This text of 630 P.2d 646 (Penn v. Transportation Lease Hawaii, Ltd.) is published on Counsel Stack Legal Research, covering Hawaii Intermediate Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Penn v. Transportation Lease Hawaii, Ltd., 630 P.2d 646, 2 Haw. App. 272, 1981 Haw. App. LEXIS 216 (hawapp 1981).

Opinion

*273 OPINION OF THE COURT BY

BURNS, J.

This is an appeal by Plaintiff-Appellant Jay Dee Penn from an interlocutory permanent injunction requiring him to deliver to Defendant-Appellee Transportation Lease Hawaii, Ltd. (herein “Translease”), certain automobiles which he was leasing from Trans-lease. We affirm the lower court’s issuance of the injunction.

In 1973, Penn purchased 200 Datsuns. By agreement dated October 23, 1975, Penn and Translease agreed that Translease would purchase the Datsuns from Penn by assuming Penn’s $60,000 debt due THC Financial; that Penn would lease the Datsuns from Translease; and that Penn would lease an additional 100 automobiles from Translease. Penn’s performance of its obligations under the October 23, 1975 agreement was guaranteed by Dr. Edmund Wong.

After effectuation of the October 23, 1975 agreement, Penn leased an additional 36 automobiles from Translease. Dr. Wong did not guarantee Penn’s performance of its obligations with respect to these 36 automobiles.

Penn fell behind in his payments due, and on April 19, 1977, signed and delivered to Translease’s general manager a promissory note in favor of Translease in the principal amount of $77,506.09. In Penn’s view, the note satisfied his delinquency. In Translease’s view, the note was ineffective unless and until Dr. Wong guaranteed it, which he did not do.

Unsatisfied by the note, Translease filed suit against Penn for, inter alia, an order mandating the return of all of the leased automobiles.

Thereafter, the parties, who were each represented by counsel, entered into a “Settlement Agreement” dated June 22, 1977, which provided, inter alia:

3. The present $77,506.09 Promissory Note will be cancelled and replaced by two (2) separate Promissory Notes.***
a. One note. . . will contain the amount of the arrearages for the one hundred (100) Aloha Motors vehicles guaranteed by Wong under the letter agreement.***
b. The second . . . will cover the 36 vehicles which are in excess of those referred to in the letter agreement.***
*274 7. On execution of this agreement, the present litigation . . . will be dismissed without prejudice. However, Penn agrees that in the event of any material default under this agreement, he will not contest the immediate issuance of a temporary restraining order .. . requiring the return .. . of all . . . vehicles. ... It is understood . . . that. . . any failure to pay which exceeds ten (10) days shall be presumed to be a material default.
8. In the event of a default by Penn, Penn shall upon demand by [Translease] immediately surrender and deliver all remaining unsold vehicles ... to [Translease].***

Dr. Wong guaranteed payment of only the first note.

On June 27, 1977, five days after the Settlement Agreement, Penn commenced an action against Translease seeking a judgment declaring the April 19, 1977 note valid and the June 22, 1977 Settlement Agreement invalid because it lacked consideration, was the result of coercion and was made under duress.

Translease responded with a motion for a preliminary injunction requiring Penn to deliver all of the automobiles to Translease. After hearings on the motion, the trial court found Penn to be in default under the lease and issued a permanent injunction requiring Penn to deliver to Translease all automobiles covered in the June 22, 1977 Settlement Agreement not including the 200 Datsuns.

Penn appealed. Although Penn’s complaint was unresolved at the time the notice of appeal was filed and the trial court was not asked to and did not certify an interlocutory appeal, we have jurisdiction to consider the appeal of the injunction because it requires immediate execution of a command that property be delivered to the appellant’s adversary, and the losing party would be subjected to irreparable injury if appellate review had to wait the final outcome of the litigation. Forgay v. Conrad, 47 U.S. 201 (1848); 15 Wright & Miller, Federal Practice and Procedure, § 3910, at 453 et seq. (1976); Sturkie v. Han, 2 Haw. App. 140, 627 P.2d 296 (1981).

