Penn Towne Builders, Inc. v. United States

31 Cont. Cas. Fed. 72,254, 4 Cl. Ct. 677, 1984 U.S. Claims LEXIS 1473
CourtUnited States Court of Claims
DecidedMarch 6, 1984
DocketNo. 580-80 C
StatusPublished
Cited by15 cases

This text of 31 Cont. Cas. Fed. 72,254 (Penn Towne Builders, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Penn Towne Builders, Inc. v. United States, 31 Cont. Cas. Fed. 72,254, 4 Cl. Ct. 677, 1984 U.S. Claims LEXIS 1473 (cc 1984).

Opinion

OPINION

SETO, Judge:

This action comes before the court on defendant’s motion for summary judgment. Plaintiff, Penn Towne Builders, Inc., (“Penn Towne”), a corporation engaged in general contracting work in New Jersey, seeks a judgment against the United States for $70,000 plus interest as payment for construction work assertedly performed on a housing project financed pursuant to § 236 of the National Housing Act, 12 U.S.C. § 1715z-l. Plaintiff avers that because its contract with the project owner, Union American M.E. Apartments, Inc., (“Union American”) was guaranteed by the Secretary of Housing and Urban Development (“HUD”), there exists a contract implied in fact between plaintiff and the United States. Alternatively, plaintiff contends that recovery is proper under unjust enrichment and third-party beneficiary theories.

Defendant, on the other hand, asserts that no implied-in-fact contract existed with Penn Towne because the Government was not a party to the construction contract. Defendant contends moreover that governmental oversight alone, no matter how pervasive, cannot obviate sovereign immunity. Finally, defendant maintains that recovery under purely equitable doctrines is beyond the jurisdiction of this court.

After carefully considering the briefs of the parties and the relevant administrative record, this court grants defendant’s motion for summary judgment, and dismisses plaintiff’s complaint.

FACTS

On May 11,1972, plaintiff, Penn Towne, a general contractor, entered into a cost-plus-fixed-fee construction contract with Union American to perform certain construction work on the Harmony House Apartments project in Camden, New Jersey.1 The project was being constructed under the provisions of § 236 of the National Housing Act of 1968.2 In accordance therewith, Penn Towne executed a performance bond with Summit Insurance Company of New York (“Summit”) to ensure its contractual performance. Summit, as required, obtained a “Certificate of Authority” from the United States Department of Treasury in order to qualify as an acceptable surety. A “Building Loan Agreement” and a “Regulatory Agreement for Nonprofit Mortgagors” were executed contemporaneously with the construction contract.3

[679]*679The construction contract signed on May 11 by Penn Towne and Union American, the general contractor and the project owner, respectively, called for a construction period of approximately eight months, commencing June 22, 1972, with completion by February 18,1973. Payments were to be made on a cost-plus-fixed-fee basis, not to exceed $910,000; this, however, was later modified by an “incentive payment” rider that established a bonus for early completion. The building loan agreement, also entered into on May 11, 1972, was executed by the project owner, Union American, and Associated-East Mortgage Company (“Associated-East”). The agreement defined the terms and conditions governing the advance and issuance of financing during construction which the mortgage company would provide to Union American, the project owner.4 The financing was secured by a mortgage on the project. The Regulatory Agreement for nonprofit mortgagors regulated the owner’s use of the loan funds, prospective rental rates, and other obligations and limitations upon the project. In return for these restrictions, the Federal Housing Commission was obligated to completely insure the mortgage note, or to consent to the assignment of the mortgaged property. Through this arrangement, Union American was able to charge lower rental fees than if financing were procured at prevailing market rates because mortgage payments were subsidized in part by HUD. Plaintiff was not a signatory to either the building loan agreement or the regulatory agreement.

Payments to Penn Towne for work completed were explicitly covered in the construction contract with Union American. As work was completed, disbursements of construction funds were to be made pursuant to both the building loan agreement5 and the construction contract6 at monthly intervals until the project had been certified substantially complete by the FHA Chief Underwriter. Any amounts due at completion, as well as any amounts in “holdback,” would be paid once the construction was certified as complete. Therefore, the construction contract, the Building Loan Agreement, and the Regulatory Agreement constituted the contractual framework within which the parties operated.

