Edgar & Thompson Foundry & Machine Works v. United States

34 Ct. Cl. 205, 1899 U.S. Ct. Cl. LEXIS 106, 1800 WL 2142
CourtUnited States Court of Claims
DecidedJanuary 23, 1899
DocketNo. 20809
StatusPublished
Cited by3 cases

This text of 34 Ct. Cl. 205 (Edgar & Thompson Foundry & Machine Works v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Edgar & Thompson Foundry & Machine Works v. United States, 34 Ct. Cl. 205, 1899 U.S. Ct. Cl. LEXIS 106, 1800 WL 2142 (cc 1899).

Opinion

Weldon, J.,

delivered the opinion of the court:

This suit is prosecuted to recover the balance alleged to be due the claimants on the contract set forth in the findings, and the only controversy in the case grows out of the deduction by the defendants of the sum of $3,250 from the consideration, because of the faillure of the claimants to perform the contract within the time limited.

The findings show that there was a delay of one hundred and thirty days, which being computed at the rate of $25 per day amounts to said sum.

The contract required the claimants “to furnish all the labor and material necessary to completely construct, erect at the workshops, take down after acceptance, and deliver at the localities and at the time prescribed the metal work” for a light-house.

The deduction by the defendants was made under the following provision of the agreement:

“And the said party of the first part further agrees to forfeit the sum of twenty-five dollars ($25) per day as liquidated dam[218]*218ages for eaeb and every day’s delay in completing either portion of the work embraced in the two deliveries after the said times, the amount thereof to be deducted from any sum which might otherwise be due the said party of. the first part in the hands of the light house engineer,” etc.

It is shown that the contract was prepared by the defendants in a printed form and signed by the parties in that condition, the amount of forfeit as liquidated damages being a part of the printed matter. It does not appear from the finding that previous to the execution of the instrument, the parties had any negotiations or understanding as to the damages which might or would accrue to the defendants in consequence of the failure of the claimants to perform the contract within the time limited, nor does it appear that the defendants suffered any appreciable damage in consequence of such failure.

The only question for us to consider is, whether the deduction on account of the delay as specified in the contract is to operate in law as a penalty, or liquidated damages as a measure of injury or compensation. If in the construction of the agreement it is to be regarded as a mere penalty, the deduction was improi>er; if as a measure of injury or compensation the deduction was proper, and the claimants have no right to recover.

The question presented by this record has been before this court in several cases growing out of contracts of a similar character, and in the decision- of those cases the court has followed the inclination of the law in determining that, unless it appears clearly to the contrary, the provision applicable to a failure to perform will be treated as a penalty and not as liquidated damages, and although the parties may agree to the sum as a measure of injury or compensation, yet if it is unreasonable and unconscionable it will not be enforced against the delinquent party.

In the case of Davis et al. (17 0. 01s. K.., 201) it is in substance said: In determining whether the amount named in a contract shall be taken as a penalty or liquidated damages courts are influenced largely by the reasonableness of the transaction, and are not restrained by the forms of the agreement, nor by the terms used by the parties, nor even by their manifest intent, which will be carried out so far only as it is right and reasonable.

This decision may be regarded as the limit in the direction of construing a provision as a penalty and not as liquidated [219]*219damages; and it is perhaps not necessary to go .to that limit in dealing with provisions of this contract and the conditions of this controversy.

In the case of Van Burén v. Diggs (11 Howard, 361), in passing on a question similar to the one in issue, the court says:

“The term forfeiture imports a penalty; it has no necessary or natural connection with the measure or degree of injury which may result from a breach of contract or from an imperfect performance. It implies an absolute infliction regardless of the nature and extent of the causes by which it is superin-duced.
“ Unless, therefore, it shall have been expressly adopted and declared by the parties to be a measure of injury or compensation it is never taken as such by courts of justice, who leave it to be enforced where this can be done in its real character, viz, that of a penalty. In a defense like that attempted by the defendant in the circuit court, upon the essential justness and fairness of the acts of the parties, a positive, immutable penalty could hardly be applied as a fair test of their merits.”

It is said in that case that the term forfeiture imports a penalty, and applying that rule of construction to the contract in this case, even though forfeiture is followed by the term “liquidated damages,” the penalty import of the agreement is not changed by the subsequent qualification. It must appear that the sum “was expressly adopted and declared by the parties to be a measure of injury or compensation.”

The consideration of the agreement is the sum of $7,500, and the deduction by the'defendants is $3,250 — a very large per cent upon the compensation which the claimants were to receive for the contract work, and although for some reason the claimants did not complete the work until four months after the expired term, the defendants in the end received and accepted from the claimants all they were entitled to under the contract.

As has been said the contract was prepared and reduced to a printed form at the time of signatures by the officers of. the defendants, and it does not appear that the clause relating to the forfeiture or damage was ever the subject of negotiation or consideration between the parties. It is a most familiar principle of law that the words of an agreement are taken most strongly against the party who prepared it, and if any liberality of construction is to be indulged it will be in-favor of the party who merely signs and not the party who signs and prepares the instrument for execution. (Garrison v. United States, [220]*2207 Wall. XT. S. R., 688; Chambers v. United States, 24 O. Ols. R., 387.)

Words of penalty and words of liquidation are used in tbe contract. Tbe party is “to forfeit tbe sum of $25 per day as liquidated damages.”

In tbe case of Bignall v. Gould (119 U. S. R., 495) tbe phraseology of tbe obligation sued on is very similar to tbe contract in this case. In tbat case it is nominated in the bond “ in the penal sum of $10,000 liquidated damages.” In tbe opinion of the court it is said “by the rules now established at law as well as in equity, the sum of $10,000 named in the bond is a penalty only, not liquidated damages.” As observed by Lord Tenter-den in asimilar case, “whoever framed this agreement does not appear to have had any very clear idea of the distinction between penalty and liquidated damages, for the sum in question is described in tbe same sentence as a penal sum and liquidated damages.” So in this case the word forfeiture is used in the same sentence with liquidated damages.

A case very much like the case at bar became the subject of official consideration in the office of the Attorney-General of the United States on a question referred to that Department by the Secretary of War. In reply to the inquiry of the Secretary the Attorney-General said:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sheridan-Kirk Contract Co. v. United States
52 Ct. Cl. 407 (Court of Claims, 1917)
Pacific Hardware & Steel Co. v. United States
48 Ct. Cl. 399 (Court of Claims, 1913)
Phoenix Iron Co. v. United States
39 Ct. Cl. 526 (Court of Claims, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
34 Ct. Cl. 205, 1899 U.S. Ct. Cl. LEXIS 106, 1800 WL 2142, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edgar-thompson-foundry-machine-works-v-united-states-cc-1899.