Penn first contends that the lower court erred in ruling as a matter of law that no matter what part Translease’s suit played in inducing Penn to enter into the June 22, 1977 Settlement Agreement, Penn could not use the pressure caused by the suit as a basis for the defense of duress. We agree with the lower court.

There arc differing views on what kind of duress creates a voidable contract. Professor Williston says that the alleged pressure *275 must be wrongful. In his view, a threat to bring a civil action or to resort to remedies available under a contract is not wrongful, but if a threat is made with a consciousness that there is no real right of action and the purpose is plainly coercive, a contract induced thereby is voidable. 13 Williston on Contracts, 3d Ed. § 1606 at 671, et seq. (1976).

According to the Restatement, the general rule is that where a party’s manifestation of assent is induced by an improper threat that leaves him no reasonable alternative, the contract is voidable by that party. Restatement (Second) Contracts § 317 (1977).

We hesitate to adopt a rule premised too much upon an examination of perceptions and motives. We prefer and therefore apply the Restatement’s rule with its added inquiry into the availability of a reasonable alternative.

Under this rule, Translease’s suit would probably have been improper if the April 19, 1977 note was effective. However, on the basis of substantial evidence, the lower court found that the note was not to be effective until guaranteed by Dr. Wong. Since Dr. Wong did not guarantee it, it was ineffective.

Further, even if the note was effective and the suit was improper, Penn had a reasonable alternative to succumbing and failed to take advantage of it. The pressure on him was caused by Translease’s request for an order mandating the return of all of the leased automobiles. Penn had the opportunity to oppose this request in court before the issuance of the order. The court then would have determined whether the pressure was proper or not and whether Translease would be allowed to continue it.

Penn next contends that the court erred in finding that he breached the June 22, 1977 Settlement Agreement. We perceive no merit in this contention. The trial court’s finding that Penn was “in material default in making the payments required by said agreement” is not clearly erroneous and conclusively establishes that Penn breached the agreement.

Finally, Penn contends that the trial court erred in issuing the injunction because there was no showing of irreparable harm. We hold that there was a sufficient showing of irreparable harm.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Friends of the Ha'ikū Stairs v. City and County of Honolulu
Hawaii Intermediate Court of Appeals, 2024
SHOPO v. HLRB
153 Haw. 431 (Hawaii Intermediate Court of Appeals, 2023)
Lambert v. Teisina.
319 P.3d 376 (Hawaii Supreme Court, 2014)
Stop Rail Now v. DeCosta
203 P.3d 658 (Hawaii Supreme Court, 2008)
KNG CORP. v. Kim
110 P.3d 397 (Hawaii Supreme Court, 2005)
Wahba, LLC v. Usrp (Don), LLC
106 P.3d 1109 (Hawaii Supreme Court, 2005)
Morgan v. Planning Department, County of Kauai
86 P.3d 982 (Hawaii Supreme Court, 2004)
Knauer v. Foote
63 P.3d 389 (Hawaii Supreme Court, 2003)
Ditto v. McCurdy
978 P.2d 783 (Hawaii Supreme Court, 1999)
Labayog v. Labayog
927 P.2d 420 (Hawaii Intermediate Court of Appeals, 1996)
Wong v. Takeuchi
924 P.2d 588 (Hawaii Intermediate Court of Appeals, 1996)
Ciesla v. Reddish
889 P.2d 702 (Hawaii Supreme Court, 1995)
Mitchell v. State, Department of Education
884 P.2d 368 (Hawaii Supreme Court, 1994)
Black v. Black
728 P.2d 1303 (Hawaii Intermediate Court of Appeals, 1986)
TBS Pacific, Inc. v. Tamura
686 P.2d 37 (Hawaii Intermediate Court of Appeals, 1984)
Hoge v. Kane
663 P.2d 645 (Hawaii Intermediate Court of Appeals, 1983)
Standard Finance Co., Ltd. v. Ellis
657 P.2d 1056 (Hawaii Intermediate Court of Appeals, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
630 P.2d 646, 2 Haw. App. 272, 1981 Haw. App. LEXIS 216, Counsel Stack Legal Research, https://law.counselstack.com/opinion/penn-v-transportation-lease-hawaii-ltd-hawapp-1981.