Although the parties are not in agreement as to the nature of the delay, it is clear that the project had not been completed on schedule by February 18, 1973. As Penn Towne’s work progressed, albeit behind schedule, Summit, Penn Towne’s surety on the performance bond, solicited status information from HUD on April 4, 1973, regarding why the Harmony House project was two months behind schedule. HUD advised Summit a week later that the project was only seventy-two percent complete, but good progress was being made and no known liens had been filed. Despite HUD’s optimism, the project eventually stalled. Recognizing a growing problem, [680]*680the mortgage company elected to assign its mortgage to HUD on October 9,1973. The assignment became effective on November 19,1973.7

On March 13, 1974, more than a year after the project was to have been completed, HUD, as the assignee of the mortgage and pursuant to its authority under the Building Loan Agreement, advised the bonding company Summit of its intention to terminate the construction contract between Union American and Penn Towne, and that the Government would look to Summit for completion of the project. Finally, on April 19,1974, approximately fourteen months after Penn Towne was obligated to complete the project, HUD terminated the contract between Union American and Penn Towne in accordance with paragraph nine of the Building Loan Agreement. On the same day, Union American entered into a construction contract with System Construction, Inc., to complete the project at a cost of $145,000. Plaintiff subsequently initiated this suit to recover sums allegedly earned prior to the April 19,1974, termination. The Superintendent of Insurance of the State of New York, as the duly-named liquidator of Summit, has intervened, claiming entitlement to any sums awarded herein to plaintiff.

DISCUSSION

Defendant’s motion for summary judgment sets forth four reasons why Penn Towne is not entitled to recover: (1) absence of a waiver of sovereign immunity under the above circumstances; (2) absence of any contract or circumstances under which plaintiff could claim status as a third-party beneficiary; (3) lack of privity between the Government and plaintiff; and (4) absence of an implied-in-fact contract between the Government and plaintiff. In response, plaintiff asserts that it is entitled to recover: (1) under federal common law principles; (2) because the Government has been unjustly enriched by receiving construction services for which it has not paid; (3) because plaintiff is a third-party beneficiary of the various agreements and contracts entered into by the other parties; or (4) that there did indeed exist an implied-in-fact contract between plaintiff and the Government. We deal with plaintiff’s theories seriatim

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Laudes Corp. v. United States
86 Fed. Cl. 152 (Federal Claims, 2009)
Maniere v. United States
31 Fed. Cl. 410 (Federal Claims, 1994)
Schuerman v. United States
30 Fed. Cl. 420 (Federal Claims, 1994)
Blaze Construction, Inc. v. United States
27 Fed. Cl. 646 (Federal Claims, 1993)
Eubanks v. United States
25 Cl. Ct. 131 (Court of Claims, 1992)
Spalding & Son, Inc. v. United States
37 Cont. Cas. Fed. 76,174 (Court of Claims, 1991)
H. Landau & Co. v. United States
35 Cont. Cas. Fed. 75,599 (Court of Claims, 1988)
Etchey v. United States
15 Cl. Ct. 152 (Court of Claims, 1988)
Pasco Enterprises v. United States
13 Cl. Ct. 302 (Court of Claims, 1987)
Erikson v. United States
12 Cl. Ct. 754 (Court of Claims, 1987)
DeRoo v. United States
12 Cl. Ct. 356 (Court of Claims, 1987)
Glopak Corp. v. United States
34 Cont. Cas. Fed. 75,248 (Court of Claims, 1987)
Korea Development Corp. v. United States
9 Cl. Ct. 167 (Court of Claims, 1985)
In Re All Asbestos Cases
603 F. Supp. 599 (D. Hawaii, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
31 Cont. Cas. Fed. 72,254, 4 Cl. Ct. 677, 1984 U.S. Claims LEXIS 1473, Counsel Stack Legal Research, https://law.counselstack.com/opinion/penn-towne-builders-inc-v-united-states-cc-1984.