract, as specified and agreed upon, that the party of the second part shall and will pay to the United States the sum of one hundred dollars ($100) for each and every day the said party of the second part shall delay in the completion of this contract, which said sum of one hundred dollars ($100) per day is hereby agreed upon, fixed, and determined by the parties hereto as 'the damages which the- said United States will suffer by such delay and default, and not by way of penalty.”

From time to time as the work progressed the defendants paid the claimant partial payments, and on June 23, 1901, the said payments amounted to $20,000 less than the contract price of the work which had been performed by claimant, and on about November 9, 1901, the defendants offered to pay the claimant the sum of $4,927.78 as a settlement in full for the balance due on the contract, claiming that liquidated damages and sundry sums to the amount of $15,070.22 should be deducted from the said $20,000 due on the contract. Included in said sum of $15,070.22 is an item of $473.55 about which there is.no controversy, the claimant conceding that such an a,mount should be allowed the defendants for work which should have been done by claimant.

. The controversy turns upon the question as to whether the delay in the performance of the work was due to the failure of the claimant, to the defendants, or to both.

The contract provides in substance that for any delay caused by the claimant it shall pay to the defendants the sum of $100 per day; the time is made an essential feature of the contract ^ that said sum of $100 is agreed upon, fixed, and determined by the parties as the damage the United States will snflier by such delay and default, and not as a penalty. In the preparation of this contract there seems to have been a special effort made to impress upon the failure of the claimant the consequences of measured liquidated damages [538]*538and not the mere limitation of damages in the form of a penalty.

It is provided in section 36 of the specifications :

“ It must be clearly understood that time is an essential feature of the contract herein contemplated, and that upon failure to complete the said contract within the time stipulated the contractor will be required to pay to the United States one hundred dollars per day for each day of delay (Sundays and legal holidays excepted) in the completion of the contract, the said payment to be made as liquidated damages, and not by way of penalty; and the party of the first part may deduct from any sum due or to become due the contractor any sums accruing for liquidated damages as herein stated.”

It is also provided—

“ Sec. 39. That.the amount of liquidated damages is determined by actual current expenditures for rent, which are made necessary by the lack of the new building and which will cease upon its completion. But no liquidated damages in' excess of $20,000 will be deducted.”

The courts are disposed to treat the sum named as a penalty, rather than the express agreement of the parties, as a settlement of the damages to which the party in fault is to be subjected to as a consequence of his failure. This tendency of the decisions is in order that the parties’ rights may be determined on the basis of actual damages rather than upon any arbitrary rule of forfeiture.

While courts are disposed to construe contracts of the kind in controversy as open to the question of real or actual damages, they do not hesitate to enforce the agreement when from the terms of the contract and the subject-matter of the litigation it is shown that the parties have agreed to the amount as a settlement of the real or actual damage.

“ If the intention, however, is clear to liquidate damages and the amount is either not greatly above or below the sum which would otherwise be recoverable; or, if above, was fixed specifically to cover contemplated consequential losses not provable under legal rules, and is not an unreasonable provision therefor, the sum fixed may be sustained as liquidated damages.” (Sutherland on Damages, vol. 1, p, 504.)

Many cases, some of which will be hereafter noted, have [539]*539been decided in this court involving the question as to whether the stipulation of the parties on the subject of damages was to be treated as a mere penalty or liquidated damages, precluding an inquiry into the question as to how much the party had suffered by the delinquency or default of the other party. One of the last and leading cases upon the subject of the stipulation of parties of-the sum to be paid for nonperformance of a covenant is the case of the Sun Printing and Publishing Association v. Moore (183 U. S., 643). As stated in the syllabi, it is said:

“ The naming of a stipulated sum to be paid for the nonperformance of a covenant is conclusive upon the parties in the absence of fraud or mutual mistake.
Parties may, in a case where the damages are of an uncertain nature, estimate and agree upon the measure of damages which may be sustained from a breach of the agreement.
The law does not limit an owner of property from affixing his own estimate of its value upon a sale thereof.”

It is true that in the above case it was not a question of penalty or liquidated damages, but the transaction is akin to a stipulation as to the damages in case of the nonperformance of an agreement within a specified time.

Where the parties have agreed upon an amount of damages by way of adjustment and have so expressed it the amount fixed will be treated as damages and not as penalty. (Gammon v. Howe, 14 Me., 250.)

In the case of

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arctic Contractors, Inc. v. State
564 P.2d 30 (Alaska Supreme Court, 1977)
Pacific Hardware & Steel Co. v. United States
49 Ct. Cl. 327 (Court of Claims, 1914)
Hughes Bros. & Bangs v. United States
45 Ct. Cl. 517 (Court of Claims, 1910)
Bethlehem Steel Co. v. United States
41 Ct. Cl. 19 (Court of Claims, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
39 Ct. Cl. 526, 1904 U.S. Ct. Cl. LEXIS 26, 1903 WL 845, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phoenix-iron-co-v-united-states-cc-1904.