Haliday v. United States

33 Ct. Cl. 453, 1898 U.S. Ct. Cl. LEXIS 36, 1800 WL 2100
CourtUnited States Court of Claims
DecidedMay 31, 1898
DocketNo. 17652
StatusPublished
Cited by2 cases

This text of 33 Ct. Cl. 453 (Haliday v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Haliday v. United States, 33 Ct. Cl. 453, 1898 U.S. Ct. Cl. LEXIS 36, 1800 WL 2100 (cc 1898).

Opinion

WeldoN, J.,

delivered the opinion of the court:

This proceeding is based on certain contracts entered into by the claimants and defendants in March, April, May, and August, 1891 — the first on the 4th of March, the second on the 17th of April, the third on the 25th of May, and the fourth in August.

The contracts are in writing, except the last one, which is verbal. There is also a claim alleged in the eleventh paragraph of the petition, the substance of which is that the claimants sold to the firm of P. H. McLaughlin & Co., in June, 1891, cement amounting in value to the sum of $1,204.28, for the purpose of being used by them in the construction of the Naval Observatory under a contract with the defendants; that the firm had not paid for the cement; that before the use of the same by them they became insolvent and were declared by the defendants “failing contractors;” and that thereupon the defendants took possession of the cement, used the same with the knowledge that it had not been paid for, although the claimants demanded such cement. There are also claims for material used by defendants belonging to claimants while they were engaged in the work embraced in the contracts alleged in the petition.

[463]*463The first contract relates to a “ drill ball” at Fort Myer, wbicb is Exhibit A to the petition. Under that contract it is alleged that at the instance and request of the officers of defendants the claimants performed extra work amounting to the sum of $277. The second agreement, Exhibit B, relates to the building of an animal house in the Zoological Park at Washington. It is alleged that out of the compensation to be paid claimants for that building the defendants improperly deducted the sum of $450; and that in the performance of the contract they did extra work to the amount of $429, at the request and by the acquiescence of the officers of the defendants.

The third contract, dated May 25,1891, Exhibit G, relates to officers’ quarters at Fort Myer, and in connection with that contract it is alleged that in payment for the work the defendants improperly deducted the sum of $1,100; and it is further alleged that in the execution of said contract the claimants, at the instance and request of the defendants, performed extra work to the amount of $575.

It is alleged that in the performance of Contracts B and O in consequence of the incompetency and unskillfulness of the agents of the defendants in charge of the work, and unreasonable exactions on their part, the claimants were hindered and delayed in the execution of the work; but the findings do not show that the claimants were hindered and delayed as alleged, so that claim is, upon a question of fact, eliminated from .this controversy.

It is also alleged that the claimants, at the instance of the defendants, erected a flagstaff at Fort Myer, which was accepted and used by the defendants, and that the same was worth the sum of $131.

It is further alleged that in December, 1891, at the special instance and request of defendants, the petioners furnished them with 60 pouuds of sheet lead, worth the sum of $85.28; and also furnished defendants extra material not specified or required by said contracts.

The defendants deny that the alleged work upon the different contracts is extra; but that the same comes within the specifications of the agreement. They admit the retention of the sum of $450 under Contract B, but insist that it was properly retained because of the failure and delinquency of claimants; they also admit the retention of the sum of $1,100 under Contract O, but maintain that such retentioii was justified because [464]*464of tbe failure of the claimants to perform the work within the time agreed upon by an extension of the time limited in the agreement.

It is insisted by the defendants that the proper authority of the defendants did not order the extra work, if any was done; that no agreement in writing was made between the claimants and any officer or agent of the defendants for the performance of any extra or additional work, or for supplying any extra or additional material in and about the construction of the buildings specified in the agreements.

In this connection it is not necessary to refer in detail to the findings on the question of the right of the claimants to recover for extra labor, because of the provisions of the contracts relating to the requirements of an agreement in writing and the direction and sanction of the officer having the superior power of directing the execution and completion of work. The items for which we allow in the conclusion of law and judgment were at the request or requirement of the officers or agents in the immediate direction of the work, and some of them by the sanction of the superior power, under circumstances indicating the good faith of the subordinates. The additions were necessary, as it was thought by those agents; the Government has received the value and benefit of them, which combination of circumstances brings the claim for extras within the spirit if not wholly within the letter of the case of Ford (17 C. 01s. E., 60).

In the third finding is shown the performance of work which is alleged by the claimants as extra, and beyond the terms of the specifications in Contract A. Item 1 is for a change of plan which involved extra labor upon the part of claimants amounting to the sum of $92. The next item is granolithic pavement at south entrance. As to item 3, we think, on the facts, that it should be disallowed. In the fifth finding are the charges for extra work, Exhibit 13, relating to the animal house at the Zoological Park. The first item is for truss at east end of the building. There was no agreement that this was extra, but it was necessary in order to complete the work on that' part of the building. Other items are disposed of in the conclusion of law. As to some of the items claimed as extra, the proof is not sufficient to establish the fact of the work being done as alleged, or the appropriation of the material by the defendants.

[465]*465The eighth finding has reference to the claim for extra work and materials under Contract C for building the officers’ quarters.

The findings show in detail what was done by claimants and the value of each item, and as the conclusion of law indicates what items are allowed and what rejected it is not necessary to discuss them in detail.

The findings do not show how much, if any, damages resulted to the defendant's in consequence of the failure of the claimants to finish the building at the Zoological Park within the time specified iu the agreement; and if we construe the provision of the contract as a deduction of a penalty and not as a measure of injury or compensation, then the claimants are entitled to recover in this proceeding on that portion of the claim.

The clause of the contract is as follows: “In case of neglect or failure of the said parties of the first part to complete the above-mentioned house agreebly to and in conformity with the specifications and plans and the terms of this contract, on or before the date specified for the completion thereof, there shall be deducted the sum of $25 j>er day from the amount thereunder, in the discretion of the Secretary of the Smithsonian Institution, for each and every day that the completion and erection of said house, as agreed, may be delayed beyond the time specified in this contract.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Hardware & Steel Co. v. United States
48 Ct. Cl. 399 (Court of Claims, 1913)
Phoenix Iron Co. v. United States
39 Ct. Cl. 526 (Court of Claims, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
33 Ct. Cl. 453, 1898 U.S. Ct. Cl. LEXIS 36, 1800 WL 2100, Counsel Stack Legal Research, https://law.counselstack.com/opinion/haliday-v-united-states-cc-1898.