Pettinaro Construction Co. v. Harry C. Partridge, Jr., & Sons, Inc.

408 A.2d 957, 1979 Del. Ch. LEXIS 338
CourtCourt of Chancery of Delaware
DecidedOctober 15, 1979
StatusPublished
Cited by35 cases

This text of 408 A.2d 957 (Pettinaro Construction Co. v. Harry C. Partridge, Jr., & Sons, Inc.) is published on Counsel Stack Legal Research, covering Court of Chancery of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pettinaro Construction Co. v. Harry C. Partridge, Jr., & Sons, Inc., 408 A.2d 957, 1979 Del. Ch. LEXIS 338 (Del. Ct. App. 1979).

Opinion

HARTNETT, Vice Chancellor.

This action was commenced to compel arbitration. For the reasons set forth, I find that the plaintiff’s claim is not ripe, at this time, for an Order compelling arbitration.

The Pettinaro Construction Co., Inc. (Pet-tinaro), and the defendant, Harry C. Partridge, Jr., and Sons, Inc., a subcontractor of plaintiff, entered into a contract incorporating by reference the arbitration provisions of a general contract then existing between Pettinaro and the State of Delaware for the construction of certain juvenile detention facilities. After completion of the work called for in the subcontract, defendant presented Pettinaro with a bill, only a portion of which Pettinaro admitted owing.

In June 1978, nine months after the dispute originally arose, Pettinaro submitted the dispute to the Architect on the project. Defendant refused to participate in the proceedings before the Architect, contending that submission of this matter to him was not the proper method for commencing the contractual arbitration process. As a result of defendant’s refusal to participate, the Architect concluded that a legal issue was involved precluding him from acting on the dispute. He therefore refused, in writing, to hold a hearing or entertain the submission of any evidence until such time as Pettinaro and defendant resolved their dispute concerning the proper forum for arbitration.

Pettinaro then filed this action pursuant to 10 Del.C., Ch. 57, which purports to be the Uniform Arbitration Act. Pettinaro seeks an order compelling defendant to arbitrate and for a determination of the proper contractual procedure for initiating the arbitration process. After inconclusive discovery demands, defendant filed this Motion For Summary Judgment raising three primary issues: (1) failure of Pettinaro to comply with 10 Del.C. § 5703(c), (2) failure of Pettinaro to comply with the arbitration procedure set out in the contract, and (3) Pettinaro’s waiver of a right to arbitration by delay.

The Delaware General Assembly, in adopting the Uniform Arbitration Act, made several inexplicable changes, some of which have led to ambiguities. The entire section 5703 is peculiar to Delaware and the language of § 5703(a) and (c) are hopelessly inconsistent. In deciding defendant’s motion for summary judgment, however, only the provisions of 10 Del.C. § 5703(a) need be considered.

I

The material provisions of the agreement between the parties provide:

