Pearl River Basin Land & Development Co. v. State Ex Rel. Governor's Office of Homeland Security & Emergency Preparedness

29 So. 3d 589, 2009 La.App. 1 Cir. 0084, 2009 La. App. LEXIS 1778, 2009 WL 3446337
CourtLouisiana Court of Appeal
DecidedOctober 27, 2009
Docket2009 CA 0084
StatusPublished
Cited by25 cases

This text of 29 So. 3d 589 (Pearl River Basin Land & Development Co. v. State Ex Rel. Governor's Office of Homeland Security & Emergency Preparedness) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pearl River Basin Land & Development Co. v. State Ex Rel. Governor's Office of Homeland Security & Emergency Preparedness, 29 So. 3d 589, 2009 La.App. 1 Cir. 0084, 2009 La. App. LEXIS 1778, 2009 WL 3446337 (La. Ct. App. 2009).

Opinion

McClendon, j.

12PIaintiff seeks review of a district court judgment granting an exception of no cause of action that dismissed Washington Parish from plaintiffs suit. For the following reasons, we affirm.

FACTUAL AND PROCEDURAL HISTORY

On September 12, 2005, Washington Parish (the Parish) issued a declaration of emergency following Hurricane Katrina. Because of the nature of the disaster, the Parish was in immediate need of debris dump sites. The Parish Council’s President, Toye Taylor, and its Director of Pub-lie Works, Troy Barber, met with representatives of Pearl River Basin Land and Development Company, L.L.C. (Pearl River) and IED, Inc. (IED) in early September to discuss five potential dump sites within the Parish.

On September 16, 2005, IED executed a Contract for Debris Management Services with the Parish for the removal of storm debris within the Parish’s jurisdiction. Pursuant to Paragraph 5.11 of the agreement, IED was required, to the extent possible, to give priority and utilize the resources of subcontractors within the Parish. IED subsequently executed contracts of lease with Pearl River for three Bogalusa disposal sites. Pearl River, which did not own the three disposal sites, sought to lease the sites from individual landowners.

On September 16, 2005, the Parish also entered into a contract with Shaw Environmental, Inc. (Shaw) regarding project management and professional services in relation to the debris removal. Pearl River asserts that Shaw’s duties under said contract included providing management support to IED and ensuring that guidelines were being followed to procure FEMA funding.

Pearl River alleges that on September 26, 2005, it “hand-delivered” a confirmation letter to Kenny Gatewood, the Parish’s Assistant District Attorney who was preparing the three leases, and to Eddie Dor-sett, a Shaw representative, for review, compliance, and approval of funding. Pearl River alleges that during the week of September 26, 2005, negotiations were conducted among the parties, including the Parish, IED, Shaw, and Pearl River, wherein an agreement was reached with regard to the amount of acreage that would be leased for each of the three sites as well as the |3term and amount paid per *592 acre. Peaii River specifically alleges that during these negotiations, IED informed it that twenty to twenty-five acre sites were needed and that Pearl River should expect a $700.00 to $1,500.00 per acre payment for debris disposal over a term of six months. Thereafter, Pearl River contracted with the three landowners to provide the sites.

Pearl River asserts that on September 28, 2005, Dorsett contacted Ronnie G. Pen-ton, Pearl River’s sole representative, and requested that the leases be signed immediately. Because Penton was out of town, Pearl River forwarded Dorsett a blank lease which bore Pearl River’s signature. Pearl River asserts that Penton instructed Dorsett to complete the terms of the three leases in accord with the negotiations that occurred during the week of September 26, 2005. Pearl River alleges that it was assured that IED would pay the leases and that reimbursement would be sought from FEMA in accordance with FEMA guidelines. However, Pearl River asserts that Dorsett lowered the total acreage to be utilized, paid only $625.00 per acre, and reduced the six-month term to three months.

On August 28, 2007, Pearl River filed suit against the State of Louisiana through the Governor’s Office of Homeland Security and Emergency Preparedness (the State), the Parish, IED, and Shaw. Pearl River alleges that the Parish improperly monitored, selected, and screened contractors in violation of state and federal laws. Pearl River alleges that as a result of the breach of these duties, it spent thousands of dollars “out-of-pocket” and had not been properly reimbursed for the preparation of the sites, roads, and payments of said leases to the landowners for use of the land.

In response, on March 6, 2008, the Parish filed a peremptory exception raising objections of no cause of action and prescription, asserting that it had no contractual privity with Pearl River and that Pearl River’s actions were based in tort and subject to a prescriptive period of one year. On March 10, 2008, Pearl River filed a supplemental and amending petition. On July 28, 2008, the district court found that Pearl River’s action was based on contract, sustained the Parish’s exception raising the objection of no cause of action, and dismissed the Parish from the suit. Pearl River has filed the instant appeal contending that the trial court erred in sustaining the exception raising [4the objection of no cause of action. Pearl River also contends that the trial court erred in dismissing its suit without allowing it to amend its petition.

DISCUSSION

The exception of no cause of action is triable on the face of the pleadings, and for purposes of resolving the issues raised by the exception, the well-pleaded facts in the petition are accepted as true in order to determine whether the law? affords a remedy on the facts alleged in the petition. Scheffler v. Adams and Reese, LLP, 06-1774, p. 5 (La.2/22/07), 950 So.2d 641, 646. Because the exception of no cause of action raises a question of law and the trial court’s decision is based solely on the sufficiency of the petition, review of the trial court’s ruling on an exception of no cause of action is de novo. Id. The pertinent question is whether, in the light most favorable to the plaintiff, and with every doubt resolved in the plaintiffs favor, the petition states any valid cause of action for relief. Id.

Pearl River contends that it has stated a cause of action against the Parish for breach of contract. However, no action for breach of contract may lie in the absence of privity of contract between the parties. Long v. Jeb Breithaupt Design *593 Build Inc., 44,002, p. 19 (La.App. 2 Cir. 2/25/09), 4 So.3d 930, 941-42. Although Pearl River asserts that the Parish required its services to accomplish the debris removal, Pearl River does not allege that it had a contract with the Parish. Rather, Pearl River alleges that the Parish entered into contracts only with Shaw and IED. The fact that Pearl River may have a contract with IED and/or Shaw, who in turn, have separate contracts with the Parish, does not create a contract or privity of contract between Pearl River and the Parish. See Louisiana Paving Company, Inc. v. State Through Dept. of Highways, 372 So.2d 245, 250 (La.App. 1 Cir.1979) (Although there is contractual privity between the owner and general contractor and between the general contractor and subcontractor, “[w]e recognize and adhere to the general rule that a subcontractor having no contractual relationship with an owner has no cause of action in contract against the owner.”)

We also note that the Parish’s mere presence at the meetings between IED and Pearl River is not sufficient to make the Parish a party to any contract with Pearl River, | ^specially given that Pearl River alleges that IED informed it of the amount of acreage required, the expected amount of the payments per acre, and the expected term.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harris v. Breaud
243 So. 3d 572 (Louisiana Court of Appeal, 2018)
Landry v. Base Camp Management, LLC
206 So. 3d 921 (Louisiana Court of Appeal, 2016)
Denham Homes, LLC v. Teche Federal Bank
182 So. 3d 108 (Louisiana Court of Appeal, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
29 So. 3d 589, 2009 La.App. 1 Cir. 0084, 2009 La. App. LEXIS 1778, 2009 WL 3446337, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pearl-river-basin-land-development-co-v-state-ex-rel-governors-office-lactapp-2009.