Geothermal Resource Group, Inc. v. Puna Geothermal Venture

216 F. Supp. 2d 1133, 2001 U.S. Dist. LEXIS 24411, 2001 WL 1940272
CourtDistrict Court, D. Hawaii
DecidedSeptember 20, 2001
DocketCiv. 91000330ACK/KSC
StatusPublished
Cited by2 cases

This text of 216 F. Supp. 2d 1133 (Geothermal Resource Group, Inc. v. Puna Geothermal Venture) is published on Counsel Stack Legal Research, covering District Court, D. Hawaii primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Geothermal Resource Group, Inc. v. Puna Geothermal Venture, 216 F. Supp. 2d 1133, 2001 U.S. Dist. LEXIS 24411, 2001 WL 1940272 (D. Haw. 2001).

Opinion

ORDER DENYING DEFENDANT’S MOTION TO DISMISS

KAY, District Judge.

BACKGROUND

This lawsuit involves a contract dispute between Geothermal Resource Group, Inc. (“Plaintiff’) and Puna Geothermal Venture (“Defendant”). Since the inception of Defendant’s geothermal power plant in 1993 until this dispute arose in October of 1999, the parties have enjoyed a relatively harmonious working relationship. 1 See Complaint at ¶ 5,17.

The instant dispute arises from the following alleged circumstances. In January of 1999, Plaintiff orally agreed to provide “consulting drilling engineering services” in conjunction with the reworking of two injection wells and the drilling of a new production well at Defendant’s geothermal power plant (“resource enhancement project”). See id. at ¶ 16. Approximately seven months into the project, in September of 1999, Defendants coerced Plaintiff into signing a written contract 2 (“Master Work Agreement”). See id. at ¶ 14. One month after Plaintiff signed the contract, in October of 1999, Defendants stopped paying for Plaintiffs services. See id. at ¶ 17. After a series of delays and incurring cost in excess of the original budget, Plaintiff completed work on the resource enhancement project in January of 2000. See id.

On April 12, 2001, Plaintiff filed a Complaint in the Third Circuit Court of the State of Hawaii that set forth the following claims: (1) breach of the original consulting agreement, (2) breach of the master work agreement, (3) promissory estoppel, and (4) unjust enrichment. On June 20, 2001 Defendant removed the action to federal court. 3 On May 21, 2001 *1135 Defendant filed a Motion to Dismiss pursuant to Federal Rules of Civil Procedure (“F.R.C.P.”) Rule 12(b)(6) arguing that Hawaii Revised Statutes (“H.R.S.”) Section 444, governing contractors, precludes Plaintiff from seeking compensation for work completed on the resource enhancement project. Plaintiff filed an Opposition on August 28, 2001 to which Defendant replied on September 6, 2001. The Court heard oral argument on September 17, 2001.

STANDARD

I. MOTION TO DISMISS

Under Rule 12(b)(6), in 'determining whether a motion to dismiss for failure to state a claim upon which relief can be granted, this Court must accept as true the plaintiffs allegations contained in the complaint and view them in a light most favorable to the plaintiff. Scheuer v. Rhodes, 416 U.S. 282, 236, 94 S.Ct. 1683, 1686, 40 L.Ed.2d 90 (1974); Wileman Bros. & Elliott, Inc. v. Giannini 909 F.2d 332, 334 (9th Cir.1990); Shah v. County of Los Angeles, 797 F.2d 743, 745 (9th Cir.1986). Thus, the complaint must stand unless it appears beyond doubt that the plaintiff has alleged no facts that would entitle him to relief. Conley v. Gibson, 355 U.S. 41, 45-46, 78 S.Ct. 99, 101-02, 2 L.Ed.2d 80 (1957); Balistreri v. Pacifica Police Dept., 901 F.2d 696, 699 (9th Cir.1988). A complaint may be dismissed as a matter of law for two reasons: (1) lack of a cognizable legal theory or (2) insufficient facts under a cognizable legal theory. Balistreri, 901 F.2d at 699; Robertson v. Dean Witter Reynolds, Inc., 749 F.2d 530, 533-34 (9th Cir.1984).

In essence, as the Ninth Circuit has stated, “[t]he issue is not whether a plaintiffs success on the merits is likely but rather whether the claimant is entitled to proceed beyond the threshold in attempting to establish his claims.” De La Cruz v. Tormey, 582 F.2d 45, 48 (9th Cir.), cert. denied, 441 U.S. 965, 99 S.Ct. 2416, 60 L.Ed.2d 1072 (1979). The Court must determine whether or not it appears to a certainty under existing law that no relief can be granted under any set of facts that might be proved in support of plaintiffs’ claims. Id.

A motion under Rule 12(b)(6) should also be granted if an affirmative defense or other bar to relief is apparent from the face of the Complaint, such as lack of jurisdiction or the statute of limitations. 2A J. Moore, W. Taggart & J. Wicker, Moore’s Federal Practice, ¶ 12.07 at 12-68 to 12-69 (2d ed.1991 & supp. 1191-92) (citing Imbler v. Pachtman, 424 U.S. 409, 96 S.Ct. 984, 47 L.Ed.2d 128 (1976)) (emphasis added).

DISCUSSION

Defendant asserts that H.R.S. Section 444 bars Plaintiff from pursuing this lawsuit because Plaintiff was an un-licensed “contractor” with respect to the resource enhancement project. Plaintiff does not allege having held any type of license. Instead, Plaintiff contends that it acted as a “professional engineer” such that H.R.S. Section 464 governs and Section 444 is inapplicable.

The critical distinction between Section 444 (Contractors) and Section 464 (Profes *1136 sional Engineers) is that Section 444 includes a provision prohibiting un-licensed contractors from initiating a civil action to recover for work done. See Haw.Rev.Stat. § 444-22 (1998). 4 Section 464 does not include a like provision and arguably 5 would not preclude an un-licensed professional engineer from enforcing a valid contract. C.f. Wilson v. Kealakekua Ranch, Ltd., 57 Haw. 124, 132, 551 P.2d 525 (1976). Moreover, Section 444 specifically exempts “professional engineers] acting solely within [their] professional capacity.” Thus, the issues presented to the Court are (1) whether, based on the pleadings, 6 Plaintiffs involvement in the resource enhancement project was that of a “contractor,” as defined by H.R.S. Section 444, or (2) whether, and to what extent, his involvement was that of a “professional engineer” as defined by H.R.S. Section 464.

A. H.R.S. Sections 444 and 464

H.R.S. Section 444-1 defines “contractor” as:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
216 F. Supp. 2d 1133, 2001 U.S. Dist. LEXIS 24411, 2001 WL 1940272, Counsel Stack Legal Research, https://law.counselstack.com/opinion/geothermal-resource-group-inc-v-puna-geothermal-venture-hid-2001.