Subcontract:
24. In case of dispute in regard to any articles of this Agreement, if arbitration is provided for in the General Contract between the Owner and Contractor, same shall apply with equal force to this Agreement. In the event that no arbitration is provided in the Contract between Contractor and Owner, then the decision of the Architect or Engineer shall be final in case of any dispute between Contractor and Subcontractor arising out of this Agreement.
*960 Everything required of the Contractor in this connection is applicable to the Subcontractor.
General Contract:
2.2.7 Claims, disputes and other matters in question between the Contractor and the Owner relating to the execution or progress of the Work or the interpretation of the Contract Documents shall be referred initially to the Architect for decision which he will render in writing within a reasonable time.
2.2.8 All interpretations and decisions of the Architect shall be consistent with the intent of the Contract Documents. In his capacity as interpreter and judge, he will exercise his best efforts to insure faithful performance by both the Owner and the Contractor and will not show partiality to either.
2.2.9 The Architect’s decisions in matters relating to artistic effect will be final if consistent with the intent of the Contract Documents.
2.2.10 Any claim, dispute or other matter that has been referred to the Architect, except those relating to artistic effect as provided in Subparagraph 2.2.9 and except any which have been waived by the making or acceptance of final payment as provided in Subparagraphs 9.7.5 and 9.7.6, shall be subject to arbitration upon the written demand of either party. However, no demand for arbitration of any such claim, dispute or other matter may be made until the earlier of:
2.2.10.1 The date on which the Architect has rendered his written decision, or
.2 the tenth day after the parties have presented their evidence to the Architect or have been given a reasonable opportunity to do so, if the Architect has not rendered his written decision by that date.
2.2.11 If a decision of the Architect is made in writing and states that it is final but subject to appeal, no demand for arbitration of a claim, dispute or other matter covered by such decision may be made later than thirty days after the date on which the party making the demand received the decision. The failure to demand arbitration within said thirty days’ period will result in the Architect’s decision becoming final and binding upon the Owner and the Contractor. If the Architect renders a decision after arbitration proceedings have been initiated, such decision may be entered as evidence but will not supersede any arbitration proceedings unless the decision is acceptable to the parties concerned.
7.10 Arbitration
7.10 All claims, disputes and other matters in question arising out of, or relating to, this Contract or the breach thereof, except as set forth in Subpara-graph 2.2.9 with respect to the Architect’s decisions on matters relating to artistic effect, and except for claims which have been waived by the making or acceptance of final payment as provided by Subpara-graphs 9.7.5 and 9.7.6, shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise. This agreement to arbitrate shall be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.
7.10.2 Notice of the demand for arbitration shall be filed in writing with the other party to the contract and with the American Arbitration Association, and a copy shall be filed with the Architect. The demand for arbitration shall be made within the time limits specified in Sub-paragraphs 2.2.10 and 2.2.11 where applicable, and in all cases within a reasonable time after the claim, dispute or other matter in question has arisen, and in no event shall it be made after the date when institution of legal or equitable proceedings based on such claim, dispute or other matter in question would be barred by the applicable statute of limitations.
Construction Industry Arbitration Rules:
*961

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alexander v. Lyft
Superior Court of Delaware, 2025
Buzzfeed Media Enterprises, Inc. v. Hannah Anderson
Court of Chancery of Delaware, 2024
Payne v. Samsung Electronics America, Inc.
Superior Court of Delaware, 2024
Michael Perik v. Student Resource Center, LLC
Court of Chancery of Delaware, 2024
Purvi Gandi-Kapoor v. Hone Capital LLC
Court of Chancery of Delaware, 2023
Ryan West v. Village Practice Mgmt. Co., LLC
Court of Chancery of Delaware, 2023
Asset Acceptance, LLC v. Newby
2014 Ark. 280 (Supreme Court of Arkansas, 2014)
DMS Properties-First, Inc. v. P.W. Scott Associates, Inc.
748 A.2d 389 (Supreme Court of Delaware, 2000)
Moran v. Carey Limousine, Inc.
737 A.2d 532 (District of Columbia Court of Appeals, 1999)
Elf Atochem North America, Inc. v. Jaffari
727 A.2d 286 (Supreme Court of Delaware, 1999)
SBC Interactive, Inc. v. Corporate Media Partners
714 A.2d 758 (Supreme Court of Delaware, 1998)
New Hampshire Insurance Co. v. State Farm Insurance Co.
643 A.2d 328 (Superior Court of Delaware, 1994)
Malekzadeh v. Wyshock
611 A.2d 18 (Court of Chancery of Delaware, 1992)
Tony Andreski, Inc v. Ski Brule, Inc
475 N.W.2d 469 (Michigan Court of Appeals, 1991)
Graham v. State Farm Mutual Automobile Insurance
565 A.2d 908 (Supreme Court of Delaware, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
408 A.2d 957, 1979 Del. Ch. LEXIS 338, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pettinaro-construction-co-v-harry-c-partridge-jr-sons-inc-delch-1979.