P.F. Manley v. Plasti-Line, Inc., a Tennessee Corporation

808 F.2d 468, 1987 U.S. App. LEXIS 763
CourtCourt of Appeals for the Sixth Circuit
DecidedJanuary 5, 1987
Docket86-1063
StatusPublished
Cited by17 cases

This text of 808 F.2d 468 (P.F. Manley v. Plasti-Line, Inc., a Tennessee Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P.F. Manley v. Plasti-Line, Inc., a Tennessee Corporation, 808 F.2d 468, 1987 U.S. App. LEXIS 763 (6th Cir. 1987).

Opinion

BAILEY BROWN, Senior Circuit Judge.

Plaintiff-Appellant P.F. Manley (plaintiff) appeals an order of the United States District Court for the Eastern District of Michigan which denied plaintiff’s summary judgment motion and granted a summary judgment motion of Defendant-Appellee Plasti-Line, Inc. (Plasti-Line) in a diversity action over the amount of compensation that Plasti-Line contractually owes to the plaintiff. Because questions of fact involving the parties’ contractual intent exist, we affirm the district court’s denial of the plaintiff’s summary judgment motion, re *470 verse its summary disposal of the ease and remand for further proceedings.

Plaintiff, having retired after spending fourteen years as the Financial Control Manager of the Dealership Identification Program at Ford Motor Company, contacted Plasti-Line in August of 1980 and suggested that his experience at Ford would be of great use to prospective bidders, such as Plasti-Line, in obtaining contracts for the installation and maintenance of signs for Ford dealerships around the country. Plasti-Line agreed and the two parties subsequently entered into a written letter agreement (consultant agreement) on October 10, 1980 for plaintiffs consultant services. Under this agreement, Plasti-Line was obligated to pay plaintiff $1,000 per month for six months in return for his efforts to secure a major Ford sign contract that was expected to be awarded by March 31, 1981. In addition, the parties agreed that the plaintiff would receive a commission of % of one percent on “[b]usiness covered under the contract [between Plasti-Line and Ford] contemplated by March 31, 1981....”

In March of 1981, Plasti-Line indeed obtained, with plaintiffs assistance, the Ford contract. 1 The present dispute has arisen over the amount of commission that the plaintiff should consequently receive under the commission clause in the consultant agreement. Plaintiff argues that the “contract contemplated by March 31, 1981” included extensions or renewals of the original Ford contract and thus his compensation under the commission clause should be calculated on a three-year period since the length of the Ford contract was, he contends, three years (two years with extensions totalling an extra year). Plasti-Line, on the other hand, argues that the commission clause did not encompass such subsequent contractual arrangements and the compensation to which the plaintiff was entitled was therefore limited to commission based on only a two-year period, the term of the initial Ford contract. 2

Plasti-Line stresses that although it continued to do business with Ford for one year after the two-year Ford contract had terminated, such business was not part of the Ford contract that plaintiff helped secure, but the result of its own negotiations, and thus plaintiff has no right to claim a commission from such business.

On September 11, 1984, plaintiff filed a complaint in district court alleging breach of the agreement between him and PlastiLine and seeking $21,145.00 as “unpaid commission.” The district court referred the matter to a magistrate who issued his Report and Recommendation on October 11, 1985. Two months before such issuance, both parties filed motions for summary judgment.

The magistrate determined that, under the commission clause (“[b]usiness covered under the contract contemplated by March 31,1981”), the plaintiff was entitled to compensation based on only two years since the “contract contemplated by March 31, 1981” was a two-year contract expiring on March 19, 1983. The inconsistent price terms, the magistrate explained, in the initial Ford contract and the subsequent agreements between Ford and Plasti-Line also indicated that the latter agreements were separate contracts and not mere extensions of the initial contract. The magistrate discounted the use of words such as “extension” and “amendment” in the contracts executed by Ford and Plasti-Line after March 19,1983 as “inartful drafting.” In addition, the magistrate emphasized the plaintiff’s knowledge that the typical length of contracts such as the Ford contract is two years, notwithstanding the plaintiff's testimony that such contracts could and sometimes do run for more than *471 two years upon renegotiation of the price terms. The magistrate then recommended that the plaintiffs motion for summary judgment be denied and Plasti-Line’s motion for the same be granted.

After a hearing before the district court regarding the plaintiffs objections to the magistrate’s report, the court, on December 13, 1985, entered an order adopting and approving the magistrate’s Report and Recommendation.

Simply stated, we believe that pivotal factual issues in the present case exist and thus the dispute cannot be properly resolved through summary disposition. Fed.R.Civ.P. 56(c) provides in part that summary judgment is appropriate when “there is no genuine issue as to any material fact....” See United States v. Articles of Device Consisting of Three Devices ... “Diapulse”, 527 F.2d 1008, 1011 (6th Cir.1976) (no determination of factual issues by summary judgment). In contract actions, summary judgment may be proper when the documents in question are undisputed and “reveal that there is no question as to intent.” 10A C. Wright, A. Miller & M. Kane, Federal Practice & Procedure § 2730.1 at 279-80 (2d ed. 1983). However, disputed questions of contractual intent are considered factual issues which are precluded from summary resolution. 3 In re Atlas Concrete Pipe, Inc., 668 F.2d 905, 910 (6th Cir.1982); Heheman v. E.W. Scripps Co., 661 F.2d 1115, 1128-29 (6th Cir.1981), cert. denied, 456 U.S. 991, 102 S.Ct. 2272, 73 L.Ed.2d 1286 (1982). See generally Central Jersey Dodge Truck Center, Inc. v. Sightseer Corp., 608 F.2d 1106, 1109 (6th Cir.1979) (Under Michigan law, the court’s “primary task in construing a contract is to give effect to the parties’ intention.”); Moulton v. Lobdell-Emery Manufacturing Co., 322 Mich. 307, 310, 33 N.W.2d 804, 806 (1948) (parties’ intent is critical in interpreting contract).

In the present case, the parties, in supporting their motions, and the magistrate, in resolving the dispute, looked beyond the express language of the consultant agreement, thus relying on parol evidence, principally the plaintiff’s deposition testimony, to vindicate their interpretations of the commission clause. 4 This reliance is patently incongruous with the district court’s grant of summary judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
808 F.2d 468, 1987 U.S. App. LEXIS 763, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pf-manley-v-plasti-line-inc-a-tennessee-corporation-ca6-1987.